Short description
Irish Water is currently advancing the Lough Mask Regional Water Supply
Scheme โ Water Treatment Plant Upgrade Design Build Operate Contract
comprising the upgrade and expansion of the existing raw water intake works and
water treatment plant to achieve a treated water output of 54 000 mยณ/day. The
existing water treatment plant is capable of a treated water output of
38 000 m3/day.
The works required under the contract are to be delivered on a Contractor Design-
Build-Operate basis. The DBO contract is approx. 18 months Design and Build
including a process proving period and with a 1 year Operation and Maintenance
period.
The planned works are necessary to ensure compliance with EU Directives, Irish
National Standards and Regulations relating to treated water for human
consumption.