Procurements: Pumping station construction work
>20 archived procurements
Pumping station construction work have been procured by organizations such as Irish Water, Ervia, and Cork County Council.
Historically, suppliers within this area have been Ward & Burke Construction Ltd, Electrical and Pump Services Ltd, GMC Utilities Group Ltd, Ward and Burke Construction Ltd, BAM Civil Ltd, BSG Group, Celtic Anglian Water Ltd. TES Technologies Ltd Northstone (NI) Ltd T/A Farrans Construction, Coffey Construction (I) Ltd, David Walsh Civil Engineering Ltd, and Efacec Engenharia E Sistemas, SA.
- Construction work (>20 new procurements)
- Works for complete or part construction and civil engineering work (>20)
- Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork (16)
- Ancillary works for pipelines and cables (8)
- Ancillary works for water pipelines (4)
- Works related to water-distribution pipelines (2)
- Water-main refurbishment construction work (1)
- Pumping station construction work ⬅️
- Construction work for water towers
- Construction work of elevated tanks for drinking water
Recent procurements of pumping station construction work in Ireland
2024-06-25
24/026 Contract for the Provision of Early Contractor Involvement Major Process and MEICA Works (incorporating... (Uisce Éireann)
24/026 Contract for the Provision of Early Contractor Involvement Major Process and MEICA Works (incorporating associated Civil Works) to Uisce Éireann View the procurement »
24/026 Contract for the Provision of Early Contractor Involvement Major Process and MEICA Works (incorporating associated Civil Works) to Uisce Éireann View the procurement »
2024-05-28
Multiple Framework Agreement for Works Contracts for Projects with a value not exceeding €15million established on... (Laois and Offaly Education and Training Board (Offaly))
The development of Groundworks to facilitate the future development of a Modern Methods of Construction (MMC) Demonstration Park, consisting of the construction of access roads, paths, set-down areas, foundation pads, storm water storage swales, service connections, public lighting, and all associated site development. These will also include the upgrade/ replacement of the existing foul water treatment plant. The foundation pads are to be oversized and constructed to provide a designed formation level … View the procurement »
The development of Groundworks to facilitate the future development of a Modern Methods of Construction (MMC) Demonstration Park, consisting of the construction of access roads, paths, set-down areas, foundation pads, storm water storage swales, service connections, public lighting, and all associated site development. These will also include the upgrade/ replacement of the existing foul water treatment plant. The foundation pads are to be oversized and constructed to provide a designed formation level … View the procurement »
2024-03-28
Limerick City and County Council - Lough Gur Wastewater Storage Holding Tank and Associated Works (Limerick City and County Council_103432)
Limerick City and County Council, to invite you to submit a tender for the cost to complete the installation of wastewater storage holding tanks, mini pump station, rising main stand off discharge manhole and all associated connection works and reinstatement as indicated on the drawings attached. View the procurement »
Limerick City and County Council, to invite you to submit a tender for the cost to complete the installation of wastewater storage holding tanks, mini pump station, rising main stand off discharge manhole and all associated connection works and reinstatement as indicated on the drawings attached. View the procurement »
2024-01-18
Donegal County Council request a tender for a Mechanical and Electrical Services Contractor for the Upgrade and... (Donegal County Council_1193)
Donegal County Council request for tender for a Mechanical and Electrical Services Contractor for the Upgrade and refurbishment of Six Group Water Scheme Pumping Stations in Donegal. The project will require the replacement of pumps, electrical panels, re-wiring and internal pipework. Further details are provided in the scope of works documents. View the procurement »
Donegal County Council request for tender for a Mechanical and Electrical Services Contractor for the Upgrade and refurbishment of Six Group Water Scheme Pumping Stations in Donegal. The project will require the replacement of pumps, electrical panels, re-wiring and internal pipework. Further details are provided in the scope of works documents. View the procurement »
2022-08-05
Stormwater Pump Stations - Athlone Flood Alleviation Scheme (Office of Public Works (OPW))
Selection, supply, installation and commissioning of pumping stations in accordance with the specification as part of the Athlone Flood Alleviation Scheme. View the procurement »
Selection, supply, installation and commissioning of pumping stations in accordance with the specification as part of the Athlone Flood Alleviation Scheme. View the procurement »
2022-02-23
22/003- Water and Wastewater Network Services and Works (WNSW) Sub – contractor List (Irish Water)
Irish Water wishes to appoint a number of Regional Services and Works Contractors (Regional Contractors) to assist in achieving its network improvement targets through targeted capital works. It is expected that these Regional Contractors will require large numbers of sub-contractors to supplement their own resources. The purpose of this Expression of Interest (EOI) is to establish a list of sub-contractors that these Regional Contractors may choose to appoint over the duration of the project. This … View the procurement »
Irish Water wishes to appoint a number of Regional Services and Works Contractors (Regional Contractors) to assist in achieving its network improvement targets through targeted capital works. It is expected that these Regional Contractors will require large numbers of sub-contractors to supplement their own resources. The purpose of this Expression of Interest (EOI) is to establish a list of sub-contractors that these Regional Contractors may choose to appoint over the duration of the project. This … View the procurement »
2021-12-13
Supply of Mobile Diesel Powered Pumps for the Springfield Flood Relief Scheme (Office of Public Works (OPW))
Supply of 2 No. 400mm diameter (16 inch) Mobile Diesel Powered Pumps & Accessories - Springfield Flood Relief Scheme View the procurement »
