As part of the Vartry Water Supply Project โ Water Treatment Plant and Reservoir Upgrade Contract, Irish Water on behalf of Ervia plans to undertake the following: โ Construction of a new 80MLD Water Treatment Plant (WTP); โ Upgrade of the Existing Vartry Reservoir Intake including new siphon pipework; โ Increase the capacity of the existing Vartry Reservoir Spillway; The planned works are necessary to ensure compliance with EU Directives, Irish National Standards and Regulations relating to treated water for human consumption. It is intended that the works will be implemented under a Design and Build Contract including a 2 year process proving stage.
Deadline
The time limit for receipt of tenders was 2016-08-24.
The procurement was published on 2016-07-06.
Suppliers
The following suppliers are mentioned in award decisions or other procurement documents:
Contract notice (2016-07-06) Object Scope of the procurement
Title: Drinking-water treatment plant construction work
Reference number: 16/085
Short description:
As part of the Vartry Water Supply Project โ Water Treatment Plant and Reservoir Upgrade Contract, Irish Water on behalf of Ervia plans to undertake the following:
โ Construction of a new 80MLD Water Treatment Plant (WTP);
โ Upgrade of the Existing Vartry Reservoir Intake including new siphon pipework;
โ Increase the capacity of the existing Vartry Reservoir Spillway;
The planned works are necessary to ensure compliance with EU Directives, Irish National Standards and Regulations relating to treated water for human consumption.
It is intended that the works will be implemented under a Design and Build Contract including a 2 year process proving stage.
As part of the Vartry Water Supply Project โ Water Treatment Plant and Reservoir Upgrade Contract, Irish Water on behalf of Ervia plans to undertake the following:
โ Construction of a new 80MLD Water Treatment Plant (WTP);
โ Upgrade of the Existing Vartry Reservoir Intake including new siphon pipework;
โ Increase the capacity of the existing Vartry Reservoir Spillway;
The planned works are necessary to ensure compliance with EU Directives, Irish National Standards and Regulations relating to treated water for human consumption.
It is intended that the works will be implemented under a Design and Build Contract including a 2 year process proving stage.
Documents are available to all candidates who register their interest through etenders. All queries for clarification must be submitted via email to Tenders@ervia.ie The questionnaire must be completed and returned to the address detailed in the attached document not later than 12:00 Wednesday, 24.8.2016.
Documents are available to all candidates who register their interest through etenders. All queries for clarification must be submitted via email to Tenders@ervia.ie The questionnaire must be completed and returned to the address detailed in the attached document not later than 12:00 Wednesday, 24.8.2016.
Object Scope of the procurement
Short description:
As part of the Vartry Water Supply Project โ Water Treatment Plant and Reservoir Upgrade Contract, Irish Water on behalf of Ervia plans to undertake the following:
โ Construction of a new 80MLD Water Treatment Plant (WTP);
โ Upgrade of the Existing Vartry Reservoir Intake including new siphon pipework;
โ Increase the capacity of the existing Vartry Reservoir Spillway;
The planned works are necessary to ensure compliance with EU Directives, Irish National Standards and Regulations relating to treated water for human consumption.
It is intended that the works will be implemented under a Design and Build Contract including a 2 year process proving stage.
Duration: 48 months
Additional information:
Documents are available to all candidates who register their interest through etenders. All queries for clarification must be submitted via email to Tenders@ervia.ie The questionnaire must be completed and returned to the address detailed in the attached document not later than 12:00 Wednesday, 24.8.2016.
Documents are available to all candidates who register their interest through etenders. All queries for clarification must be submitted via email to Tenders@ervia.ie The questionnaire must be completed and returned to the address detailed in the attached document not later than 12:00 Wednesday, 24.8.2016.
Legal, economic, financial and technical information Conditions for participation
Suitability to pursue the professional activity: As per PQQ documents.
List and brief description of rules and criteria: As per PQQ documents.
Contract execution
Deposits and guarantees required: As per contract documents.
Main financing conditions and payment arrangements and/or reference to the relevant provisions governing them: As per contract documents.
Legal form to be taken by the group of economic operators to whom the contract is to be awarded:
Requests to participate may be submitted by single entities or by groups of service providers. A group will not be required to convert into a specific legal form in order to submit a request to participate, but may if Ervia considers it necessary to ensure that the contract is carried out to its satisfaction, be required to do so prior to award of the contract. Ervia also reserves the right to contract with each member of the group on the basis of joint and several liability, or with 1 member of the group as a main contractor with a number of sub-contractors or on any other basis as Ervia considers appropriate.
Legal form to be taken by the group of economic operators to whom the contract is to be awarded
Requests to participate may be submitted by single entities or by groups of service providers. A group will not be required to convert into a specific legal form in order to submit a request to participate, but may if Ervia considers it necessary to ensure that the contract is carried out to its satisfaction, be required to do so prior to award of the contract. Ervia also reserves the right to contract with each member of the group on the basis of joint and several liability, or with 1 member of the group as a main contractor with a number of sub-contractors or on any other basis as Ervia considers appropriate.
Contract performance conditions: As per contract documents.
