2023-08-22   8498 - Corporate Power Purchase Agreement for Iarnród Éireann (Iarnrod Eireann-Irish Rail)
Call to competition by Iarnród Éireann (IÉ) for the procurement of financially-settled renewable electricity and the associated guarantee of origin certificates (GOs) via a newly built offsite corporate power purchase agreement (CPPA) View the procurement »
2023-07-17   Provision of Energy Saving Services (Maynooth University)
Maynooth University are looking to establish a partnership with a third party to develop, design and deliver an improved energy management system using the most economically advantageous, behind the meter solutions available. These improvements would be through upgrading on present technologies and the incorporation of emerging renewable technologies and solutions. The candidate must be an obligated party under the SEAI Energy Efficiency Obligation Scheme (EEOS). The term of the partnership will be for 5 … View the procurement »
2023-07-17   ENQEIR841 Low Carbon Inertia Service Procurement – Phase 1 (EirGrid plc)
The purpose of the Pre-Qualification Questionnaire (PQQ) is to invite qualification applications from interested parties for the provision of a Low Carbon Inertia Service. This document provides a detailed description of the scope of requirements for the service we wish to procure. It also provides information about the selection procedure being used to qualify Candidates. The objective of this PQQ process is to produce a short-list of suitably qualified Candidates who will be invited to tender for the … View the procurement »
2023-06-30   The establishment of an Energy Performance Contract for Seven Cork City Council buildings (Cork City Council)
The Council is interested in exploring carbon emission reduction measures for seven of its buildings by way of an Energy Performance Contract (EPC). These include: 1. Leisureworld Churchfield 2. Leisureworld Sam Allen Pitches 3. Wilton Library, Bishopstown 4. Cork City Archives 5. The Glen Resource Centre 6. Mahon Golf Club* 7. Ballyvolane Fire Station View the procurement »
2023-05-15   Consultancy Services for Single Point of Contact (Renewable Energy) for SEAI (Sustainable Energy Authority of Ireland)
The objective of this RFT is to invite proposals from suitably qualified service providers to research the role of the Single Point of Contact (Renewable Energy) as defined by existing and upcoming EU legislation and examine how this role might best add value to the licensing and permitting system and contribute towards the achievement of the overall aim, which is to speed up the deployment of energy from renewable sources. The final deliverable from this service will be a suite of detailed options for … View the procurement »
2021-10-11   Requirement for Temporary Emergency Generation - 200MW (EirGrid plc)
The CRU, with the consent of the Minister for the Environment, Climate and Communications, has directed EirGrid under Regulation 28(10) of the Regulations, in our capacity as the transmission system operator, to secure the delivery of c. 200MW of emergency temporary generation from 2022 EirGrid is therefore seeking a Candidate(s) that can provide 200 MW of generation onto the transmission network by a target date of Q3 2022. (The provision of the fully operational generation is required for 3 years from … View the procurement »
Mentioned suppliers: ESB Generation & Wholesale Markets Huntstown Power Company Limited
2021-02-03   Vision 2030 Partner Framework (EirGrid plc)
The purpose of the Pre-Qualification Questionnaire (PQQ) is to invite qualification applications from interested parties for the provision of consultancy advisory services, technical and economic studies, technical consulting and managed services under a multi-party supplier framework agreement. Candidates are invited to submit a qualification application for inclusion on the tender list for one or more or all of the applicable Lots in accordance with the PQQ. Lot 1: Network Advisors Lot 2: Future … View the procurement »
Mentioned suppliers: (2) Powertech Labs, Inc. Accenture Limited AFRY Management Consulting Limited / (AFRY MC) Cesi S.P.A. DNV GL Netherlands B.V. Enzen Global Ltd. Ernst & Young Guidehouse Netherlands B.V. Mott Macdonald Ireland Power System Consultants UK Limited RTE INTERNATIONAL Smith Institute Stantec UK Limited Version 1 WSP UK Ltd
2020-08-05   DPS for the Provision of Goods and Services for Energy and Climate Action Consultancy Projects and for the Provision... (3 Counties Energy Agency)
The 3 Counties Energy Agency (‘3CEA’) (the ‘Contracting Authority’) is issuing this request for applications to participate (‘RFATP’) in a Dynamic Purchasing System (‘DPS’) on its own behalf and on behalf of other agencies and public bodies such as SEAI Sustainable Energy Communities, members of the Association of Irish Energy Agencies (AIEA), One-Stop-Shops under the aegis of the National Retrofit Delivery Body, local authorities and LEADER companies. The DPS will be coordinated and managed by the 3CEA. View the procurement »
2020-05-29   Inclusion on a Framework Agreement for Provision of Grid Services to Coillte’s Renewable Energy Business (Coillte CGA)
Coillte wishes to appoint a framework of grid consultants to provide advice and support related to the grid connection, substation design, electrical balance of plant (EBOP) and civil balance of plant (CBOP) of various renewable energy and energy storage projects, and associated electrical infrastructure. To this end we now invite suitably qualified candidates to express an interest in this competition in respect of the areas of expertise (lots) outlined in the summary document attached. Please note that … View the procurement »