Supply of 2 No. 400mm diameter (16 inch) Mobile Diesel Powered Pumps & Accessories - Springfield Flood Relief Scheme View the procurement »
2021-09-09
Multi Supplier Framework for the Provision of Major Process and MEICA Works (incorporating associated Civil Works)... (Irish Water)
IW intends to undertake a competitive tendering process to establish a national Multi-Supplier Framework Agreement for the provision of design, construction and operation of major process and MEICA works (incorporating associated civil engineering works and all required works and services). Suppliers will be required to provide a solution to: Design, build and/or operation of water abstraction, treatment, sludge treatment and handling, water distribution systems, on site renewable energy generation and … View the procurement »
IW intends to undertake a competitive tendering process to establish a national Multi-Supplier Framework Agreement for the provision of design, construction and operation of major process and MEICA works (incorporating associated civil engineering works and all required works and services). Suppliers will be required to provide a solution to: Design, build and/or operation of water abstraction, treatment, sludge treatment and handling, water distribution systems, on site renewable energy generation and … View the procurement »
2021-07-28
Multi Supplier Framework for the Provision of Water and Wastewater Network Services and Works to Irish Water (Irish Water)
Irish Water intends to undertake a competitive tendering process, the objective of which is to establish a Multi-supplier Framework Agreement for the provision of Water and Wastewater Network Services and Works nationwide. A new contract delivery mechanism is required to facilitate the delivery of the Irish Water’s Network Capital Programmes such as: • Water Network Management • Wastewater Network Management • New Connections • Growth and Development Suppliers will be required to provide an end to end … View the procurement »
Irish Water intends to undertake a competitive tendering process, the objective of which is to establish a Multi-supplier Framework Agreement for the provision of Water and Wastewater Network Services and Works nationwide. A new contract delivery mechanism is required to facilitate the delivery of the Irish Water’s Network Capital Programmes such as: • Water Network Management • Wastewater Network Management • New Connections • Growth and Development Suppliers will be required to provide an end to end … View the procurement »
2019-09-27
Carrigaline Western Relief Road (Cork County Council)
Construction of a single 750 m carriageway road. The CWRR will run along the southern boundary of Nova Court residential estate, before crossing over the Owenboy River, by means of a 32 m reinfroced concrete river bridge. Current land-use within the CPO lands primarily comprises Greenfield lands; however residential properties and brownfield sites are located in the northern portion of the proposed CWRR route. Pedestrian and traffic lights will be placed at the north, south and central junctions to … View the procurement »
Construction of a single 750 m carriageway road. The CWRR will run along the southern boundary of Nova Court residential estate, before crossing over the Owenboy River, by means of a 32 m reinfroced concrete river bridge. Current land-use within the CPO lands primarily comprises Greenfield lands; however residential properties and brownfield sites are located in the northern portion of the proposed CWRR route. Pedestrian and traffic lights will be placed at the north, south and central junctions to … View the procurement »
2019-07-01
Extension to IDA Infrastructure, Mullagharlin, Dundalk, Co. Louth (IDA Ireland)
The proposed works will comprise of the extension of the existing access road and utility infrastructure to facilitate the development of IDA Ireland’s 44,5 ha site at Mullagharlin, Dundalk, Co. Louth. The works will include road construction (including 2 No roundabouts), footpaths, drainage, SuDS, foul pumping station (reinforced concrete tank and control building), rising mains, street lighting, utilities, signage, road markings and landscaping including screening mounds, deep excavations/trenchless … View the procurement »
The proposed works will comprise of the extension of the existing access road and utility infrastructure to facilitate the development of IDA Ireland’s 44,5 ha site at Mullagharlin, Dundalk, Co. Louth. The works will include road construction (including 2 No roundabouts), footpaths, drainage, SuDS, foul pumping station (reinforced concrete tank and control building), rising mains, street lighting, utilities, signage, road markings and landscaping including screening mounds, deep excavations/trenchless … View the procurement »
2018-08-07
Cork City Water Supply Scheme Networks Upgrades (Irish Water)
Irish Water is responsible for the treatment and distribution of drinking water in Cork City. As part of the implementation of a Water Conservation Project for the city, watermains in the network have been identified for rehabilitation. These include watermains that: — Are not suitably responsive to active leakage control measures, — Have water quality issues, — Have reached the end of their service life, and — Have insufficient hydraulic capacity and are impacting on the efficient operation of the … View the procurement »
Irish Water is responsible for the treatment and distribution of drinking water in Cork City. As part of the implementation of a Water Conservation Project for the city, watermains in the network have been identified for rehabilitation. These include watermains that: — Are not suitably responsive to active leakage control measures, — Have water quality issues, — Have reached the end of their service life, and — Have insufficient hydraulic capacity and are impacting on the efficient operation of the … View the procurement »
2018-04-13
Cork City and Mallow Network Contracts (Irish Water)
Irish Water is responsible for the treatment & distribution of drinking water & the provision of sewer collection systems in Cork City & Co. — Lot 1: A number of Combined Sewer Overflows (CSOs) have been identified for removal from the sewer network in Mallow as they are currently in breach of the urban wastewater treatment directive & are the subject of an European Court of Justice (ECJ) infringement notice. The removal of these CSOs will necessitate new trunk sewers to be constructed within the town. — … View the procurement »
