2019-12-1619/223 — PQQ — Interreg Swell Wastewater Upgrades — Main Works Contract (Irish Water)
The Shared Waters Enhancement and Loughs Legacy (SWELL) project is supported by the European Union’s Interreg VA Programme, managed by the Special EU Programmes Body. The SWELL project’s aim is to improve the water quality, within the shared waters of Carlingford Lough and Lough Foyle. Through strategic catchment investigations and modelling, the SWELL project is planned to deliver optimised, sustainable capital upgrades to wastewater assets.
The works associated with this particular contract PQQ involve …
View the procurement » Mentioned suppliers:BSG Civil Engineering Ltd
2018-11-07Greater Dublin Drainage Project – Wastewater Treatment Plant and Abbotstown Pumping Station DBO Contract (Irish Water)
The WwTP and Abbotstown Pumping Station are the subject of this competition and will be constructed utilising a design, build and operate contract. Within the WwTP site, a second pumping station is required to lift the incoming North Fringe Sewer (NFS) intercepting pipeline to the inlet works. Scope of works for this competition — Detailed design and construction and Operation of a WwTP with an initial capacity of 500 000 PE to treat a Dry Weather Flow (DWF) of 112 500 m/day and a total sludge tonnage of …
View the procurement »
2018-07-20Ringsend WwTP — Phosphorus Fixation Contract (Irish Water)
The Ringsend WwTP treats most of the wastewater arising in the Greater Dublin Area. Irish Water is currently planning an upgrade to the Ringsend Treatment Plant based on the application of aerobic granular sludge technology (Nereda®) which will provide for nutrient removal, including Enhanced Biological Phosphorus Removal (EBPR). The introduction of aerobic granular sludge and EBNR will be carried out in phased upgrades of the Ringsend plant, with the aim (inter alia) of reducing the Phosphorus (P) …
View the procurement » Mentioned suppliers:Murphy International Ltd
2017-03-23Millstreet WWTP Upgrade Contract (Irish Water)
The Contracting Entity intends to appoint a Contractor who will be responsible for the design, construction and operation, for some elements, of major Civil, MEICA and process works (incorporating associated works and services) at Millstreet WWTP and within the wider agglomeration. These works will be part of Irish Water's Capital Investment Plan.
Please refer to the PQQ documents for further details.
View the procurement » Mentioned suppliers:Electrical and Pump Services Ltd
2017-03-01Cork Mid-West Bundle — Waste-water Treatment Plants DBO Contract (Irish Water)
The Contract consists of the detailed design, construction and testing of new waste-water treatment facilities and upgrades to the collection networks in 4 separate agglomerations in Ballyvourney/Ballmakeera, Dripsey, Innishannon and Coachford. Commissioning and testing of all works. The Operation Service requirements will include operation and maintenance of the WWTP and collections network (including pumping stations) up to a period of 7-years, with the option to extend by 3 years, following completion …
View the procurement » Mentioned suppliers:Electrical and Pump Services Ltd
2017-02-21Ringsend WwTP Retrofit Contract Stage 1 (Irish Water)
Ringsend Wastewater Treatment Plant (WwTP) treats most of the wastewater arising in the Greater Dublin Area. Irish Water is inviting tenders for a contract which will comprise the upgrading and retrofitting of between 8 and 11 of the upper deck tanks, and an aerobic granular sludge (AGS) biological treatment process (the Works) for which the Contracting Entity has already procured the proprietary Nereda® process.
Please refer to the PQQ for further details.
View the procurement »
2017-02-03Bandon Sewerage Scheme — Wastewater Treatment Plant Upgrade (Irish Water)
This project spans 2 separate site locations on the outskirts of Bandon town; the Glasslinn Road Pumping Station and the Bandon Wastewater Treatment Plant. The sites are currently inter-connected by 2no. rising mains with a new 350mm rising main to be constructed under the current contract.
Please refer to the PQQ for further details.
