2023-06-27Est Constr Surgical Hub at Merlin Park University Hospital Galway (Health Service Executive HSE)
The development will comprise of the following: •The provision of a three storey Surgical Hub building (Gross Floor Area: 4,265 sq.m) to include: o Staff Services, Storage and Plant Rooms at Ground Floor Level; o Operating Theatres, Preparation Area, Recovery Area , Waiting Area and ancillary support services at First Floor Level; and o Plant and associated equipment at Second Floor Level. • The provision of roof mounted Solar PV Panels; • The provision of 108 no. car parking spaces (including 6 no. …
View the procurement »
2022-10-20The Contracting Authority (Connacht Rugby Stadium Ltd.) is seeking to appoint a Works Contractor (on a Design &... (Connacht Rugby Stadium Ltd)
The Redevelopment of the Sportsgrounds, College Road, Galway - Phase 2 – North Stand and High-Performance Centre & Associated External Works generally consists of the following: • Phase 2A - A new High-Performance Centre comprising of a new indoor synthetic training pitch and office accommodation which will incorporate offices and player welfare facilities (canteen, treatment rooms, etc). This new High-Performance Centre is adjacent to the existing Bohermore Cemetery wall which is within the curtilage of …
View the procurement »
2021-07-26Acute Inpatient Ward (96-bed) Block at University Hospital Limerick (UHL) (Health Service Executive (HSE))
The development will be a new 4-storey, 96 single bed, acute inpatient ward block extension (GFA 9 817 m.) with interstitial plantroon floor part of existing plantroom all located above the existing 2 storey above ground Renal and Emergency Department over 2 Storey Basement Carpark, adjacent to the Critical Care Unit, along with supporting services associated with site works, additional plant on the existing phase 1 building, an extension to the existing outpatients department at level 0, 110 carparking …
View the procurement » Mentioned suppliers:John Sisk & Son (Holdings) Ltd
2021-03-02Clare County Library (Clare County Council)
The overall project will comprise construction of a new County Library on a brownfield site.
A previous contractor had commenced works, including piling, substructure and site works. The contractor's obligations under the previous contract have now been terminated.
Under this proposed new contract, the contractor will be responsible for the complete construction works for the project.
View the procurement » Mentioned suppliers:Coolsivna Construction Ltd
2020-10-27Upgrade of Façade with Installation of Windows, Doors and Insulated Render External. Removal of Redundant roof... (Dundalk Institute of Technology)
The existing external envelope and roof covering membranes to the North Building are reaching the end of their economic life and require replacement. The existing envelope and some areas of the existing roof have insufficient thermal properties due to the absence of insulation and as part of the fabric and roofing upgrade works it is proposed to upgrade the thermal properties of the existing structure through the replacement of existing glazing, application of insulated render to existing precast …
View the procurement »
2020-09-24Proposed Corporate Support Services Building at Institute of Technology Carlow, Kilkenny Road, Co. Carlow (Institute of Technology Carlow)
The new Corporate Support Services Building (CSSB) is a circa 5000 sqm four storey building which is being constructed on the northern end of the IT Carlow campus towards the eastern boundary to provide storage and office space for various departments including HR, development, finance, international, academic staff, admin, estates and insurtech.
The new building will include a vertical central atrium throughout, sub station and new east road.
The facility is a stone and glazing clad structural steel …
View the procurement »
2020-05-14STEM Building Extension at Dundalk Institute of Technology Campus, Dublin Road, Dundalk, Co. Louth (Dundalk Institute of Technology)
The new STEM building extension is a circa 1 300 m two storey building which is being constructed on the eastern side of the existing North Building to provide teaching and lab spaces for students at the facility.
The new building will include a two storey link to the existing North Building which will require some alteration works within the North Building to facilitate same.
The new facility is a brick and glazing clad RC structure with highly serviced laboratory and associated teaching spaces. …
View the procurement » Mentioned suppliers:McKeon Group
2019-11-18Academic Hub Library Complex (Grangegorman Development Agency)
The initial phase of the TU Dublin Academic Hub and Library Complex is planned as a cluster of buildings and courtyards, both existing and new around the historic North House protected structure. The library and student support complex will sit at the heart of the new Grangegorman campus, addressing a large plaza and commanding views over the city.