Irish Water is responsible for the treatment & distribution of drinking water & the provision of sewer collection systems in Cork City & Co. — Lot 1: A number of Combined Sewer Overflows (CSOs) have been identified for removal from the sewer network in Mallow as they are currently in breach of the urban wastewater treatment directive & are the subject of an European Court of Justice (ECJ) infringement notice. The removal of these CSOs will necessitate new trunk sewers to be constructed within the town. — … View the procurement »
2017-09-05
Project Indigo Green — Contract 2 (Irish Water)
The scope consists of water pumping station, watermain, foul sewer rising main, and gas related works as per Part 3 — Scope document. The works will consist of approximately 4.2 km of 140 mm PE SDR17 foul sewer rising main, 4.8 km watermain of various sizes ranging from 355 mm PE SDR17 to 560 mm PE SDR17, a new water pumping station at Loughsallagh and all associated ancillaries. The works will also construction and testing of circa 5 km of 315 mm diameter PE100 4 bar gas main and all associated … View the procurement »
The scope consists of water pumping station, watermain, foul sewer rising main, and gas related works as per Part 3 — Scope document. The works will consist of approximately 4.2 km of 140 mm PE SDR17 foul sewer rising main, 4.8 km watermain of various sizes ranging from 355 mm PE SDR17 to 560 mm PE SDR17, a new water pumping station at Loughsallagh and all associated ancillaries. The works will also construction and testing of circa 5 km of 315 mm diameter PE100 4 bar gas main and all associated … View the procurement »
2017-05-31
Old Connaught and Woodbrook Water Supply Scheme Design Build Contract (Irish Water)
The Works comprise the design and construction of water infrastructure including the associated testing, commissioning and proving of same and including the Taking-Over of the Works by the Employer. Full details of the scope of works will be detailed in the ITT. View the procurement »
The Works comprise the design and construction of water infrastructure including the associated testing, commissioning and proving of same and including the Taking-Over of the Works by the Employer. Full details of the scope of works will be detailed in the ITT. View the procurement »
2017-04-27
Ring Helvick Water Supply Scheme (Irish Water)
Ring Helvick Water Supply Scheme works are: Connection to the existing water supply network. new pumping station 2 No. reservoir sites Installation of a 6 150 m 250 mm rising main with surge vessel 2 No. 150 m³ reservoirs Construction of a control building Installation of pumping plant and equipment Installation of 640 m of 125 mm OD SDR11 HDPE rising from the Lower Reservoir site to the Upper Reservoir site. Construction of 1 No. 300 m³ reservoir Installation of 5 970 m of distribution pipework Civil … View the procurement »
Ring Helvick Water Supply Scheme works are: Connection to the existing water supply network. new pumping station 2 No. reservoir sites Installation of a 6 150 m 250 mm rising main with surge vessel 2 No. 150 m³ reservoirs Construction of a control building Installation of pumping plant and equipment Installation of 640 m of 125 mm OD SDR11 HDPE rising from the Lower Reservoir site to the Upper Reservoir site. Construction of 1 No. 300 m³ reservoir Installation of 5 970 m of distribution pipework Civil … View the procurement »
2017-03-23
Millstreet WWTP Upgrade Contract (Irish Water)
The Contracting Entity intends to appoint a Contractor who will be responsible for the design, construction and operation, for some elements, of major Civil, MEICA and process works (incorporating associated works and services) at Millstreet WWTP and within the wider agglomeration. These works will be part of Irish Water's Capital Investment Plan. Please refer to the PQQ documents for further details. View the procurement »
The Contracting Entity intends to appoint a Contractor who will be responsible for the design, construction and operation, for some elements, of major Civil, MEICA and process works (incorporating associated works and services) at Millstreet WWTP and within the wider agglomeration. These works will be part of Irish Water's Capital Investment Plan. Please refer to the PQQ documents for further details. View the procurement »
2017-02-21
Stillorgan Reservoir (Irish Water)
Stillorgan Reservoir is a modular storage facility for treated drinking water, built in 2 stages between 1862 and 1885. The site has a total plan area of approximately 16 hectares and is subdivided into 3 discrete water storage reservoirs, the Gray, Upper and Lower Reservoirs. The Lower and Upper reservoirs were constructed first, as part of the Vartry Water Supply Scheme. The Gray Reservoir was built in 1885 following a period of severe water shortage in Dublin City. The reservoirs originally contained … View the procurement »
Stillorgan Reservoir is a modular storage facility for treated drinking water, built in 2 stages between 1862 and 1885. The site has a total plan area of approximately 16 hectares and is subdivided into 3 discrete water storage reservoirs, the Gray, Upper and Lower Reservoirs. The Lower and Upper reservoirs were constructed first, as part of the Vartry Water Supply Scheme. The Gray Reservoir was built in 1885 following a period of severe water shortage in Dublin City. The reservoirs originally contained … View the procurement »
2016-12-13
Killybegs and Lettermacaward Regional Water Supply Schemes Project (Irish Water)
Irish Water on behalf of Ervia propose to upgrade two existing Water Treatment Plants (WTP's), an existing raw water impoundment, and a range of associated network infrastructure improvements including service reservoirs, booster pumping stations and pipeline works. The planned works are necessary to ensure compliance with EU Directives, Irish National Standards and Regulations relating to treated water for human consumption. It is intended that the works will be implemented under a Design, Build and … View the procurement »
Irish Water on behalf of Ervia propose to upgrade two existing Water Treatment Plants (WTP's), an existing raw water impoundment, and a range of associated network infrastructure improvements including service reservoirs, booster pumping stations and pipeline works. The planned works are necessary to ensure compliance with EU Directives, Irish National Standards and Regulations relating to treated water for human consumption. It is intended that the works will be implemented under a Design, Build and … View the procurement »