2018-11-19   Soliciting Interest to Invest in Coillte's Bio Energy Opportunity (Coillte CGA)
Coillte is inviting potential investors to bring forward proposals for a 50:50 co-development partnership (as outlined in the summary document attached) to participate in this opportunity, and to fully develop the proposal with Coillte through inception and development of the full proposal, and subject to agreement by all parties the delivery and operation of the proposal. Please find attached a summary document which provides further details of the opportunity. Coillte intends to use a competitive … View the procurement »
2017-12-28   Supply of a test site and testing services to optimise and demonstrate performance of power generations from a... (Design Pro Ltd)
The company requires test facilities and support services to assist with scale up, testing, power offtake integration, performance optimisation, output validation, environmental impact validation and staff training to demonstrate the power generation capabilities and performance of a 60 kW hydrokinetic turbine in a commercially relevant environment. The company requires river or estuary testing facilities with associated support services to demonstrate the full functionality of an operational grid … View the procurement »
2017-09-29   Control & Instrumentation Resources for Moneypoint Overhauls 2018-2019 (Electricity Supply Board ( ESB ))
GWM7081 Control & Instrumentation Resources for Moneypoint Overhauls 2018-2019. View the procurement »
Mentioned suppliers: Enva Ireland Limited
2017-07-12   Testing and validation services in respect of power generation via hydrokinetic turbine (Design Pro Ltd)
Provision of testing berth in a river or estuary with a suitable water flow, together with corresponding testing and analytical services, to document operational and environmental performance characteristics (including electrical power generation) from a 25kW hydrokinetic turbine device. Testing will commence in the 4th quarter of 2017 and run for a period of up to 6 months. Test facilities to include a mooring berth, deployment, extraction and storage facilities, workshop and office accommodation, power … View the procurement »
Mentioned suppliers: Seeneoh
2016-06-28   Moneypoint SCR Catalyst Regeneration Services (Electricity Supply Board (ESB))
Framework agreement for the supply of Catalyst Regeneration services to ESB Moneypoint to cover the years 2017 to 2019 inclusive. In the period from 2017-2019 ESB foresee a requirement to commence a regeneration program of several of the existing SCR Catalyst Layers. This contract will include for the transport of the Catalyst modules to and from Moneypoint Generating Station, Kilrush, Co. Clare. View the procurement »
Mentioned suppliers: Ebinger Katalysatorservice GmbH & Co. KG
2015-12-21   GWM4277 Moneypoint Unit 2 SCR New Catalyst Layers (ESB)
The contract is for the supply of honeycomb catalyst layers for one 285MWe coal fired boiler at Moneypoint Generating Station. The layers will be installed in a high dust SCR plant. There are two SCR reactors per unit which are situated between the economiser and the airheaters. Each Reactor has three layers of honeycomb catalyst currently installed (Layer 1, 2 and 3), with each Reactor Layer made up of 42 individual catalyst modules comprising a total catalyst volume of approx. 78 m. View the procurement »
Mentioned suppliers: Cormetech Inc.
2015-03-20   Thermal Energy Efficiency Project (Irish Prison Service)
The project aims are to provide for the upgrade of the West Dublin Campus, thermal distribution and hot water systems to reduce the campus thermal energy profile in keeping with the public body requirements from Government to reduce energy consumption by 33 % by 2020. To provide an energy efficient system to achieve the thermal comfort of all persons using the building and to provide this by means of a energy performance based contract, which will provide the guarantees necessary to fund the project … View the procurement »
2014-05-20   Pre qualification questionnaire (PQQ) response document for the Provision of Energy Service Company (ESCO) (Health Service Executive (HSE))
Installation of wood fuelled boilers at Roscommon County Hospital and the Sacred Heart Hospital Roscommon And Installation of a wood fuelled boiler and energy retrofits in the swimming pool, public areas and housing units at Aras Attracta, Swinford, Co. Mayo. View the procurement »
2011-09-16   Request for proposals for land sale for the provision of a centralised alternative energy centre (IDA Ireland)
It is IDA Property Division’s intent to enable, in conjunction with the private sector, centralized alternative energy centres at specific locations throughout its property portfolio in Ireland. The first of these locations is Letterkenny business and technology park where a site within the park of up to 3 hectares (7,4 acres) is being made available to purchase for the purpose of creating a centralized alternative energy centre. A condition of the sale is that the project must include the provision of a … View the procurement »
2011-05-30   PG108T778 Moneypoint SCR New Catalyst Layers (ESB Power Generation)
The contract is for the supply of honeycomb catalyst layers for three 305MWe coal fired boilers at Moneypoint Generating Station. The layers will be installed in a high dust SCR plant. There are two SCR reactors per unit which are situated between the economiser and the airheaters.There are two layers of honeycomb catalyst currently installed in each reactor. This work is likely to include supply of honeycomb catalysts in the order of 78m3 volume per layer. Two new layers will be required per unit. Also … View the procurement »
Mentioned suppliers: Cormetech, Inc.