The overall Phase 1 development is approximately 12 580 m in area. The development consists of 9 505 m of new build construction with the balance comprising …
View the procurement »
2019-11-18AHLC: Reserved Specialists (Grangegorman Development Agency)
The initial phase of the TU Dublin Academic Hub and Library Complex is planned as a cluster of buildings and courtyards, both existing and new around the historic North House protected structure. The library and student support complex will sit at the heart of the new Grangegorman campus, addressing a large plaza and commanding views over the city.
The overall Phase 1 development is approximately 12 580 m in area. The development consists of 9 505 m of new build construction with the balance comprising …
View the procurement »
2019-09-16Maynooth University Student Centre (Maynooth University)
Maynooth University wishes to construct a new 3 700 m student centre which will act as a hub for Maynooth Student Union (MSU), clubs, societies, events and the variety of activities that create that special sense of belonging at Maynooth University. The distinctive architecture and facilities will deliver a unique destination on campus that offers a welcoming and inclusive environment for our students. Construction will commence in early 2020 and the anticipated completion date is August 2021.
View the procurement »
2019-09-06Samuel Beckett Civic Campus Phase 2: Timber Facade (Dun Laoghaire Rathdown County Council)
The site is located on Ballyogan Road, Carrickmines and is adjacent to the LUAS line. Phase 1 included a sports and community building, sports pitches and surface car parks. Phase 2 will expand on Phase 1 and will include the following:
A. the change of use of the Phase 1 sports and community building to a library and community building;
B. refurbishment of the existing sports building to create a new library;
C. the construction of a new sports building, incorporating a 25 metre swimming pool, a …
View the procurement »
2018-10-03Maynooth University Refurbishment of Existing Arts Building (Maynooth University)
The Works Contractor contract defined as the Refurbishment of the existing Arts Building of 4 700 m accommodation which may be delivered over 2 phases. Phase 1 is circa 1 390 m which provides for reconfiguration of existing offices into modern teaching spaces and courtyard. Phase 2 is circa 3 310 m which provides reconfiguration of existing toilets, office space into modern teaching spaces. Works also include provision of new courtyard and works to existing mechanical and electrical systems.
View the procurement »
2018-09-21Maynooth University Academic Building New Construction (Maynooth University)
The Works Contractor contract defined as the Academic Building New Construction comprises the new construction of 10,554 m accommodation which may be delivered across a single or 2 phases. Phase 1 is circa 5,287 m which provides for teaching spaces predominantly on ground and first floors with offices, reading and support spaces on second and third floors. Enclosed plant space is located at fourth floor. The main objective of the competition is the Phase 1, with the option to proceed with Phase 2, …
View the procurement » Mentioned suppliers:JJ Rhatigan and Company
2018-07-24Works Contractors for UCC Health Innovation Hub for Building Works Design by the Contractor PW-CF2 (University College Cork (UCC))
The project consists of the construction of a new circa 3 750 m building consisting of a ground floor, first floor, second floor and third floor. The building is going to be primarily used as an open plan business innovation space with limited cellular offices on ground to second floors. The second floor North wing and the third floor will not be fitted out as part of these works The building is a concrete frame with RC/block work walls and an architectural precast concrete cladding external wall finish. …
View the procurement »
2018-06-29Construction of Clare County Library (Clare County Council)
The overall project will comprise construction of a new County Library on a brownfield site. The proposed project when completed will be attached to the existing Glór Theatre and consequently there will be significant works required at the interface of the two buildings including some demolition work. Applicants should note that the works will be carried out in a live environment and safe access to and full use of the Glór Theatre will be required for the duration of the works. The new building measuring …
View the procurement » Mentioned suppliers:L&M Keating Ltd
2017-01-23RFI for Shannon Airport Aircraft Hangar and Taxiway Project (Shannon Airport Authority DAC)
The Works Contractor shall be responsible for the construction of a new 7 200 m² steel framed aircraft hangar clad with insulated panels within the airport lands at Shannon Airport, Co. Clare, Ireland. The area includes for ancillary office space, workshops, plant rooms and storage space. Site works including car parking, landscaping and civil works.
The hangar will have an approximate 90m clear span steel roof truss with the works being carried out in poor ground conditions requiring significant ground …
View the procurement » Mentioned suppliers:L&M Keating Ltd
2016-06-16Hanging Gardens Development, Henry St, Limerick (Limerick City and County Council)
The development will comprise the completion of a partially constructed circa 7 765m 6 storey over basement shell and core office building, the demolition of no 19 Henry St and the construction of a circa 1 900 m 5 storey shell and core office building, the refurbishment of circa 680 m of the existing Mercantile, GPO and Hanging Gardens Buildings and associated external works.