2016-11-10
Letterkenny Regional Water Supply Scheme No 3 — Network (Irish Water)
Irish Water on behalf of Ervia propose to improve the water supply infrastructure in the Letterkenny and Milford regions of County Donegal with the provision of a number of strategic water mains which will enable greater flexibility and efficiency in the use of the existing water resources. — The Pollan Dam Water Supply network will be extended to supply an existing reservoir in Letterkenny town as Phase 1 of a two phase strategy. — The Letterkenny WTP supply network will be upgraded to enable a more … View the procurement »
Irish Water on behalf of Ervia propose to improve the water supply infrastructure in the Letterkenny and Milford regions of County Donegal with the provision of a number of strategic water mains which will enable greater flexibility and efficiency in the use of the existing water resources. — The Pollan Dam Water Supply network will be extended to supply an existing reservoir in Letterkenny town as Phase 1 of a two phase strategy. — The Letterkenny WTP supply network will be upgraded to enable a more … View the procurement »
2016-11-04
Bantry to Kealkill Trunk Watermain Project (Irish Water)
Irish Water plans to undertake the construction of the following to deliver water from Bantry to Kealkill: — Construction of new water mains. — Replacement of defective water mains. — Upgrade of river intake works. — Construction of water booster pumping stations. — Construct raw water mixing tank. — Construction of treated water storage reservoirs. — Associated ancillary works. View the procurement »
Irish Water plans to undertake the construction of the following to deliver water from Bantry to Kealkill: — Construction of new water mains. — Replacement of defective water mains. — Upgrade of river intake works. — Construction of water booster pumping stations. — Construct raw water mixing tank. — Construction of treated water storage reservoirs. — Associated ancillary works. View the procurement »
2016-11-03
Lee Road Water Treatment Plant Upgrade (Irish Water)
Refurbishment/Upgrade/Expansion of the existing Lee Road Water Treatment Plant (WTP) including a one year Operation Service period. View the procurement »
Refurbishment/Upgrade/Expansion of the existing Lee Road Water Treatment Plant (WTP) including a one year Operation Service period. View the procurement »
2016-10-07
Vartry Water Supply Project — Vartry to Callowhill Link Contract (Irish Water)
As part of the Vartry Water Supply Project — Water to Callowhill Link Contract, Irish Water plan to replace the existing Vartry to Callowhill Tunnel and Callowhill BPT with a high lift pumping station, 4 km pipeline, summit BPT and energy recovery turbine / BPT at Callowhill. The planned works are necessary to ensure compliance with EU Directives, Irish National Standards and Regulations relating to treated water for human consumption. It is intended that the works will be implemented under a Design and … View the procurement »
As part of the Vartry Water Supply Project — Water to Callowhill Link Contract, Irish Water plan to replace the existing Vartry to Callowhill Tunnel and Callowhill BPT with a high lift pumping station, 4 km pipeline, summit BPT and energy recovery turbine / BPT at Callowhill. The planned works are necessary to ensure compliance with EU Directives, Irish National Standards and Regulations relating to treated water for human consumption. It is intended that the works will be implemented under a Design and … View the procurement »
2016-09-26
A Multi Supplier Framework for the Provision of Major Civil Engineering Works for Water, Wastewater and Gas... (Ervia)
Ervia is requesting tenders to establish a multi-supplier framework for the provision of major civil engineering works for Water, Wastewater and Gas (incorporating associated MEICA Works) to Ervia. It is envisaged that each item of works will be requested in a planned manner where work packages are identified in advance of each call off. The framework is divided into 2 Lots. Lot 1: Works associated with wastewater treatment, collection systems and ancillaries. Lot 2: Civil engineering works and networks … View the procurement »
Ervia is requesting tenders to establish a multi-supplier framework for the provision of major civil engineering works for Water, Wastewater and Gas (incorporating associated MEICA Works) to Ervia. It is envisaged that each item of works will be requested in a planned manner where work packages are identified in advance of each call off. The framework is divided into 2 Lots. Lot 1: Works associated with wastewater treatment, collection systems and ancillaries. Lot 2: Civil engineering works and networks … View the procurement »
2016-08-18
Skibbereen Regional Water Supply Scheme (Irish Water)
Irish water is undertaking the amalgamation of a number of water supply schemes formerly known as Schull WSS, Leap/Baltimore WSS Phase 2, Drimoleague WSS and Skibbereen WSS Stage 4. The facilitation of this amalgamation requires the construction of Water Treatment Plant upgrades, increased storage in key areas of the network, network capacity upgrades and mains rehabilitation. View the procurement »
Irish water is undertaking the amalgamation of a number of water supply schemes formerly known as Schull WSS, Leap/Baltimore WSS Phase 2, Drimoleague WSS and Skibbereen WSS Stage 4. The facilitation of this amalgamation requires the construction of Water Treatment Plant upgrades, increased storage in key areas of the network, network capacity upgrades and mains rehabilitation. View the procurement »
2016-07-25
Howth Balbriggan Kingstown Malahide Water Supply Scheme (Irish Water)
This contract is for the design and construction of an upgrade to the existing water supply network in Howth, Balbriggan, Malahide and between Ballycoolen and Kingstown in Fingal. The works included in this contract include the construction of large diameter water mains, a pumping station, reservoir and ancillary controls and telemetry. The above is the anticipated scope of the contract but 1 or more of the above schemes may not be included in the tender stage of this competition, and thus may not be … View the procurement »
