Recent procurements by ESB Power Generation

2012-04-02   PG108T802. Supply of lubricants/lubrication services as required to ESB generating stations (ESB Power Generation)
ESB has a requirement for the supply and delivery of various grades of turbine oils and general lubrication currently being used in all ESB generating stations, and to provide for routine testing of turbine oils and a general lubrication service during their operational life. There is also a requirement for a total lubrication management service (to include supply, testing and on site lubrication service) in a number of our generating stations. View the procurement ยป
2012-03-30   PG108T807 waste management services ESBEI generation (ESB Power Generation)
Management of waste in ESBEI generating stations. The scope covers: 1. Hazardous waste management; 2. Non hazardous waste management; 3. Combined hazardous and non hazardous waste management. The contract will include for the management of documentation in accordance with Waste Management Act 1996 and subsequent regulations, development of waste management strategies towards best practice environmentally and financially, codification of waste in accordance with EWC. View the procurement ยป
Mentioned suppliers: Advanced Environmental Solutions (Ireland) Ltd Enva Ireland Ltd
2011-09-30   PG108T790 Provision of Security Services at Various ESB Generating Stations (ESB Power Generation)
ESB requires manned security guarding / patrolling services to be provided at five of its Generating Stations. The stations are 1/ Ardnacrusha, 2/ Erne, 3/ Turlough Hill, 4/ Lough Ree, 5/ West Offaly. The final contract may be divided into lots. Details of these lots will be specified in the tender documents and finalised during the ensuing tender assessment process. The award of the respective lots will be at ESB Generation's sole discretion. ESB requires interested parties to supply all the information โ€ฆ View the procurement ยป
Mentioned suppliers: Brinks Ireland Limited
2011-08-15   PG108T783 Gantry crane refurbishment in hydro stations (ESB Power Generation)
The ESB wishes to carry out refurbishment and upgrade work to 7 indoor gantry cranes in various Hydro generating station located throughout Ireland. The cranes range in size from 18 to 100ton with auxiliary hoists attached and range in vintage from 1920 to 1950. The scope of work will include assessment, mechanical refurbishment, electrical refurbishment/modernisation, commissioning, load testing and certification. View the procurement ยป
2011-05-30   PG108T778 Moneypoint SCR New Catalyst Layers (ESB Power Generation)
The contract is for the supply of honeycomb catalyst layers for three 305MWe coal fired boilers at Moneypoint Generating Station. The layers will be installed in a high dust SCR plant. There are two SCR reactors per unit which are situated between the economiser and the airheaters.There are two layers of honeycomb catalyst currently installed in each reactor. This work is likely to include supply of honeycomb catalysts in the order of 78m3 volume per layer. Two new layers will be required per unit. Also โ€ฆ View the procurement ยป
Mentioned suppliers: Cormetech, Inc.
2011-04-15   PG108T772 - Site Haulage Moneypoint Generating Station (ESB Power Generation)
The operational process in Moneypoint Generating Station requires the transport of material from each of the following processes on Moneypoint site - Ash haulage from the ash hoppers to the ash disposal area and Flue Gas Desulphurisation (FGD) by-product haulage from FGD by-product hopper in Coalyard to adjacent landfill area. This tender enquiry provides for the hire of suitable trucks, vibrating roller and excavator to transport and manage the above. The hire of trucks and other plant may be required โ€ฆ View the procurement ยป
Mentioned suppliers: L&M Keating Ltd Matthew Bermingham
2011-03-23   PG108T773 - Booster Fan Motors Moneypoint (ESB Power Generation)
The contract is for the supply of up to four 6.6kV industrial motors as per the criteria outlined below (all values indicative only). Prospective tenderers should have experience in design and manufacturer of these motors and be able to provide on site technical assistance for the installation. The function of these motors is to drive a centrifugal fan which is directly coupled. The motors will be required to carry out multiple starts within a one hour period. Power 5000kW. Voltage 6600V. Insulation โ€ฆ View the procurement ยป
Mentioned suppliers: Teco Electric Europe Ltd.