The proposed development comprises the construction of The National Maternity Hospital at St. Vincent’s University Hospital campus, Elm Park, Dublin 4. The proposed new National Maternity Hospital building will be located at the eastern side of the hospital campus and comprises the construction of a building that rises to seven (7) storeys above ground level, with one partial basement level, plus additional ancillary plant areas on the roof level, giving an overall height of 42.300m. The gross floor area of the building will be up to 53,676m2 including shared services / facilities for both the new National Maternity Hospital and the existing St. Vincent’s University Hospital Campus. The proposed development will be constructed in a sequential manner that allows for the continual operation of the hospital campus and as such, includes the phased demolition of approximately 8,500m2 of existing buildings at St. Vincent’s University Hospital campus to facilitate clearing the site for the proposed development, the construction of approximately 6,400m2 of temporary accommodation to facilitate construction sequencing (including a Purchasing + Stores Building, a Carpenter’s Workshop, a Waste Marshalling Yard etc.) and the relocation of essential infrastructure and equipment. The works may include the provision for Soft Landings, Facilities Maintenance, and other services in support of Operational Readiness. Some advanced and enabling works have been undertaken and successfully completed to facilitate these proposed works and it is intended that further similar works will be undertaken and completed prior to the commencement of this project on site. As this proposed development is located on a live hospital campus, the applicant must note and be aware that other substantial building works will be undertaken on the campus during the construction period of this development; these building works may vary between small to large scale projects (i.e., of values ranging from €10.0m to in excess of €150m) and be highly serviced facilities and of similar complexity etc. Due to the nature and scale of these potential works, the intended form of construction contract for use on the project is the PW-CF1 – Building Works designed by the Employer, which may, subject to approval from the Government Construction Contracts Committee, incorporate some potential amendments to the standard form of contract, in order to suit and facilitate the construction of this new hospital. All authorised amendments will be clearly set-out and identified within the second stage of the tender process.
Deadline
The time limit for receipt of tenders was 2023-10-27.
The procurement was published on 2023-08-31.
Object Scope of the procurement
Title:
“The National Maternity Hospital at St. Vincent's University Hospital Campus - WORKS CONTRACTOR and PSCS.
2023_NMH@SVUH_Main_Works”
Products/services: Building construction work📦
Short description:
“The proposed development comprises the construction of The National Maternity Hospital at St. Vincent’s University Hospital campus, Elm Park, Dublin 4. The...”
Short description
The proposed development comprises the construction of The National Maternity Hospital at St. Vincent’s University Hospital campus, Elm Park, Dublin 4. The proposed new National Maternity Hospital building will be located at the eastern side of the hospital campus and comprises the construction of a building that rises to seven (7) storeys above ground level, with one partial basement level, plus additional ancillary plant areas on the roof level, giving an overall height of 42.300m. The gross floor area of the building will be up to 53,676m2 including shared services / facilities for both the new National Maternity Hospital and the existing St. Vincent’s University Hospital Campus. The proposed development will be constructed in a sequential manner that allows for the continual operation of the hospital campus and as such, includes the phased demolition of approximately 8,500m2 of existing buildings at St. Vincent’s University Hospital campus to facilitate clearing the site for the proposed development, the construction of approximately 6,400m2 of temporary accommodation to facilitate construction sequencing (including a Purchasing + Stores Building, a Carpenter’s Workshop, a Waste Marshalling Yard etc.) and the relocation of essential infrastructure and equipment. The works may include the provision for Soft Landings, Facilities Maintenance, and other services in support of Operational Readiness. Some advanced and enabling works have been undertaken and successfully completed to facilitate these proposed works and it is intended that further similar works will be undertaken and completed prior to the commencement of this project on site. As this proposed development is located on a live hospital campus, the applicant must note and be aware that other substantial building works will be undertaken on the campus during the construction period of this development; these building works may vary between small to large scale projects (i.e., of values ranging from €10.0m to in excess of €150m) and be highly serviced facilities and of similar complexity etc. Due to the nature and scale of these potential works, the intended form of construction contract for use on the project is the PW-CF1 – Building Works designed by the Employer, which may, subject to approval from the Government Construction Contracts Committee, incorporate some potential amendments to the standard form of contract, in order to suit and facilitate the construction of this new hospital. All authorised amendments will be clearly set-out and identified within the second stage of the tender process.