This contract is for the design and construction of an upgrade to the existing water supply network in Howth, Balbriggan, Malahide and between Ballycoolen and Kingstown in Fingal. The works included in this contract include the construction of large diameter water mains, a pumping station, reservoir and ancillary controls and telemetry. The above is the anticipated scope of the contract but 1 or more of the above schemes may not be included in the tender stage of this competition, and thus may not be … View the procurement »
2016-07-06
16/138 — Tuam Regional Water Supply Scheme Extensions Project — Phase 1 Works Contract (Irish Water)
Includes: —Contractor design and construction of approx 35 km of new watermains at various locations throughout Co. Galway including Loughrea, Dunmore, Glenamaddy, Kilkerrin and Moylough; —The watermains will range from 140 mm OD (125 mm DN) to 400 mm OD (350 mm DN); —Contractor design and construction of an approx 1 000 m³ Storage Reservoir; —Approx 5 no. pressure boosting stations; —Decommissioning of 5 no. existing WTPs; —Installation of chlorine monitoring and boosting stations; —Adjustments to … View the procurement »
Includes: —Contractor design and construction of approx 35 km of new watermains at various locations throughout Co. Galway including Loughrea, Dunmore, Glenamaddy, Kilkerrin and Moylough; —The watermains will range from 140 mm OD (125 mm DN) to 400 mm OD (350 mm DN); —Contractor design and construction of an approx 1 000 m³ Storage Reservoir; —Approx 5 no. pressure boosting stations; —Decommissioning of 5 no. existing WTPs; —Installation of chlorine monitoring and boosting stations; —Adjustments to … View the procurement »
2016-05-17
Lough Mask Regional Water Supply Scheme, Water Treatment Plant Upgrade (Irish Water)
Irish Water is currently advancing the Lough Mask Regional Water Supply View the procurement »
Irish Water is currently advancing the Lough Mask Regional Water Supply View the procurement »
2016-02-22
15/158 — Strategic Watermain Link between Leixlip and Saggart (Ervia)
Design and Construction of a Water Pumping Station and Trunk Watermain to advance the Strategic Watermain Link between Leixlip and Saggart, to provide greater flexibility in the management of water transfers in the Greater Dublin Area and therefore improve the overall resilience of the water network. View the procurement »
Design and Construction of a Water Pumping Station and Trunk Watermain to advance the Strategic Watermain Link between Leixlip and Saggart, to provide greater flexibility in the management of water transfers in the Greater Dublin Area and therefore improve the overall resilience of the water network. View the procurement »
2016-02-10
15/159 — Ballyshannon Regional Water Supply Scheme Contract No 1 — Water Treatment Plant and Primary Network Design... (Ervia)
Irish Water is currently advancing the Ballyshannon Regional Water Supply Scheme Design Build Operate Contract comprising the construction of an intake structure at Lough Assaroe, pumping station, new WTP at Knader, storage reservoir(s) including all interconnecting pipework and some trunk/distribution mains. The works required under the contract are to be delivered on a Contractor Design- Build-Operate basis. The DBO contract is 24 months D-B with a 7 year Operation and Maintenance period, with an … View the procurement »
Irish Water is currently advancing the Ballyshannon Regional Water Supply Scheme Design Build Operate Contract comprising the construction of an intake structure at Lough Assaroe, pumping station, new WTP at Knader, storage reservoir(s) including all interconnecting pipework and some trunk/distribution mains. The works required under the contract are to be delivered on a Contractor Design- Build-Operate basis. The DBO contract is 24 months D-B with a 7 year Operation and Maintenance period, with an … View the procurement »
2015-09-21
Inistioge Water Supply Scheme (Ervia)
The proposed works will include the upgrade of the supply to Grennan WTP with the installation of a new borehole to supplement the existing boreholes, an upgrade to Grennan WTP, installation of 17,62 km of water main from Grennan to the existing reservoir at Ballygub, Inistioge, installation of a new reservoir at Kilmacshane, Inistioge, installation of a booster pumping station at Kilcross, Inistioge and decommissioning of the existing intake and treatment plant at Ballygub WTP, together with associated … View the procurement »
The proposed works will include the upgrade of the supply to Grennan WTP with the installation of a new borehole to supplement the existing boreholes, an upgrade to Grennan WTP, installation of 17,62 km of water main from Grennan to the existing reservoir at Ballygub, Inistioge, installation of a new reservoir at Kilmacshane, Inistioge, installation of a booster pumping station at Kilcross, Inistioge and decommissioning of the existing intake and treatment plant at Ballygub WTP, together with associated … View the procurement »
2015-08-06
Castlerea and Environs Water Supply Scheme — Phase 1 Ballyhaunis to Garranlahan and Williamstown (Ervia)
Irish Water propose to extend the Lough Mask Regional Water Supply Scheme to supply Castlerea and a number of further towns and villages in Counties Roscommon and Galway. The first phase is to supply treated water from an existing service reservoir in Ballyhaunis County Mayo onward to Garranlahan in County Roscommon and to Williamstown in County Galway. Under the proposals the existing sources would be abandoned and the schemes will be supplied with water from the Lough Mask scheme via Ballyhaunis using … View the procurement »
Irish Water propose to extend the Lough Mask Regional Water Supply Scheme to supply Castlerea and a number of further towns and villages in Counties Roscommon and Galway. The first phase is to supply treated water from an existing service reservoir in Ballyhaunis County Mayo onward to Garranlahan in County Roscommon and to Williamstown in County Galway. Under the proposals the existing sources would be abandoned and the schemes will be supplied with water from the Lough Mask scheme via Ballyhaunis using … View the procurement »
2013-12-10
13/112 - The Provision of Major Civil Engineering Works (incorporating ancillary MEICA Works) to Irish Water (Bord Gais Eireann)
IW is requesting tenders to establish a multi-supplier framework agreement for the provision of all required works and services associated with Major Civil Engineering Works (incorporating ancillary MEICA Works) to support the provision of water services capital investment. It is envisaged that these works will be carried out in a planned manner where work packages are identified in advance of each call off. The works will be sub-divided into two separate Lots detailed below. — Lot 1: Works Associated … View the procurement »
