2021-03-02Public Lighting Maintenance and Related Services Contract – Tipperary County Council (Tipperary County Council)
Tipperary County Council provides public lighting within their respective administrative areas. Tipperary County Council is seeking to procure the supply of maintenance and associated services of the public lighting stock under their control. This maintenance contract shall operate for a 24-month period commencing on the date of the contract signing between the successful contractor and the employer. An option will be included to allow for two further 12-month extensions (or part thereof) up to a maximum …
View the procurement » Mentioned suppliers:ENERVEO Ireland Ltd.,
2021-03-02Clare County Library (Clare County Council)
The overall project will comprise construction of a new County Library on a brownfield site.
A previous contractor had commenced works, including piling, substructure and site works. The contractor's obligations under the previous contract have now been terminated.
Under this proposed new contract, the contractor will be responsible for the complete construction works for the project.
View the procurement » Mentioned suppliers:Coolsivna Construction Ltd
2021-02-17Dublin Airport (DAP) Works Framework Agreement (daa plc)
The scope of the projects issued under the WP11 Dublin Airport (DAP) works framework agreement comprises the design, procurement, construction, testing, commissioning and putting into service of works and services to safeguard the potential for future development at Dublin Airport and improve the existing infrastructure.
View the procurement »
2021-02-16Works Contract for the Design and Construction of Shanganagh Castle Estate Housing Development for the Land... (Land Development Agency)
Shanganagh Castle Estate housing development is a key strategic project located in Shankill, Co. Dublin, Ireland and forms part of current and future programmes of work to be undertaken by the contracting authority to develop affordable sale, cost rental and social housing and apartments. The development is a collaboration between Dún Laoghaire-Rathdown County Council and the contracting authority. The works contractor shall enter into the works contract directly with the contracting authority. Further …
View the procurement »
2021-02-12Main Works Contractor: Trinity East — Early Activation Innovation Hub (Trinity College Dublin, the University of Dublin)
Trinity College Dublin, the University of Dublin is seeking to appoint a main works contractor to deliver the Trinity East: Early Activation Innovation Hub project. The project proposes the adaptation and refurbishment of No.4 Grand Canal Quay and the two adjacent smaller buildings, together with the refurbishment of the ground floor of the adjacent tower (No.5 Grand Canal Quay) which is a protected structure. The two buildings are to be connected by an external covered walkway, which also divides the …
View the procurement » Mentioned suppliers:Flynn Management & Contractors
2021-02-05Electrical Balance of Plant Services — Derryadd Wind Farm (Bord Na Mona)
Bord na Móna Powergen Ltd intends to procure design and build services for the Derryadd wind farm grid connection works.
The scope of works for the proposed contract shall include design, procurement, construction, testing, and commissioning pertaining to the grid connection works as outlined in the below list. It should be noted the below list is non-exhaustive and detailed scope of work will be issued at tender stage.
• civil works for 110 kV contestable substation and IPP MV substation;
• civil works …
View the procurement »
2021-01-25New Post Primary School (Department of Education and Skills)
Electrical reserved specialist shall be responsible for the complete electrical services installations associated with the project including appointing sub-specialists for the following installations – fire alarms, voice evacuation, structured cabling, lightning protection, lighting controls, LV Switchgear, induction loops, security installations, emergency lighting systems and solar PV panels.
View the procurement »
2021-01-19RTÉ MV Switchgear (Raidio Teilifis Eireann (RTE))
RTÉ has a requirement to upgrade its existing TV Block medium voltage switchgear at its Donnybrook site. As part of this upgrade, it is planned to replace the existing MV switchboard as detailed in this tender document. This turnkey project incorporates both Civil and M&E works. A single contractor will be awarded this turnkey project and will be responsible for the Project Management of the project from Contract Award to Practical Completion.
View the procurement » Mentioned suppliers:CJK Engineering
2021-01-06Mechanical and Electrical Engineering services St Joseph's Secondary School Rush and Gaelscoil RosEo (CEIST)
It is proposed to construct both schools on the 5.24 Ha./13 Acre campus site identified. Both schools and all elements of the site works are to be designed and constructed in accordance with all technical guidance and in accordance with the parameters as set out in the site strategy drawing. Separate appointments will be made for architectural, civil and structural, quantity surveying and PSDP services.
View the procurement »
2020-12-22Head Quarters Building Fit Out (An Post)
This is a call to competition by An Post for the provision of fit out services for a new head quarters building in Dublin City (referred to below as the Site) (the ‘Contract’). An Post intends to procure a contract for the fit out of the category B new office fit-out, c. 100 000 sq., ft. (Net Internal Floor Area) over 6 floors and ancillary spaces including basement and ground floor spaces at the building. The building will be finished to a ‘shell and core with Category A fit-out, and this contract will …
View the procurement »
2020-12-18Schools Remediation Programme 3 (Department of Education)
The Minister for Education and Skills (the Contracting Authority), intends to establish a multi-party framework, of suitably qualified and experienced MEP services contractors to deliver works contracts for the MEP remediation and associated works. Remediation works shall be carried out at existing schools across the Republic of Ireland. Applicants should note that further/fewer projects may be carried out under the framework at the discretion of the contracting authority.