The proposed development comprises the construction of The National Maternity Hospital at St. Vincent’s University Hospital campus, Elm Park, Dublin 4. The proposed new National Maternity Hospital building will be located at the eastern side of the hospital campus and comprises the construction of a building that rises to seven (7) storeys above ground level, with one partial basement level, plus additional ancillary plant areas on the roof level, giving an overall height of 42.300m. The gross floor area of the building will be up to 53,676m2 including shared services / facilities for both the new National Maternity Hospital and the existing St. Vincent’s University Hospital Campus. The proposed development will be constructed in a sequential manner that allows for the continual operation of the hospital campus and as such, includes the phased demolition of approximately 8,500m2 of existing buildings at St. Vincent’s University Hospital campus to facilitate clearing the site for the proposed development, the construction of approximately 6,400m2 of temporary accommodation to facilitate construction sequencing (including a Purchasing + Stores Building, a Carpenter’s Workshop, a Waste Marshalling Yard etc.) and the relocation of essential infrastructure and equipment. The works may include the provision for Soft Landings, Facilities Maintenance, and other services in support of Operational Readiness. Some advanced and enabling works have been undertaken and successfully completed to facilitate these proposed works and it is intended that further similar works will be undertaken and completed prior to the commencement of this project on site. As this proposed development is located on a live hospital campus, the applicant must note and be aware that other substantial building works will be undertaken on the campus during the construction period of this development; these building works may vary between small to large scale projects (i.e., of values ranging from €10.0m to in excess of €150m) and be highly serviced facilities and of similar complexity etc. Due to the nature and scale of these potential works, the intended form of construction contract for use on the project is the PW-CF1 – Building Works designed by the Employer, which may, subject to approval from the Government Construction Contracts Committee, incorporate some potential amendments to the standard form of contract, in order to suit and facilitate the construction of this new hospital. All authorised amendments will be clearly set-out and identified within the second stage of the tender process.
Show more Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
Scope of the procurement
Estimated total value excluding VAT: EUR 1 💰
Duration of the contract, framework agreement or dynamic purchasing system
The time frame below is expressed in number of months.
Description
Duration: 48
Information about the limits on the number of candidates to be invited
Envisaged number of candidates: 5
Objective criteria for choosing the limited number of candidates:
“Please refer to Suitability Assessment Questionnaire and associated documentation appended to this notice.”
Legal, economic, financial and technical information Conditions for participation
List and brief description of conditions:
“Please refer to Suitability Assessment Questionnaire and associated documentation appended to this notice.” Economic and financial standing
Selection criteria as stated in the procurement documents
Technical and professional ability
Selection criteria as stated in the procurement documents
Conditions related to the contract
Contract performance conditions:
“Please refer to Suitability Assessment Questionnaire and associated documentation appended to this notice.” Information about staff responsible for the performance of the contract
Obligation to indicate the names and professional qualifications of the staff assigned to performing the contract
Procedure Type of procedure
Restricted procedure
Administrative information
Time limit for receipt of tenders or requests to participate: 2023-10-27
15:00 📅
Estimated date of dispatch of invitations to tender or to participate to selected candidates: 2024-02-05 📅
Languages in which tenders or requests to participate may be submitted: English 🗣️
The time frame below is expressed in number of months.
Minimum time frame during which the tenderer must maintain the tender: 6
Complementary information Review body
Name: The High Court,
Postal address: The Four Courts, King's Inns Quay,
Postal town: Dublin 7,
Country: Ireland 🇮🇪 Body responsible for mediation procedures
Name: Hse
Postal address: Sir Patrick Dun's
Postal town: Dublin 2
Postal code: D02 P667
Country: Ireland 🇮🇪
E-mail: frameworks@hse.ie📧 Service from which information about the review procedure may be obtained
Name: Health Service Executive
Postal address: Sir Patrick Dun's
Postal town: Dublin 2
Postal code: D02 P667
Country: Ireland 🇮🇪
E-mail: frameworks@hse.ie📧
Source: OJS 2023/S 170-533933 (2023-08-31)