2019-11-25   Civil Balance of Plant (CBOP) Contract for Oweninny Phase 2 Wind Farm (Oweninny Power 2 DAC)
Oweninny Power 2 DAC, the contracting entity, is a joint venture company formed between Bord na Mรณna Energy Ltd and ESB Wind Development Ltd. Oweninny Power DAC has developed the first phase of a Wind Farm at Oweninny, Bellacorick, Co. Mayo. The contracting entity now intends to procure works, supplies and services related to civil balance of plant for the Oweninny Phase 2 wind farm project. Oweninny Phase 2 wind farm is an 83MW project located adjacent to the existing 89MW Oweninny Phase 1 Project. The โ€ฆ View the procurement ยป
Mentioned suppliers: Roadbridge Ltd
2018-12-18   GCC01-2018, Galway County Council Framework for Pavement & Associated Minor Works on National Roads (Galway County Council)
The Procuring Authority on behalf of Galway County Council wishes to establish and operate a multi-supplier Framework Agreement for the provision of pavement and associated minor works for Transport Infrastructure Ireland (TII) funded road schemes. View the procurement ยป
Mentioned suppliers: Harrington Concrete and Quarries John Madden and Sons Ltd Lagan Asphalt Ltd McGraths Limestone (Cong) Ltd Michael O Malley Tarmacadam Contractors Ltd Priority Construction Ltd Roadbridge Ltd Roadstone Ltd
2018-12-11   Ballycoolen to Forrest Little and Ballycoolen to Ratoath Trunkmain Scheme (Irish Water)
โ€” Lot 1 Ballycoolen to Forrest Little Trunkmain Scheme: It has been identified that a new trunk main is required to augment the supply to North County Dublin and to ensure security of supply, โ€” Lot 2 Ballycoolen to Ratoath Trunkmain Scheme: It has been identified that a new regional trunk main is required to enable the transfer of available treated water between the Greater Dublin Area and Meath. View the procurement ยป
Mentioned suppliers: Roadbridge Ltd
2016-03-18   Upper Liffey Valley Regional Sewerage Scheme Contract 2A Networks (Ervia)
Irish Water plan to undertake the construction of a new sewerage collection network from Kilbelin in Newbridge to Osberstown WwTP including gravity sewers, 3 No new pumping stations, 3 No new storm tanks and rising mains. The project will convey flows from Newbridge, reducing storm water overflows to the River Liffey, to Osberstown WwTP. View the procurement ยป
Mentioned suppliers: Roadbridge Ltd