2021-11-29   Foynes East Jetty Reclamation Project (Shannon Foynes Port Company)
The proposed procurement is for the main works contractor relating to the reclamation behind the berth 5 east jetty in Foynes Port, Co. Limerick Ireland (which will remain operational throughout the works) Further details in the tender documents. View the procurement ยป
Mentioned suppliers: Niaron Ltd
2016-02-24   Ringaskiddy Port Re-development Project (Port of Cork Company)
The proposed works comprise the construction of the marine and civil engineering infrastructure elements for a new container terminal and multi-purpose berth at Ringaskiddy Port, Cork. Key elements may include: โ€” Quay wall structures including marine piling; โ€” Dredging in overburden and rock to a depth of -13,0 m Chart Datum CD); โ€” Reclamation and shore protection; โ€” Quay deck surfacing and quayside crane foundations including piling; โ€” Heavy duty surfacing of existing port lands for use as operational โ€ฆ View the procurement ยป
Mentioned suppliers: BAM Civil Ltd
2015-01-14   Dredging and Disposal of Contaminated Material at Dunmore East Fishery Harbour Centre, Co. Waterford to a design... (Department of Agriculture, Food and the Marine)
The Department of Agriculture, Food and the Marine (DAFM) wish to appoint a suitably experienced Contractor to undertake dredging works at Dunmore East Fishery Harbour Centre (DEFHC), Co. Waterford. The works required are: 1. Dredge DEFHC and approaches to a design dredge depth of -3.6 m CD (-6.06 m OD Malin) in accordance with the Works Requirements and contract drawings; 2. Disposal of the dredged material at a suitable licensed disposal facility(s) taking into account the Site Information provided. View the procurement ยป
Mentioned suppliers: L&M Keating Ltd
2015-01-14   Dredging and Disposal of Contaminated Material at Dunmore East Fishery Harbour Centre, Co. Waterford to a design... (Department of Agriculture, Food and the Marine)
The Department of Agriculture, Food and the Marine (DAFM) wish to appoint a suitably experienced Contractor to undertake dredging works at Dunmore East Fishery Harbour Centre (DEFHC), Co. Waterford. The works required are: 1. Dredge DEFHC and approaches to a design dredge depth of -3.2 m CD (-5.66 m OD Malin) in accordance with the Works Requirements and contract drawings; 2. Disposal of the dredged material at a suitable licensed disposal facility(s) taking into account the Site Information provided. View the procurement ยป
2014-05-26   Maintenance Dredging and Disposal of Contaminated Sediment at Dunmore East Fishery Harbour Centre (DEFHC), Co.... (Department of Agriculture, Food and the Marine)
The maintenance dredging works are to be undertaken at DEFHC and comprise: 1. Dredging to the design dredge depths illustrated on the tender drawings and as per the Works Requirements (Vol A). 2. Disposal of the dredged material at a suitable licensed disposal facility(s) taking into account the information provided in this tender. Chemical analysis has shown that most of the proposed dredge material is contaminated with heavy metals and TBT and cannot be disposed of at sea. The extent of the dredge area โ€ฆ View the procurement ยป