IW is requesting tenders to establish a multi-supplier framework agreement for the provision of all required works and services associated with Major Civil Engineering Works (incorporating ancillary MEICA Works) to support the provision of water services capital investment. It is envisaged that these works will be carried out in a planned manner where work packages are identified in advance of each call off. The works will be sub-divided into two separate Lots detailed below. — Lot 1: Works Associated … View the procurement »
2013-10-24
13/098 - A Multi-Supplier Framework for the provision of Minor Civil Engineering Works to Irish Water (Bord Gais Eireann)
IW is requesting tenders to establish a multi-supplier framework agreement for the provision of all required works and services associated with Minor Civil Engineering Works to support the provision of water services capital investment. It is envisaged that these Minor Civil Engineering Works will be carried out in a planned manner where work packages are identified in advance of each call off. The works will be sub-divided into five separate Lots detailed below. Lot 1: All works and services associated … View the procurement »
IW is requesting tenders to establish a multi-supplier framework agreement for the provision of all required works and services associated with Minor Civil Engineering Works to support the provision of water services capital investment. It is envisaged that these Minor Civil Engineering Works will be carried out in a planned manner where work packages are identified in advance of each call off. The works will be sub-divided into five separate Lots detailed below. Lot 1: All works and services associated … View the procurement »
2013-02-26
PMWSIS - PMWSIS Contract No. 6 RAL (Laois County Council)
This Contract, Contract No. 6 RAL provides for the construction and maintenance for a period of 12 months of the following Works: - Approximately 2.5km of 350mm diameter ductile iron pipeline from Coolbanagher Production Well 10 (PW 10) to Darkin. - Approximately 1km of 450mm diameter ductile iron pipeline between Ballydavis and the existing Kilminchy WTP. - Approximately 14m of 300mm diameter ductile iron pipeline at the Coolbanagher borewell location. - Pipework, Mechanical and Electrical Works … View the procurement »
This Contract, Contract No. 6 RAL provides for the construction and maintenance for a period of 12 months of the following Works: - Approximately 2.5km of 350mm diameter ductile iron pipeline from Coolbanagher Production Well 10 (PW 10) to Darkin. - Approximately 1km of 450mm diameter ductile iron pipeline between Ballydavis and the existing Kilminchy WTP. - Approximately 14m of 300mm diameter ductile iron pipeline at the Coolbanagher borewell location. - Pipework, Mechanical and Electrical Works … View the procurement »
2012-06-15
Thurles Regional Water Contract No.2 - Treatment & Intake Works Design Build Operate (DBO) Contract (North Tipperary County Council (Utilities))
Expressions of interest are invited from suitably qualified contractors for the design, build, operation and maintenance for 20 years of a new water treatment plant with an approximate capacity of 10 500 m3/d together with 2 No. river intakes, rising mains, pumping stations, sludge dewatering facilities, and associated site and ancillary works. The works may involve the execution of additional and repetition of similar works and services. NOTE: To register your interest in this notice and obtain any … View the procurement »
Expressions of interest are invited from suitably qualified contractors for the design, build, operation and maintenance for 20 years of a new water treatment plant with an approximate capacity of 10 500 m3/d together with 2 No. river intakes, rising mains, pumping stations, sludge dewatering facilities, and associated site and ancillary works. The works may involve the execution of additional and repetition of similar works and services. NOTE: To register your interest in this notice and obtain any … View the procurement »
2012-02-03
Burncourt Fethard water supply scheme contract no. 1 - design, build and operate contract (South Tipperary County Council (Utility))
Expressions of interest are invited from suitably qualified contractors for the design, build, operation and maintenance for 10 years of two (2) new water treatment plants ranging from 2 600 m/d to 6 500 m/d together with sludge dewatering facilities, river intakes, rising mains, pumping stations and reservoirs to serve the areas of Fethard and Burncourt in Co. Tipperary. View the procurement »
Expressions of interest are invited from suitably qualified contractors for the design, build, operation and maintenance for 10 years of two (2) new water treatment plants ranging from 2 600 m/d to 6 500 m/d together with sludge dewatering facilities, river intakes, rising mains, pumping stations and reservoirs to serve the areas of Fethard and Burncourt in Co. Tipperary. View the procurement »
2011-10-06
Wexford Collection System Extension Scheme - Contract No. 1 (Taghmon & Crosstown Ferrybank) (Wexford County Council)
Construction of 3 new pumping stations and associated rising mains and gravity sewers and all ancilliary works, fittings, connections etc. to connect the villages of Crosstown/Ferrybank and Taghmon to the public sewer network in Wexford Town. The works include the construction of approximately 12 500 m length rising mains (varying from 150 mm to 250 mm diameter), approximately 3 000 m length of gravity sewers (varying from 200 mm to 300 mm in diameter) and 50No. manholes associated with the above … View the procurement »
Construction of 3 new pumping stations and associated rising mains and gravity sewers and all ancilliary works, fittings, connections etc. to connect the villages of Crosstown/Ferrybank and Taghmon to the public sewer network in Wexford Town. The works include the construction of approximately 12 500 m length rising mains (varying from 150 mm to 250 mm diameter), approximately 3 000 m length of gravity sewers (varying from 200 mm to 300 mm in diameter) and 50No. manholes associated with the above … View the procurement »
2011-08-11
Carrickmacross water supply augmentation scheme – design/build & operate contract (Monaghan County Council)