View the procurement » Mentioned suppliers:Electrical and Pump Services Ltd
2017-01-18Interceptor Cleaning Service (Dublin Bus / Bus Atha Cliath)
Dublin Bus require a service for the cleaning of interceptors.
The service involves the removal of contaminated sludge, silt, and oily surface films from the interceptors, traps, channels, and grilles at the various locations within our 7 Dublin City Garages as indicated on our service point listings. The interceptors, traps, channels, and grilles are to be serviced at the time intervals indicated on the service point listings.
Removal of all contaminated sludge, silt, and oily surface films collected …
View the procurement » Mentioned suppliers:Rilta Environmental
2016-02-24Dunlavin WwTW and Satellite Plants — Operation and Maintenance Contract (Ervia)
This scheme involves provision of services to areas in West Wicklow. It comprises
4 No wastewater treatment facilities, 2 No pump stations and associated
foul/combined waste water collection network. A drawing showing the location of
the proposed works is included in Appendix 3.
Scope of Works.
The services to be provided by the Contractor include but are not limited to the
following:
— Design-Build: Enabling works at Knockannana, Kiltegan and Rathdangan to
facilitate operation (instrumentation and …
View the procurement »
2015-09-04Enniscorthy Sewerage Scheme Phase 3: Contract 1 — Wastewater Treatment Plant Upgrade (Ervia)
Irish Water plan to undertake the following works:
— Refurbishment/Upgrade/Expansion of the existing Enniscorthy Wastewater Treatment Plant (WwTP).
— Refurbishment/Upgrade of the existing infrastructure at St Johns Pumping Station and Promenade Pumping Station.
— Provision of storm-water handling facilities.
It is intended that the works will be implemented under a Design, Build and Operate (‘DBO’) Contract.
View the procurement » Mentioned suppliers:Response/Ward and Burke JV
2014-03-14ENQEIR409 - Provision of Local Reserve (EirGrid plc)
The risk of a local shortage of generation adequacy is caused by restrictions on the transmission network. The Northern Ireland Authority for Utility Regulation (NIAUR) has written to SONI requesting it to explore arrangements, such as putting in place relevant System Support Services, to alleviate some or all of the risk identified. NIAUR has noted that any such arrangements should be time limited and that any additional costs of putting in place such measures should be reasonable and proportionate. …
View the procurement »
2013-12-19S104/DBO - Gweedore Sewerage Scheme - Phase 1 - Design/Build/Operate Works (Donegal County Council)
Expressions of interest are invited from suitably qualified applicants for the design, construction, commissioning, testing, operation and maintenance of the following works as part of the Gweedore Sewerage Scheme:
— upgrade and expansion of the an existing wastewater treatment plant to cater for a population equivalent of 6,000;
— new outfall pipeline from the wastewater treatment plant to an offshore discharge point in Gweedore Bay;
— a wastewater collection network comprising approximately 19km of …
View the procurement »
2013-10-01Enniscorthy Sewerage Scheme Phase 3 – Contract 1: Wastewater treatment plant Upgrade – DBO contract (Wexford County Council)
General Description
Enniscorthy Sewerage Scheme Phase 3 Contract 1: WWTP Upgrade DBO Contract (which is covered by these Pre- qualification documents) involves the following:
— Refurbishment, upgrade, expansion and construction on a Design Build and Operate basis, of the existing Enniscorthy WWTP.
— Refurbishment and taking in charge of the existing infrastructure at St Johns Pumping Station, Promenade Pumping Station and the respective rising/gravity mains to the Enniscorthy WWTP.
Design Build Works
— …
View the procurement »
2013-10-01Enniscorthy Sewerage Scheme Phase 3 – Contract 1: Wastewater Treatment Plant Upgrade (Wexford County Council)
General Description:
Enniscorthy Sewerage Scheme Phase 3 Contract 1: WWTP Upgrade DBO Contract (which is covered by these Pre-qualification documents) involves the following:
— Refurbishment, upgrade, expansion and construction on a Design Build and Operate basis, of the existing Enniscorthy WWTP.
