2022-04-15   Civil Works associated with Live Substations in the Republic of Ireland under a multi-contractor Framework Agreement (Electricity Supply Board ( ESB ))
The Contracting Entity intends to procure a multi-contractor Framework Agreement for the delivery of civil works associated with Live substations in the Republic of Ireland. It is proposed that the multi-contractor Framework Agreement scope of works will include services and installation/upgrading of civil and building works. Refer to section A.1.1 of the PQQ for a more detailed description of the works. View the procurement ยป
2020-06-16   Turnkey Delivery of High Voltage Electrical Substations in the Republic of Ireland Pursuant to a... (Electricity Supply Board (ESB))
The contracting entity intends to procure a multi-supplier/contractor framework agreement for the turnkey delivery of high voltage substations in the Republic of Ireland. Refer to section A.1.1 of the PQQ for a general description of the proposed scope of the framework. View the procurement ยป
Mentioned suppliers: ABB Power Grids Ireland Limited H&MV Engineering Ltd Linxon UK Limited Mace Technology [Ireland] Limited... Siemens Energy Ltd Siemens Energy Ltd (Consortium Lead) &... Suir Engineering Ltd
2020-05-29   Inclusion on a Framework Agreement for Provision of Grid Services to Coillteโ€™s Renewable Energy Business (Coillte CGA)
Coillte wishes to appoint a framework of grid consultants to provide advice and support related to the grid connection, substation design, electrical balance of plant (EBOP) and civil balance of plant (CBOP) of various renewable energy and energy storage projects, and associated electrical infrastructure. To this end we now invite suitably qualified candidates to express an interest in this competition in respect of the areas of expertise (lots) outlined in the summary document attached. Please note that โ€ฆ View the procurement ยป
2019-04-30   Turnkey Delivery of 220 kV GIS Substation in the Dublin Region (Electricity Supply Board (ESB))
Turnkey Ddelivery of 220 kV GIS substation in the Dublin Region. View the procurement ยป
Mentioned suppliers: Siemens Ltd
2018-01-05   Establishment of a Single Operator Framework for Enabling Works; The National Maternity Hospital at St Vincent's... (Health Service Executive (HSE))
The works relate to the creation of a single operator to deliver a series of enabling works in connection with The NMH relocation to the campus of SVUH. Such works will include but are not limited to, the following: 1) The provision of temporary service supplies including laboratory gases, N2O, LTHW, etc., and all associated works; 2) The provision of permanent service supplies including M, LV, FA, Oil, NG, Comms, etc., and all associated works; 3) Decommissioning of existing services and associated โ€ฆ View the procurement ยป
2016-11-21   Limerick Gasworks Remediation _Phase 2 (Soil Stabilisation/ Solidification) (Ervia)
Design of soil binder mixes and implementing Soil Stabilisation and Solidification works to contaminated soils 3 m deep over a 1.4 ha site based on this design. View the procurement ยป
2012-07-05   Landfill Gas Plant at Drehid (Bord Na Mona)
Bord na Mรณna seeks expressions of interest from suitably qualified companies to design, supply, install, commission and maintain a landfill gas for electricity generation plant with a total output of circa 5.6MW. The contract will involve a complete turnkey solution involving civil works, supply, installation and maintenance of LFG generator sets, switchgear, gas regulation equipment, flares and utility equipment. Please note that this is the prequalification stage of a competition and full detailed โ€ฆ View the procurement ยป