Expressions of interest are invited from suitably experienced contractors who wish to tender for works comprising the design, construction, operation and maintenance for a period of up to 20 years of facilities to abstract water from a number of existing production wells, pumping of the raw water to a new water treatment plant and storing treated water for distribution to the existing distribution network. Note: To register your interest in this notice and obtain any additional information please visit … View the procurement »
Expressions of interest are invited from suitably experienced contractors who wish to tender for works comprising the design, construction, operation and maintenance for a period of up to 20 years of facilities to abstract water from a number of existing production wells, pumping of the raw water to a new water treatment plant and storing treated water for distribution to the existing distribution network. Note: To register your interest in this notice and obtain any additional information please visit … View the procurement »
2011-03-22
Wexford collection system extension scheme - contract no. 1 (Taghmon & Crosstown Ferrybank) (Wexford County Council)
Construction of 3 new pumping stations and associated rising mains and gravity sewers and all ancilliary works, fittings, connections etc. to connect the villages of Crosstown/Ferrybank and Taghmon to the public sewer network in Wexford Town. The works include the construction of approximately 12 500 m length rising mains (varying from 150 mm to 250 mm diameter), approximately 3 000 m length of gravity sewers (varying from 200 mm to 300 mm in diameter) and 50 No. manholes associated with the above … View the procurement »
Construction of 3 new pumping stations and associated rising mains and gravity sewers and all ancilliary works, fittings, connections etc. to connect the villages of Crosstown/Ferrybank and Taghmon to the public sewer network in Wexford Town. The works include the construction of approximately 12 500 m length rising mains (varying from 150 mm to 250 mm diameter), approximately 3 000 m length of gravity sewers (varying from 200 mm to 300 mm in diameter) and 50 No. manholes associated with the above … View the procurement »
2010-09-03
Water-treatment work (Roscommon County Council)
North East Roscommon Regional Water Supply Scheme: contract 2 - DBO water treatment works. Expressions of interest are invited from suitably qualified firms capable of performing the following: Works shall comprise the design, procurement, supply, construction, testing, setting to work, performance testing and operation and maintenance of a complete, fully functioning raw water intake and water treatment facility including for the dewatering and disposal of waterworks sludge. Each element of the … View the procurement »
North East Roscommon Regional Water Supply Scheme: contract 2 - DBO water treatment works. Expressions of interest are invited from suitably qualified firms capable of performing the following: Works shall comprise the design, procurement, supply, construction, testing, setting to work, performance testing and operation and maintenance of a complete, fully functioning raw water intake and water treatment facility including for the dewatering and disposal of waterworks sludge. Each element of the … View the procurement »
2009-08-15
Construction work for water and sewage pipelines (Cork County Council)
Title attributed to the contract by the contracting authority: Mallow Ballyviniter Regional Water Supply Scheme - Box Cross Phase 1. This Contract provides for the construction of watermains (diameters ranging from 150 mm to 450 mm) approximately 16 900 m in length along with all asscoiated valves, valves and chambers. the watermains commence at Box Cross and terminate at Mallow Bridge. The Contract also involves the construction of a new water treatment facility (mechanical and electrical ionstallation) … View the procurement »
Title attributed to the contract by the contracting authority: Mallow Ballyviniter Regional Water Supply Scheme - Box Cross Phase 1. This Contract provides for the construction of watermains (diameters ranging from 150 mm to 450 mm) approximately 16 900 m in length along with all asscoiated valves, valves and chambers. the watermains commence at Box Cross and terminate at Mallow Bridge. The Contract also involves the construction of a new water treatment facility (mechanical and electrical ionstallation) … View the procurement »
2009-03-07
Water-treatment work (Cavan County Council)
Title attributed to the contract by the contracting authority: Kingscourt Water and Wastewater Scheme DBO Contract 3. Expressions of interest are invited from suitably qualified firms capable of performing the following: 1. Design and construction of facilities to abstract water from a number of production wells and pump the raw water to a new water treatment plant. Design and construction of a water treatment plant and storage reservoir which will ensure an adequate supply of water to Kingscourt … View the procurement »
Title attributed to the contract by the contracting authority: Kingscourt Water and Wastewater Scheme DBO Contract 3. Expressions of interest are invited from suitably qualified firms capable of performing the following: 1. Design and construction of facilities to abstract water from a number of production wells and pump the raw water to a new water treatment plant. Design and construction of a water treatment plant and storage reservoir which will ensure an adequate supply of water to Kingscourt … View the procurement »
2008-08-29
Construction work for water projects (Kilkenny County Council)
Title attributed to the contract by the contracting authority: Mooncoin Regional Water Supply Scheme - Phase 1A - Request to Participate. Suitability Assessment of Works Contractors [phase 1 of restricted procedure] for the following works to be carried out in South Kilkenny. — Provision of pumps, control house, power and instrumentation and site works, to facilitate the development of the Kilmacow Well Field, — Construction of a treatment plant and highlift pumping station close to Dunkitt village, — … View the procurement »
Title attributed to the contract by the contracting authority: Mooncoin Regional Water Supply Scheme - Phase 1A - Request to Participate. Suitability Assessment of Works Contractors [phase 1 of restricted procedure] for the following works to be carried out in South Kilkenny. — Provision of pumps, control house, power and instrumentation and site works, to facilitate the development of the Kilmacow Well Field, — Construction of a treatment plant and highlift pumping station close to Dunkitt village, — … View the procurement »