View the procurement » Mentioned suppliers:CJK Electrical LtdSensori Facilities Management Ltd
2020-12-14Public Lighting, Maintenance and Ancillary Services for Waterford City and County Council (Waterford City and County Council)
The lighting contract will consist of the follow:
Number of lights 17 300 (approx) details as follows:
Category 1 Public lights powered by underground cabled Council network throughout the County;
Category 1 Public lights powered by overhead ESB network throughout the County;
Category 1 Public Lighting located along National Primary, National Secondary, Regional and Local road networks throughout the County;
Category 2 Public lights providing flood lighting to buildings etc.
This contract will operate …
View the procurement » Mentioned suppliers:Killaree Lighting Services
2020-11-2620/057 - PQQ - SWSOS Security Upgrades (Ervia)
Design, construction, testing, commissioning of upgrades to security systems and enhancements to two existing Gas transmission stations and two existing compressor stations in Scotland. Installation of extensive (>1km) lengths of high specification security fencing and gates, incorporating perimeter intruder detection system, electric toppers, security lighting, CCTV & video analytics. Protect all sensitive information. Perform the roles of Principal Designer and Principal Contractor.
View the procurement » Mentioned suppliers:Murphy International Limited UK
2020-11-11Moneypoint Electrical Maintenance Resources Framework Agreement (Electricity Supply Board (ESB))
The contracting entity intends to procure, GWM12310 Moneypoint electrical maintenance resources contract for services qualified electricians and electrical charge hands to support the electrical maintenance requirements of the station at Moneypoint for the next 4 years with an option for further 4 years. The requirement is for contractor resources on site to ensure that the units continue to run efficiently and effectively for the duration of the contract. In order to mitigate the resource shortfall is …
View the procurement »
2020-10-27Upgrade of Façade with Installation of Windows, Doors and Insulated Render External. Removal of Redundant roof... (Dundalk Institute of Technology)
The existing external envelope and roof covering membranes to the North Building are reaching the end of their economic life and require replacement. The existing envelope and some areas of the existing roof have insufficient thermal properties due to the absence of insulation and as part of the fabric and roofing upgrade works it is proposed to upgrade the thermal properties of the existing structure through the replacement of existing glazing, application of insulated render to existing precast …
View the procurement »
2020-10-27Higher Education PPP Programme — Bundle 2 (National Development Finance Agency)
The National Treasury Management Agency (describing itself as the National Development Finance Agency) (the ‘NDFA’) for and on behalf of the Department of Further and Higher Education, Research, Innovation and Science (as Approving Authority) and the Higher Education Authority (as Sponsoring Agency) wishes to procure, by Public Private Partnership (‘PPP’), the design, build, finance, operation and maintenance of a number of new buildings at Higher Education Institutions in Ireland (the ‘Project …
View the procurement »
2020-10-25Building Services (M&E) Engineering Services for Additional Accommodation at Tarmon NS, Co. Roscommon (Tarmon National School)
Building services (M&E) engineering services for additional accommodation at Tarmon NS, Co. Roscommon.
Section A:
• 2 classrooms: 80 m each,
• additional toilets 8 m.
Giving a floor area including circulation and internal walls of: 224 m.
Section B: Special needs accommodation
• 1 classroom safe base 70 m,
• 1 classroom early intervention class 70 m,
• student and staff toilets: 40 m,
• 2 small safe place rooms 24 m,
• multi-sensory room 20 m,
• office, store and storage 46 m.
Giving a floor area (incl …
View the procurement »
2020-10-07Refurbishment and Extension Block (L) (IT Sligo)
The project comprises an extensive deep refurbishment and extension of the existing Block (L) to accommodate facilities for the faculty of engineering and design. The existing building is predominantly single storey totalling 1 568 m and the refurbishment will involve full element replacement. The proposed new build of Approx. 1 700 m will comprise a part three storey extension to the existing building. Accommodation includes art and design studios, workshops, black box accommodation, ceramics, print and …
View the procurement » Mentioned suppliers:Aisho Construction Ltd t/a Boyle Construction
2020-10-07Extension (E01) and Partial Refurbishment Block (B) (IT Sligo)
The works comprise an new four-storey Extension (E01) to Block (B) together with partial refurbishment of the existing building. The proposed extension will be circa 3 950 m with refurbishment involving approximately 430 m.
Accommodation will comprise mixed teaching and research facilities including undergraduate and postgraduate science laboratories, clean room, PC laboratories, project rooms, classrooms, research facilities, online leaning facilities together with staff and ancillary accommodation and …
View the procurement » Mentioned suppliers:Tracey Brothers Ltd