2022-03-29The Design and Build of 400kV Shannon Estuary Cable Project (Electricity Supply Board ( ESB ))
The Contracting Entity intends to procure a Contract for the Design and Build of 400kV Shannon Estuary Cable Project.
The Contracting Entity requires the manufacture and installation of a 400kV land and subsea cable circuit in the South of Ireland. The new 400 kV cable circuit is required to be installed in the Shannon Estuary and adjoining lands to connect Moneypoint 400 kV Gas Insulated Switchgear (GIS) Substation to a 400kV Air Insulated Switchgear (AIS) compound within Kilpaddoge 220 kV โฆ
View the procurement ยป
2018-08-22Greenlink Interconnector Project (Greenlink Interconnector Limited)
Greenlink Interconnector Limited is developing a 500 MW HVDC interconnector system between the existing electricity grids in Ireland and Wales (UK). The interconnector will provide a new grid connection between Great Island transmission substation in County Wexford, Ireland and Pembroke transmission substation in South Wales. The Greenlink Interconnector cable route is approximately 205 km in length between the Pembroke Converter Station and the Great Island Converter Station of which 7 km is onshore in โฆ
View the procurement ยป
2017-10-31ROV Umbilical (Marine Institute)
At present a requirement exists for the supply, installation and commissioning of a replacement umbilical of 4 300 m for the Institute's deep water ROV Holland 1.
The umbilical will be used with the ROV Holland 1 in a free boating/live boating mode and will require installation on the existing ROV umbilical winch. The tender requires the supply of the umbilical cable, adjustment of the existing winch drum to accommodate a smaller size umbilical, adjustment of spooling mechanism and spooling of the new โฆ
View the procurement ยป Mentioned suppliers:Soil Machine Dynamics Limited
2016-01-22Cables and Connectors for Marine Test Site (Marine Institute)
The Marine Institute wishes to invite Applicants to submit a tender under an Open Procedure with the objective of putting a Single Supplier Framework Agreement in place for the design, manufacture and supply of Cables and Connector Units for the Galway Bay Marine and Renewable Energy Test Site for a period of 2 years (2016-2018). 1 unit of cables and connector to be delivered by end of August 2016, with additional unit(s) dependant on available funding. The Marine Institute is seeking design, manufacture โฆ