2021-11-04   Remote Terminal Units (RTUs) for EirGrids Supervisory Control and Data Acquisition (SCADA) (EirGrid plc)
EirGrid's Energy Management System (EMS) is connected to approximately 300 Remote Terminal Units (RTUs) and 70 Substation Control Systems (SCS). The RTUs are installed at Transmission and Generation Stations, including windfarm sites and provide Supervisory Control and Data Acquisition (SCADA) to the EMS. The objective of this Pre-Qualification Questionnaire (PQQ) process is to produce a short-list of suitably qualified companies who would be invited to tender for the supply of Transmission Utility SCADA … View the procurement »
Mentioned suppliers: MIKRONIKA Sp. z o.o.
2020-06-16   Turnkey Delivery of High Voltage Electrical Substations in the Republic of Ireland Pursuant to a... (Electricity Supply Board (ESB))
The contracting entity intends to procure a multi-supplier/contractor framework agreement for the turnkey delivery of high voltage substations in the Republic of Ireland. Refer to section A.1.1 of the PQQ for a general description of the proposed scope of the framework. View the procurement »
Mentioned suppliers: ABB Power Grids Ireland Limited H&MV Engineering Ltd Linxon UK Limited Mace Technology [Ireland] Limited... Siemens Energy Ltd Siemens Energy Ltd (Consortium Lead) &... Suir Engineering Ltd
2020-05-29   Inclusion on a Framework Agreement for Provision of Grid Services to Coillte’s Renewable Energy Business (Coillte CGA)
Coillte wishes to appoint a framework of grid consultants to provide advice and support related to the grid connection, substation design, electrical balance of plant (EBOP) and civil balance of plant (CBOP) of various renewable energy and energy storage projects, and associated electrical infrastructure. To this end we now invite suitably qualified candidates to express an interest in this competition in respect of the areas of expertise (lots) outlined in the summary document attached. Please note that … View the procurement »
2019-04-30   Turnkey Delivery of 220 kV GIS Substation in the Dublin Region (Electricity Supply Board (ESB))
Turnkey Ddelivery of 220 kV GIS substation in the Dublin Region. View the procurement »
Mentioned suppliers: Siemens Ltd
2017-07-19   Transmission Utility SCADA Equipment (EirGrid plc)
EirGrid's Energy Management System (EMS) is connected to approximately 260 Remote Terminal Units (RTUs) and 60 Substation Control Systems (SCS). The RTUs are installed at Transmission and Generation Stations, including windfarm sites and provide Supervisory Control and Data Acquisition (SCADA) to the EMS. The objective of this Pre-Qualification Questionnaire (PQQ) process is to produce a short-list of suitably qualified companies who would be invited to tender for the supply of Transmission Utility SCADA … View the procurement »
Mentioned suppliers: Schneider Electric Ireland
2017-02-13   Maintenance of 38kV Equipment in Traction Substations (Iarnrod Eireann-Irish Rail)
Iarnród Éireann (IÉ) requires the services of a suitably qualified Electrical Contractor to carry out maintenance on the 38kV equipment in Traction Substations located throughout the IÉ Rail Network. View the procurement »
Mentioned suppliers: O'Hara Engineering Electrical Maintenance
2012-07-05   Landfill Gas Plant at Drehid (Bord Na Mona)
Bord na Móna seeks expressions of interest from suitably qualified companies to design, supply, install, commission and maintain a landfill gas for electricity generation plant with a total output of circa 5.6MW. The contract will involve a complete turnkey solution involving civil works, supply, installation and maintenance of LFG generator sets, switchgear, gas regulation equipment, flares and utility equipment. Please note that this is the prequalification stage of a competition and full detailed … View the procurement »
2011-05-23   Remote terminal unit (RTU) supply (EirGrid plc)
Supply and delivery in the Republic of Ireland of 50 – 100 remote terminal units (RTUs) over a 5 year period, in batches commencing 3 months after awarding of the contract. Supply of software/hardware tools required to centrally manage the RTU configuration database and to configure and maintain the RTU equipment. Ongoing technical support of all supplied equipment and software over the period of supply as well as certifying EirGrid or its agents to carry out maintenance work. Note: to register your … View the procurement »
Mentioned suppliers: Siemens Energy