View the procurement »
2016-05-11100 Bed Nursing Facility and Catering Department (Peamount Healthcare)
Construction of a new 2 storey healthcare unit comprising residential accommodation for 100 people, ancillary healthcare services, catering, pharmacy and staff facilities, associated site works, access road, landscaping, an internal link to the existing rehabilitation unit, together with redistribution of existing car parking spaces and the demolition of a disused building. The proposed works are located on the site of Protected Structures.
View the procurement »
2015-08-27Works Specialists with Design Input for the new children‘s hospital at St James Campus, Dublin 8 (National Paediatric Hospital Development Board)
The scope of the main works for the new children's hospital in broad terms comprises of:
— The demolition of all buildings on the site of the new children's hospital;
— Construction of a new children's hospital building and associated helipad;
— A two-level underground car park under same, with a further level of shared facilities management hub and energy centre below;
— Public realm improvements to the existing St James's campus spine road; the linear park at the Rialto Luas stop and the public steps …
View the procurement »
2014-07-04UL0330 – University of Limerick Sport Arena Extension (University of Limerick)
The development will comprise the construction of a circa 4,500 m² extension to the UL Sports Arena on the University of Limerick Campus. The development includes a single storey buidling to provide a 25M X 10M swimming pool and a separate three store extension to provide an elite dry sports training facility. The swimming pool includes a 25M x 10M training pool complete with diving facility to 4m depth at one end, additional squad changing rooms and associated shower areas complete with ancillary pool …
View the procurement »
2013-08-13Dublin Institute of Technology Research Hub (EHSI & HHI) (Grangegorman Development Agency)
The GDA is seeking to appoint a design & build contractor with an integrated multidisciplinary contractor design team who will design and construct a new build Research Hub incorporating the Environmental Health Sciences Institution (EHSI) and Hot House Incubation Unit (HHI) within a 5 storey development circa 4 500 m².
The Grangegorman Site is a brownfield site of 28.7 Hectares that is in a process of change from institutional use as the former St Brendan's Hospital to a new urban quarter comprising of …
View the procurement » Mentioned suppliers:Bam Building Ltd
2012-08-17UCC Western Gateway Building - Phase 2 Fit-Out (University College Cork (UCC))
The construction of Phase 1 of the fit out works to the 3rd and 4th floors was completed in March 2012.
Phase 2 comprises both new build and fit out of the existing third and fourth floors of the Western Gateway Building. The new build works consist of extension to the south plant room on the 4th and 5th floor/roof and the construction of new offices along the southern length of the 4th floor.
The fit out of the existing shell on the 3rd and 4th floors comprises of biomedical research laboratories namely …
View the procurement » Mentioned suppliers:Walls Construction Ltd
2012-05-21Science/Canteen Extension Phase 2 (E02) (Institute of Technology Sligo)
Construction of a three storey concrete framed extension with atriums to the South face of the existing 1970 Building (Block B) totalling approx 4 300 sqm of new build together with approx 2 000 sqm of refurbishment to include new mezzanine floor within the existing occupied building. Works include two floors of highly serviced science laboratories, staff offices and associated facilities over a new 500 seat canteen with associated kitchen/servery. Construction of a new Part M compliant pedestrian access …
View the procurement »
2012-02-22Beaufort Maritime & Energy Research Laboratory (University College Cork (UCC))
The works will consist of the development of the new Beaufort Maritime & Energy Research Laboratory having a total floor area of 5,132 m2, demolition of existing warehouse, construction of access road and ancillary site development works, located on a site adjoining the National Maritime College of Ireland (NMCI).
NOTE: To register your interest in this notice and obtain any additional information please visit the eTenders Web Site at http://www.etenders.gov.ie/Search/Search_Switch.aspx?ID=370852.
View the procurement »
2011-05-19Campus development works, St. Patrick's College, Drumcondra (St Patrick's College)
Construction of two new teaching blocks of approximately 4 900 sq.m each, incorporating lecture theatres, study areas, workshops, cafe. Other new buildings include a sports building and a new creche facility. There will be a redevelopment of an existing teaching block and a mechanical and electrical refurbishment of three other blocks. Temporary office buildings will be required during construction phase. There will be extensive external works. The college will continue to operate normal activities …
View the procurement » Mentioned suppliers:JJ Rhatigan & Company