Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the daa wishes to procure the services of a baggage integrator(s) for three (3) Lots (Dublin T1, Dublin T2 and Cork) to act as design and build contractor for the design, supply, installation, testing and commissioning and handover of a number of baggage handling system (BHS) projects from concept development (through the competitive dialogue process) through to detail design, build and handover.
Deadline
The time limit for receipt of tenders was 2017-07-17.
The procurement was published on 2017-06-16.
Contract notice (2017-06-16) Object Scope of the procurement
Title: Baggage-handling system
Reference number: P3408
Short description:
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the daa wishes to procure the services of a baggage integrator(s) for three (3) Lots (Dublin T1, Dublin T2 and Cork) to act as design and build contractor for the design, supply, installation, testing and commissioning and handover of a number of baggage handling system (BHS) projects from concept development (through the competitive dialogue process) through to detail design, build and handover.
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the daa wishes to procure the services of a baggage integrator(s) for three (3) Lots (Dublin T1, Dublin T2 and Cork) to act as design and build contractor for the design, supply, installation, testing and commissioning and handover of a number of baggage handling system (BHS) projects from concept development (through the competitive dialogue process) through to detail design, build and handover.
Notice metadata
Original language: English ๐ฃ๏ธ
Document type: Contract notice
Nature of contract: Works
Regulation: European Union, with participation of GPA countries
Common procurement vocabulary (CPV)
Code: Baggage-handling system๐ฆ
Additional CPV: Airport equipment๐ฆ Place of performance
NUTS region: รire/Ireland
๐๏ธ
Procedure
Procedure type: Competitive dialogue
Type of bid: Submission for all lots
Award criteria
The most economic tender
Reference Dates
Date dispatched: 2017-06-16 ๐
Submission deadline: 2017-07-17 ๐
Publication date: 2017-06-21 ๐
Identifiers
Notice number: 2017/S 117-235337
Refers to notice: 2017/S 082-159133
OJ-S issue: 117
Additional information
As per the RFI documentation available from www.etenders.gov.ie
Object Scope of the procurement
Estimated total value: 70 000 000 EUR ๐ฐ
Title of the lot: HBS Upgrade / Baggage Integrators Dublin Airport T1
Lot number: 1
Short description:
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the daa wishes to procure the services of a baggage integrator(s) for Terminal 1 in Dublin Airport to act as design and build contractor for the design, supply, installation, testing and commissioning and handover of a number of baggage handling system (BHS) projects from concept development (through the competitive dialogue process) through to detail design, build and handover.
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the daa wishes to procure the services of a baggage integrator(s) for Terminal 1 in Dublin Airport to act as design and build contractor for the design, supply, installation, testing and commissioning and handover of a number of baggage handling system (BHS) projects from concept development (through the competitive dialogue process) through to detail design, build and handover.
Duration: 180 months
Additional information: As per the RFI documentation available from www.etenders.gov.ie
Title of the lot: HBS Upgrade / Baggage Integrators Dublin Airport T2
Lot number: 2
Short description:
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the daa wishes to procure the services of a baggage integrator(s) for Terminal 2 at Dublin Airport to act as design and build contractor for the design, supply, installation, testing and commissioning and handover of a number of baggage handling system (BHS) projects from concept development (through the competitive dialogue process) through to detail design, build and handover.
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the daa wishes to procure the services of a baggage integrator(s) for Terminal 2 at Dublin Airport to act as design and build contractor for the design, supply, installation, testing and commissioning and handover of a number of baggage handling system (BHS) projects from concept development (through the competitive dialogue process) through to detail design, build and handover.
Title of the lot: HBS Upgrade / Baggage Integrators Cork Airport
Lot number: 3
Short description:
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the daa wishes to procure the services of a baggage integrator(s) for Cork Airport to act as design and build contractor for the design, supply, installation, testing and commissioning and handover of a number of baggage handling system (BHS) projects from concept development (through the competitive dialogue process) through to detail design, build and handover.
