2019-07-0518/167 — Transmission Pipeline Emergency Response and Repair Services (Ervia)
Provision of emergency response and repair services including materials and equipment for the natural gas high-pressure onshore Ireland transmission network located in the Republic of Ireland (Refer to Appendix 3 of this PQQ for general network map).
Gas Networks Ireland (GNI) requires a single supplier agreement to provide the services as outlined in the scope of work.
For more information please refer to PQQ Document.
View the procurement » Mentioned suppliers:National Gas Transmission Plc
2018-09-18Retrofit Excess Flow Valves (Ervia)
A Single Party Framework Agreement for the manufacturing and/or supply of Retrofit Excess Flow Valves (REFVs) and associated equipment for Gas Networks Ireland.
Applicant shall note that if they are appointed to the Framework Agreement, they will be required to supply either directly to the Gas Networks Ireland or at the Contracting Entity's sole discretion, to the Contracting Entity’s Agents or other authorised contractors on the same terms to the terms of the Framework Agreement.
All Applicants to …
View the procurement » Mentioned suppliers:SA Banides Et Debeaurain
2018-09-05Provision of Odorant Intensity Assessor Services to GNI (Ervia)
The scope of this contract is for a single-supplier Framework Agreement covering the Republic of Ireland and Northern Ireland for the analysis of natural gas samples for the determination of odorant concentrations.
The scope of contract required will involve providing suitably qualified personnel and appropriate laboratory and equipment for the following:
— analysis of natural gas samples taken from the Gas Networks Ireland (GNI) network to determine odour content concentration and calculation of odour …
View the procurement » Mentioned suppliers:TMS Environment Ltd
2018-01-10Center Parcs Gas Feeder Main Project (Ervia)
Works contract for the construction of approximately 21 km of 400 mm PE feeder main gas pipeline and all associated ancillaries (e.g. smaller diameter pipeline and commissioning works) from Ories AGI in Co. Westmeath to Rathmore Co. Longford (more detailed description of scope is contained in the ITT section 1.1 of Part 3- Scope).
View the procurement » Mentioned suppliers:GMC Utilities Group Ltd
2016-11-03Gas to Listowel (Ervia)
This works contract will be for the construction and commissioning of a distribution gas feeder main pipeline to Listowel Town Co. Kerry from Craggs Co. Limerick and include the installation of gas network and associated connections.
View the procurement » Mentioned suppliers:Murphys/GMC
2014-10-23Gas to Wexford Town (Bord Gáis Éireann/Ervia)
This works contract will be for the construction and commissioning of a utility gas network to Wexford Town from Campile Co. Wexford and include the installation of gas network and potentially, the upgrade of some of existing water network at specific locations in Wexford Town. The contract has been subdivided into the following Lots: Lot 1 — Gas Feeder Main, Lot 2 — Wexford Town Gas Network & Lot 3 — Wexford Town Gas & Water Network.
View the procurement » Mentioned suppliers:Roadbridge
2012-12-03RT12_039 - Firmus Energy Construction and Maintenance Works and Services Contract (Bord Gais Eireann)
Firmus energy is currently undergoing the construction of a gas network and associated connections to natural gas within a number of townlands in Northern Ireland including Londonderry, Limavady, Coleraine, Ballymoney, Ballymena, Antrim, Craigavon (including Lurgan and Portadown), Armagh, Banbridge and Newry.
Against this background we will shortly be inviting tenders for a number of services in Northern Ireland, to include: polyethylene mains and service laying; emergency response; materials logistics.
View the procurement »
2011-01-28Pipeline to Great Island Power Station, Co. Wexford (Bord Gais Eireann)
Bord Gáis Éireann is seeking applications from suitably experienced contractors to construct a natural gas pipeline from Baunlusk AGI near Co. Kilkenny to Great Island Power Station, Co. Wexford. The pipeline length is approximately 45 km. The diameter of the pipeline is in a range of 300 mm to 500 mm. The majority of this pipeline will be located in a cross country environment. The project also involves modifications to the existing AGI’s and inclusion of block valve(s) along the route. The scope of …