— Refurbishment and taking in charge of the existing infrastructure at St Johns Pumping Station, Promenade Pumping Station and the respective rising/gravity mains to the Enniscorthy WWTP.
Design Build Works:
— …
View the procurement »
2013-08-28ENQEIR336 - Short Term Active Response (EirGrid plc)
STAR is an interruptible load type service in Ireland by which electricity consumers agree to have either their entire load or a portion of their load disconnected, without notice, during an under-frequency incident. STAR assists in the recovery of the power system frequency to normal operating conditions following the loss of a major generation in-feed to the power system. The TSO makes payment for the service based on the level of load that an electricity consumer makes available for interruption.
View the procurement »
2012-12-21Upper Liffey Valley Regional Sewerage Scheme - Contract No 1 - Osberstown WWTP Upgrade (Kildare County Council)
The contract consists of the expansion and upgrade of the
existing Osberstown waste water and sludge treatment
facility from a population equivalent of 80 000 to 130 000
while maintaining the existing operations and treatment
standards.
The Contracting Authority has determined their
requirements in respect of the treatment process and
general site layout. The Contractor will be required to
assume design responsibility for the Contracting Authority's
selected solution, complete the design, and then …
View the procurement »
2012-02-21Cavan Sewerage Scheme/Wastewater Treatment Plant Upgrade (Cavan County Council)
Expressions of interest are invited from suitably qualified contractors for the Cavan Sewerage Scheme – Wastewater Treatment Plant Upgrade. It is required to expand the existing wastewater treatment plant (WWTP) from a capacity of 20 565 population equivalent (PE) to a capacity of 30 000 PE. The Contract will be “Public Works Contract for Civil Engineering Works ” and shall include operation and maintenance of the existing wastewater treatment plant during construction and shall include a one year …
View the procurement »
2011-12-06Mutton Island WWTW - 20 Year Operation & Maintenance Contract with Design Build Upgrade (Galway City Council (Utility))
This Scheme involves the operation and maintenance of the Mutton Island WWTW for a period of 20 years and the upgrade of the existing plant from its current design capacity of 91 600 pe to 170 000 pe. The upgrade works will be carried out during the O&M contract period. The upgrade works are expected to be by means of alterations to the existing process as the current site is highly constrained. The operator will also be responsible for management and disposal of the sludge produced at the works.The …
View the procurement »
2011-08-29Lower Liffey Valley Sewerage Scheme - wastewater treatment plant upgrade (Kildare County Council)
Expresssions of interest are invited from suitably qualified contractors for the Lower Liffey Valley Sewerage Scheme - wastewater treatment plant upgrade. It is required to expand the existing wastewater treatment plant (WWTP) from a capacity of 80 000 population equivalent (PE) to a capacity of 150 000 PE. The contract will be "Designed by contractor" and shall include operation and maintenance of the existing wastewater treatment plant during construction and shall include a one year extended process …
View the procurement »
2011-08-17Mutton Island waste water treatment works - design build operate & maintain contract (Galway City Council)
This Scheme involves the upgrade of the existing Mutton Island WWTP from its current design capacity of 91 600 PE to 170 000 PE and the operation and maintenance of the plant for a period of 20 years. The upgrade works will be carried out during the O&M contract period. The upgrade works are expected to be by means of alterations to the existing process as the current site is highly constrained. The operator will also be responsible for management and disposal of the sludge produced at the works.The …
View the procurement »
2011-06-02Carbery Muskerry wastewater treatment plants DBO and O&M contract (Cork County Council)
This contract involves the upgrading of Clonakilty Wastewater treatment plant as a design build and operate contract.
This contract also involves the operation and maintenance of 12 additional wastewater treatment plants at the folowing locations: Bantry, Halfway, Kilmacsimon, Kilbrittain, Kilnamatyra, Aghabullogue, Rylane, Ladysbridge, Mogeely, Riverstick, Cloughduv, Ardgroom. Cork County Council reserves the right to include an additional 1 to 3 wastewater treatment plants to this list if they become …
View the procurement »