2021-10-11Requirement for Temporary Emergency Generation - 200MW (EirGrid plc)
The CRU, with the consent of the Minister for the Environment, Climate and Communications, has directed EirGrid under Regulation 28(10) of the Regulations, in our capacity as the transmission system operator, to secure the delivery of c. 200MW of emergency temporary generation from 2022
EirGrid is therefore seeking a Candidate(s) that can provide 200 MW of generation onto the transmission network by a target date of Q3 2022. (The provision of the fully operational generation is required for 3 years from …
View the procurement » Mentioned suppliers:ESB Generation & Wholesale MarketsHuntstown Power Company Limited
2021-03-15Control and Instrumentation Maintenance Resources Framework (Electricity Supply Board (ESB))
Control and instrumentation maintenance resources framework for ESB generating stations.
The work to be carried out is the provision of Instrumentation contractor resources for ongoing instrumentation maintenance at ESB Generating Stations.
A substantial amount of additional work may be in progress by other contractors at the same time therefore the contractor will be expected to undertake and commit to working closely with the engineer, whose approval will be required for access to specific work areas. …
View the procurement »
2020-03-13Tender for Supply, Install and Maintain Electric Vehicle Chargers for Laois County Council (Laois County Council)
As the uptake of electric vehicles in Ireland and across Europe increases significantly, the demand for Electric Vehicle (EV) charging services is also increasing. While there is a basic EV charging infrastructure in place across Ireland, there is a need to develop and expand the EV charging infrastructure network to further drive the uptake of EV use and make it easier for current and new EV users to reliably charge their vehicles.
In this regard Laois County Council has received funding for the …
View the procurement »
2019-09-06Samuel Beckett Civic Campus Phase 2: Electrical Services (Dun Laoghaire Rathdown County Council)
The site is located on Ballyogan Road, Carrickmines and is adjacent to the LUAS line.
Phase 1 included a sports and community building, sports pitches and surface car parks.
Phase 2 will expand on phase 1 and will include the following:
A. The change of use of the Phase 1 sports and community building to a library and community building;
B. Refurbishment of the existing sports building to create a new library;
C. The construction of a new sports building, incorporating a 25 m swimming pool, a children’s …
View the procurement »
2018-08-22Greenlink Interconnector Project (Greenlink Interconnector Limited)
Greenlink Interconnector Limited is developing a 500 MW HVDC interconnector system between the existing electricity grids in Ireland and Wales (UK). The interconnector will provide a new grid connection between Great Island transmission substation in County Wexford, Ireland and Pembroke transmission substation in South Wales. The Greenlink Interconnector cable route is approximately 205 km in length between the Pembroke Converter Station and the Great Island Converter Station of which 7 km is onshore in …
View the procurement »
2013-12-20FD/02/05/292 - Facilities Management Services (Irish Prison Service)
The Irish Prison Service (IPS) requires the provision of a
facilities management contract covering Mechanical and
Electrical planned and reactive maintenance.
Service provider must provide a fully managed service,
acting as a Prime Contractor with single point responsibility
for managing and delivering all the services at the specified
premises.
The scope of the contract shall be to provide a facilities
management service for the provision of specialist
contractor support with a managed service to cover …
View the procurement »
2012-11-01LIT Framework Agreements for the Provision of Electrical Maintenance Services (Limerick Institute of Technology)
LIT is issuing this contract notice inviting expressions of interest as the first stage of a two-stage process for appointment to three single-party framework agreements (“the Framework Agreements”) as follows:
Lot 1 Call Out Electrical Maintenance & Attendance Works – LIT Limerick.
Lot 2 Call Out Electrical Maintenance Works – LIT Thurles.
Lot 3 Call Out Electrical Maintenance Works – LIT Clonmel.
The purpose of the first stage is to obtain information from the applicants to determine their suitability …