Procurements: Connaught Airport Development Company Ltd

3 archived procurements

Recent procurements by Connaught Airport Development Company Ltd

2025-07-04   IWA Solar Farm (Connaught Airport Development Company Ltd)
This project involves the design, construction, and commissioning of a new Solar Photovoltaic Farm to supply 1MVA of renewable energy directly to Ireland West Airport. The initiative supports the airportโ€™s sustainability goals by reducing reliance on grid electricity and lowering carbon emissions. The contract will be delivered under a Design and Build model, followed by a 24month Operation and Maintenance phase to ensure optimal performance and reliability of the system. The scope of works includes Full โ€ฆ View the procurement ยป
2024-09-12   Single Party Framework Agreement for Provision of an Electric Vehicle Tractor Unit and Bulk Fuel Bowser and... (Connaught Airport Development Company Ltd)
A competitive process under the negotiated procedure for the establishment of a framework agreement for the supply, testing, commission and training of an electric vehicle tractor unit and bulk fuel bowser and and associated vehicles and Plant required to maintain the operational readiness for Irish West Airport Knock. The framework agreement will be established on foot of a competition for an initial contract for an Electric Vehicle Tractor Unit and Bulk Fuel Browser .The initial contract will be โ€ฆ View the procurement ยป
2023-07-26   IWAK RWY26 RESA Upgrade (Connaught Airport Development Company Ltd)
The objective for this project is to upgrade the RWY 26 RESA and the associated an ancillary works to ensure that the RWY 26 RESA is fully the exiting RESA against clauses from Chapter C โ€“ Runway End Safety Area of the European Union Aviation Safety Agency (EASA) Certification Specifications and Guidance Material for Aerodrome Design (CS-ADR-DSN) Issue 6. View the procurement ยป