Procedure
Time of receipt of tenders: 12:00
Languages in which tenders or requests to participate may be submitted: English ๐ฃ๏ธ
Irish ๐ฃ๏ธ
Tender validity period: 6 months
Complementary information Review body
Name: The High Court
Postal address: High Court Central Office, Four Courts, Inns Quay
Postal town: Dublin
Country: Ireland ๐ฎ๐ช
Phone: +35 318886000๐
E-mail: highcourtcentraloffice@courts.ie๐ง
Internet address: http://www.courts.ie๐
Source: OJS 2016/S 131-235520 (2016-07-06)
Additional information (2016-08-18) Object Scope of the procurement
Short description:
As part of the Vartry Water Supply Project โ Water Treatment Plant & Reservoir Upgrade Contract, Irish Water on behalf of Ervia plans to undertake the following:
โ *Construction of a new 80MLD Water Treatment Plant (WTP);
โ *Upgrade of the Existing Vartry Reservoir Intake including new siphon pipework
โ *Increase the capacity of the existing Vartry Reservoir Spillway;
The planned works are necessary to ensure compliance with EU Directives, Irish National Standards and Regulations relating to treated water for human consumption.
It is intended that the works will be implemented under a Design and Build Contract including a 2 year process proving stage.
As part of the Vartry Water Supply Project โ Water Treatment Plant & Reservoir Upgrade Contract, Irish Water on behalf of Ervia plans to undertake the following:
โ *Construction of a new 80MLD Water Treatment Plant (WTP);
โ *Upgrade of the Existing Vartry Reservoir Intake including new siphon pipework
โ *Increase the capacity of the existing Vartry Reservoir Spillway;
The planned works are necessary to ensure compliance with EU Directives, Irish National Standards and Regulations relating to treated water for human consumption.
It is intended that the works will be implemented under a Design and Build Contract including a 2 year process proving stage.
Notice metadata
Document type: Additional information
Reference Dates
Date dispatched: 2016-08-18 ๐
Submission deadline: 2016-08-31 ๐
Publication date: 2016-08-23 ๐
Identifiers
Notice number: 2016/S 161-291195
Refers to notice: 2016/S 131-235520
OJ-S issue: 161
Additional information
16/085 โ Vartry Water Supply Project โ Water Treatment Plant & Reservoir Upgrade Contract โ PQQ Clarification 6
Extension Granted:
The closing date for return of tender submissions must be not later than Not later than 12:00 hours (local time) Wednesday 31.8.2016
Tenders received after the above mentioned time and date will not be considered.
Should you have any queries in regard to the details supplied, please refer immediately to the undersigned in writing by email tenders@ervia.ie
16/085 โ Vartry Water Supply Project โ Water Treatment Plant & Reservoir Upgrade Contract โ PQQ Clarification 6
Extension Granted:
The closing date for return of tender submissions must be not later than Not later than 12:00 hours (local time) Wednesday 31.8.2016
Tenders received after the above mentioned time and date will not be considered.
Should you have any queries in regard to the details supplied, please refer immediately to the undersigned in writing by email tenders@ervia.ie
Object Scope of the procurement
Short description:
As part of the Vartry Water Supply Project โ Water Treatment Plant & Reservoir Upgrade Contract, Irish Water on behalf of Ervia plans to undertake the following:
โ *Construction of a new 80MLD Water Treatment Plant (WTP);
โ *Upgrade of the Existing Vartry Reservoir Intake including new siphon pipework
โ *Increase the capacity of the existing Vartry Reservoir Spillway;
Source: OJS 2016/S 161-291195 (2016-08-18)
Contract award notice (2018-11-05) Object Scope of the procurement
Short description:
As part of the Vartry Water Supply Project โ Water Treatment Plant and Reservoir Upgrade Contract, Irish Water on behalf of Ervia plans to undertake the following:
โ construction of a new 80 MLD Water Treatment Plant (WTP),
โ Upgrade of the Existing Vartry Reservoir Intake including new siphon pipework,
โ increase the capacity of the existing Vartry Reservoir Spillway.
The planned works are necessary to ensure compliance with EU Directives, Irish National Standards and Regulations relating to treated water for human consumption.
It is intended that the works will be implemented under a Design and Build Contract including a 2 year process proving stage.
As part of the Vartry Water Supply Project โ Water Treatment Plant and Reservoir Upgrade Contract, Irish Water on behalf of Ervia plans to undertake the following:
โ construction of a new 80 MLD Water Treatment Plant (WTP),
โ Upgrade of the Existing Vartry Reservoir Intake including new siphon pipework,
โ increase the capacity of the existing Vartry Reservoir Spillway.
The planned works are necessary to ensure compliance with EU Directives, Irish National Standards and Regulations relating to treated water for human consumption.
It is intended that the works will be implemented under a Design and Build Contract including a 2 year process proving stage.
Notice metadata
Document type: Contract award notice
Regulation: European Union, with participation of GPA countries
Procedure
Type of bid: Not applicable
Award criteria
Lowest price
Contracting authority Identity
Postal address: The Shared Services Procurement Manager, Ervia, P
Postal code: Co. Cork
Object Scope of the procurement
Short description:
โ construction of a new 80 MLD Water Treatment Plant (WTP),
โ Upgrade of the Existing Vartry Reservoir Intake including new siphon pipework,
โ increase the capacity of the existing Vartry Reservoir Spillway.
Award of contract
Date of contract conclusion: 2018-07-18 ๐
Name: Veolia Water Ireland Ltd
Postal town: Kilkenny
Country: Ireland ๐ฎ๐ช
Complementary information Review body
Information about review deadlines:
Interested parties are referred to Statutory Instrument 131 of 2010, European Communities (Award of Contracts by Utility Undertaking) (Review Procedures) Regulations 2010 (and in particular Regulation 7 and 10(2).