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the daa wishes to procure the services of a baggage integrator(s) for Cork Airport to act as design and build contractor for the design, supply, installation, testing and commissioning and handover of a number of baggage handling system (BHS) projects from concept development (through the competitive dialogue process) through to detail design, build and handover.
Place of performance
Main site or place of performance:
Dublin Airport.
Cork Airport.
Legal, economic, financial and technical information Conditions for participation
Suitability to pursue the professional activity: As per the RFI documentation available at www.etenders.gov.ie
Economic and financial standing: As per the RFI documentation available at www.etenders.gov.ie
Technical and professional ability: As per the RFI documentation available at www.etenders.gov.ie
List and brief description of rules and criteria: As per the RFI documentation available at www.etenders.gov.ie Contract execution
Deposits and guarantees required: As per the RFI documentation available at www.etenders.gov.ie
Main financing conditions and payment arrangements and/or reference to the relevant provisions governing them: As per the RFI documentation available at www.etenders.gov.ie
Legal form to be taken by the group of economic operators to whom the contract is to be awarded: As per the RFI documentation available at www.etenders.gov.ie
Contract performance conditions: As per the RFI documentation available at www.etenders.gov.ie
Procedure
Number of participants to be contemplated: 8
Justification for the framework agreement:
The Framework Period reflects the long term support and maintenance requirements of the project, having regard to the asset life of the system components involved.
Time of receipt of tenders: 17:00
Languages in which tenders or requests to participate may be submitted: English ๐ฃ๏ธ
Complementary information Review body
Name: Martin Acton
Postal address: Dublin Airport
Postal town: Dublin
Country: Ireland ๐ฎ๐ช
Source: OJS 2017/S 117-235337 (2017-06-16)
Contract award notice (2019-01-08) Object Scope of the procurement
Short description: Daa plc wish to advise that this tender process has been cancelled.
Notice metadata
Document type: Contract award notice
Procedure
Type of bid: Not applicable
Award criteria
Lowest price
Contracting authority Identity
Awarding authority name: Daa plc
Postal address: Dublin Airport
Postal code: Co Dublin
Object Scope of the procurement
Title of the lot: HBS Upgrade/Baggage Integrators Dublin Airport T1
Short description:
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the daa wishes to procure the services of a baggage integrator(s) for Terminal 1 in Dublin Airport to act as design and build Contractor for the:
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the daa wishes to procure the services of a baggage integrator(s) for Terminal 1 in Dublin Airport to act as design and build Contractor for the:
โ design,
โ supply,
โ installation,
โ testing and commissioning and handover of a number of Baggage Handling System (BHS) projects from concept development (through the competitive dialogue process) through to detail design, build and handover.
Title of the lot: HBS Upgrade/Baggage Integrators Dublin Airport T2
Short description:
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the Daa wishes to procure the services of a baggage integrator(s) for Terminal 2 at Dublin Airport to act as design and build contractor for the design, supply, installation, testing and commissioning and handover of a number of Baggage Handling System (BHS) projects from concept development (through the competitive dialogue process) through to detail design, build and handover.
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the Daa wishes to procure the services of a baggage integrator(s) for Terminal 2 at Dublin Airport to act as design and build contractor for the design, supply, installation, testing and commissioning and handover of a number of Baggage Handling System (BHS) projects from concept development (through the competitive dialogue process) through to detail design, build and handover.
Title of the lot: HBS Upgrade/Baggage Integrators Cork Airport
Short description:
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the daa wishes to procure the services of a baggage integrator(s) for Cork Airport to act as design and build contractor for the:
Daa currently has a number of baggage handling system installations at Dublin and Cork Airports. As a result of upcoming regulatory compliance requirements and in response to the increased capacity requirements and need to consider asset life replacements of existing installations, the daa wishes to procure the services of a baggage integrator(s) for Cork Airport to act as design and build contractor for the:
Place of performance
Main site or place of performance: