Procurements: Civil engineering support services (page 5)
2014-06-12Bantry Inner Harbour Phase 1 - Establishment of an Engineering Service Level Agreement for the Design and... (Port of Cork Company)
The former Bantry Bay Harbour Commissioners had retained RPS Consulting
Engineers to develop a scheme entitled “Bantry Inner Harbour Development”.
A Preliminary report was produced and presented to the Commissioners in February 2011. A redacted version of this report, together with the Site
Investigation factual report is attached in Annex 1.
Planning consent for the project was received from Cork County Council in August 2013 and full details of the planning documentation in relation to the application …
View the procurement »
2014-04-24FRT R&T 14- - Multiparty Framework Agreement for Consultancy Services for Coastal Protection Strengthening and Repairs (Galway County Council)
Galway County Council ('the Contracting Authority') has identified an on-going need for the services of consulting Engineers in connection with the provision of consultancy services in relation to forthcoming works as a result of damage to public infrastructure following the severe weather in January and early February 2014 and for improvements in coastal protection. The areas of work is on the coastal areas of county galway and islands.
GCC proposes to establish and operate a Framework Agreement for the …
View the procurement »
2014-03-28Civil Works Balance of Plant for Coillte Sliabh Bawn Wind Farm Project (Coillte Teoranta)
Coillte wishes to invite expressions of interest from suitably qualified candidates for civil works balance of plant in relation to its Sliabh Bawn wind farm project. Further information is available in the following documents which are attached to this notice: 1. Expression of interest document 2. Pre Qualification Questionaire document. In order to be considered for this competition candidates must complete the pre-qualification questionnaire requirements and return by the deadline date stated.
View the procurement »
2013-05-28Motorway Contracts Audit and Adminstration Services (National Roads Authority)
- Provision of supervision, monitoring, audit and consulting engineering services in relation to the three Motorway Maintenance and Renewal Contracts (MMaRC), operation stage of PPP Contracts and other contracts relating to network operations.
- Anticipated duration of the Contract is 48 months, with a possible extension, at the sole discretion of the Authority, for a further 24 months.
View the procurement » Mentioned suppliers:WS Atkins Ireland Limited
2013-04-25Technical Advisory Services M11 Gorey to Enniscorthy PPP Scheme (National Roads Authority)
The provision of technical advice and support services to the Contracting Authority during the design, procurement, construction, handover and dispute resolution stages of the M11 Gorey to Enniscorthy Public Private Partnership Scheme.
The M11 Gorey to Enniscorthy Scheme is a realignment of the N11 National Primary Route from south of Gorey (Clogh) to south of Enniscorthy (Oilgate). The realigned route will comprise of the provision of approximately 26km of M11 mainline along with approximately 1km of …
View the procurement » Mentioned suppliers:Halcrow Barry
2013-04-12Technical Advisory Services N25 New Ross Bypass PPP Scheme (National Roads Authority)
The provision of technical advice and support services to the Contracting Authority during the design, procurement, construction, handover and dispute resolution stages of the N25 New Ross Bypass Public Private Partnership Scheme.
The N25 New Ross Bypass Scheme involves the construction of approximately 14.8 km of National Route comprised of approximately 13.6 km of Dual Carriageway and approximately 1.2 km of Single Carriageway and associated works.
The services to be provided include Technical (Tender) …
View the procurement » Mentioned suppliers:Mott MacDonald Ireland Ltd.
2013-03-05Carrigrennan WWTW - Carrigrennan Wastewater Treatment Works Upgrade - Consultant Contract Planning Stage (Cork City Council)
Carrigrennan WWTP (Wastewater Treatment Plant) is located at Little Island, Co. Cork. The plant treats wastewater from Cork City and surrounding areas in the County.
The plant was commissioned in 2004 with a design organic load capacity of 413 000 population equivalent (p.e.).
The plant was designed to ensure compliance with the Urban Wastewater Directive. It provides primary and secondary treatment. Secondary treatment is achieved by means of a cyclical activated sludge system which is
carried out in …
View the procurement »
2012-06-29Framework for owners/resident engineer for Dev. & construction of BG (energy) wind farms (Bord Gais Eireann)
Multi supplier framework for owners/resident engineer role for the development and construction of Bord Gáis (energy) Wind Farms. It is anticipated that the proposed owners/resident engineer works relating to Bord Gáis (energy) wind farm developments that may be procured by Bord Gáis (energy) (or a subsidiary of Bord Gáis (energy)) under the framework will be at various locations throughout Ireland and Northern Ireland. To meet its requirements for the services of an owners/resident engineer for the …
View the procurement »
2012-06-01Client's Representative for Construction and Commissioning Phases of Dublin Waste to Energy Facility (Dublin City Council)
Dublin City Council wishes to engage a multi-disciplinary, competent and suitabily experienced Consultant to act as Client's Representative for the Construction and Commissioning Phases of the Dublin Waste to Energy Facility.
NOTE: To register your interest in this notice and obtain any additional information please visit the eTenders Web Site at http://www.etenders.gov.ie/Search/Search_Switch.aspx?ID=418092.
View the procurement »
2012-04-27Kerdiffstown Landfill Remediation Project - Environmental Services (Environmental Protection Agency)
The landfill and waste facility at Kerdiffstown has closed and is now undergoing the early stages of a clean-up or ‘remediation’ process. The Environmental Protection Agency (EPA) is using powers under the Waste Management Act 1996 (as amended) to restore the site and put in place appropriate aftercare measures to prevent and limit pollution from the materials on the site.
The site consisted of an extensive recycling facility, now partly dismantled, an authorised lined landfill that had been partially …
View the procurement »