2008-08-13
Works related to water-distribution pipelines (Kilkenny County Council)
Title attributed to the contract by the contracting authority: Mooncoin Regional Water Supply Scheme - Phase 1A - Request to Participate. Suitability Assessment of Works Contractors in advance of a tender competition run by restricted procedure for the following works to be carried out in South Kilkenny: — Provision of pumps, control house, power and instrumentation and site works, to facilitate the development of the Kilmacow Well Field, — Construction of a treatment plant and highlift pumping station … View the procurement »
Title attributed to the contract by the contracting authority: Mooncoin Regional Water Supply Scheme - Phase 1A - Request to Participate. Suitability Assessment of Works Contractors in advance of a tender competition run by restricted procedure for the following works to be carried out in South Kilkenny: — Provision of pumps, control house, power and instrumentation and site works, to facilitate the development of the Kilmacow Well Field, — Construction of a treatment plant and highlift pumping station … View the procurement »
2008-03-27
Water-treatment work (Wicklow County Council)
Title attributed to the contract by the contracting authority: Arklow water supply contract 4 design build & operate contract abstraction & water treatment works. Expressions of interest are invited from suitably qualified firms capable of performing the following: 1. Design and construction of facilities to abstract water from a number of production wells and pump the raw water to a new water treatment plant. Design and construction of a water treatment plant which will ensure an adequate supply of … View the procurement »
Title attributed to the contract by the contracting authority: Arklow water supply contract 4 design build & operate contract abstraction & water treatment works. Expressions of interest are invited from suitably qualified firms capable of performing the following: 1. Design and construction of facilities to abstract water from a number of production wells and pump the raw water to a new water treatment plant. Design and construction of a water treatment plant which will ensure an adequate supply of … View the procurement »
2008-02-26
Water-treatment work (Monaghan County Council)
Title attributed to the contract by the contracting authority: Carrickmacross Water Supply Augmentation Scheme ¿ Design/Build & Operate Contract. Expressions of interest are invited from suitably experienced contractors who wish to tender for works comprising the design, construction, operation and maintenance for a period of up to 20 years of facilities to abstract water from a number of production wells, pumping of the raw water to the new water treatment plant and storing treated water for … View the procurement »
Title attributed to the contract by the contracting authority: Carrickmacross Water Supply Augmentation Scheme ¿ Design/Build & Operate Contract. Expressions of interest are invited from suitably experienced contractors who wish to tender for works comprising the design, construction, operation and maintenance for a period of up to 20 years of facilities to abstract water from a number of production wells, pumping of the raw water to the new water treatment plant and storing treated water for … View the procurement »
2008-02-06
Water-treatment work (Westmeath County Council)
Title attributed to the contract by the contracting authority: South Westmeath Water Supply Scheme. The South Westmeath Water Supply Scheme involves the provision of a new raw water intake arrangement from Killinure Lough, an inlet of Lough Ree on the River Shannon, provision of pumping station and treatment plant at Portaneena with a capacity of up to 41 million litre per day, pumping main to a reservoir, the provision of trunk mains, service reservoirs and distribution mains, together with connections … View the procurement »
Title attributed to the contract by the contracting authority: South Westmeath Water Supply Scheme. The South Westmeath Water Supply Scheme involves the provision of a new raw water intake arrangement from Killinure Lough, an inlet of Lough Ree on the River Shannon, provision of pumping station and treatment plant at Portaneena with a capacity of up to 41 million litre per day, pumping main to a reservoir, the provision of trunk mains, service reservoirs and distribution mains, together with connections … View the procurement »
2007-12-27
Construction work for water and sewage pipelines (Cork County Council)
Title attributed to the contract by the contracting authority: Dripsey Coachford Water Supply Scheme Upgrade. The scheme includes the construction of a new pumping station, 900cu.m reservoir, rising mains,trunk mains and distribution mains and miscellaneous siteworks in the Dripsey/Coachford area of Co. Cork. View the procurement »
Title attributed to the contract by the contracting authority: Dripsey Coachford Water Supply Scheme Upgrade. The scheme includes the construction of a new pumping station, 900cu.m reservoir, rising mains,trunk mains and distribution mains and miscellaneous siteworks in the Dripsey/Coachford area of Co. Cork. View the procurement »
2007-12-04
Construction work for water and sewage pipelines (Cork County Council)
Title attributed to the contract by the contracting authority: Bantry water supply - interim scheme - civil works. This scheme includes the construction of a new intake, pumping station, 1 150 m3 reservoir, water treatment plant, meter house, sludge holding tank, rising mains and trunk mains, roadworks and miscellaneous siteworks in the environs of Bantry. further information relating to this notice may be available on the eTenders web site at http://www.etenders.gov.ie/Search/ Search_Switch.aspx?ID=57302. View the procurement »
Title attributed to the contract by the contracting authority: Bantry water supply - interim scheme - civil works. This scheme includes the construction of a new intake, pumping station, 1 150 m3 reservoir, water treatment plant, meter house, sludge holding tank, rising mains and trunk mains, roadworks and miscellaneous siteworks in the environs of Bantry. further information relating to this notice may be available on the eTenders web site at http://www.etenders.gov.ie/Search/ Search_Switch.aspx?ID=57302. View the procurement »