Iarnród Eireann (IÉ) are seeking expressions of interest from suitably qualified applicants to participate in a tender competition for the design and construction of a proposed Offshore Renewable Energy (ORE) Hub at Rosslare Europort. Rosslare Europort is proposing the construction of port facilities which will be capable of facilitating fixed bottom wind farm projects in the Irish and Celtic Seas. Some of the key features of the proposed development are as follows: • Approximately 20 hectares of land reclamation from the sea at the westerly side of the existing Rosslare Europort; • Heavy lift berth (250m-330m in length) for accommodating ORE installation vessels; • Second berth (~240m long) for the delivery of foundation and wind turbine components; • Capital dredging works to the main berth pockets and approach channel; • Small boat harbour for local fishing vessels, Crew Transfer Vessels (CTV’s) and associated quayside facilities.
Deadline
The time limit for receipt of tenders was 2024-06-13.
The procurement was published on 2024-05-12.
Contract notice (2024-05-12) Object Scope of the procurement
Title: 8825 - DESIGN AND CONSTRUCTION OF ROSSLARE EUROPORT OFFSHORE RENEWABLE ENERGY (ORE) HUB
Short description:
“Iarnród Eireann (IÉ) are seeking expressions of interest from suitably qualified applicants to participate in a tender competition for the design and...”
Short description
Iarnród Eireann (IÉ) are seeking expressions of interest from suitably qualified applicants to participate in a tender competition for the design and construction of a proposed Offshore Renewable Energy (ORE) Hub at Rosslare Europort. Rosslare Europort is proposing the construction of port facilities which will be capable of facilitating fixed bottom wind farm projects in the Irish and Celtic Seas. Some of the key features of the proposed development are as follows: • Approximately 20 hectares of land reclamation from the sea at the westerly side of the existing Rosslare Europort; • Heavy lift berth (250m-330m in length) for accommodating ORE installation vessels; • Second berth (~240m long) for the delivery of foundation and wind turbine components; • Capital dredging works to the main berth pockets and approach channel; • Small boat harbour for local fishing vessels, Crew Transfer Vessels (CTV’s) and associated quayside facilities.
Show more
Type of contract: Works
Products/services: Construction work for buildings relating to various means of transport📦 Information about lots
Maximum number of lots that may be awarded to one tenderer: 1
Tenders may be submitted for maximum number of lots: 1
Description
Description of the procurement:
“Iarnród Eireann (IÉ) are seeking expressions of interest from suitably qualified applicants to participate in a tender competition for the design and...”
Description of the procurement
Iarnród Eireann (IÉ) are seeking expressions of interest from suitably qualified applicants to participate in a tender competition for the design and construction of a proposed Offshore Renewable Energy (ORE) Hub at Rosslare Europort. Rosslare Europort is proposing the construction of port facilities which will be capable of facilitating fixed bottom wind farm projects in the Irish and Celtic Seas. Some of the key features of the proposed development are as follows: • Approximately 20 hectares of land reclamation from the sea at the westerly side of the existing Rosslare Europort; • Heavy lift berth (250m-330m in length) for accommodating ORE installation vessels; • Second berth (~240m long) for the delivery of foundation and wind turbine components; • Capital dredging works to the main berth pockets and approach channel; • Small boat harbour for local fishing vessels, Crew Transfer Vessels (CTV’s) and associated quayside facilities.
Procedure Type of procedure
Negotiated procedure with prior call for competition ✅ Administrative information
Time limit for receipt of tenders or requests to participate: 2024-06-13 12:00:00 📅
Languages in which tenders or requests to participate may be submitted: English 🗣️
Legal, economic, financial and technical information Conditions for participation
List and brief description of rules and criteria:
“See PQQ document: See PQQ document”
Deposits and guarantees required:
“See PQQ document for requirements in regards to Minimum Financial Qualification Criteria”
Main financing conditions and payment arrangements and/or reference to the relevant provisions governing them:
“See PQQ document” Conditions related to the contract
Contract performance conditions:
“within ITT documents”
Complementary information Review body
Name: The High Court of Ireland
National registration number: The High Court of Ireland
Postal address: Four Courts, Inns Quay, Dublin 7
Postal code: D07 WDX8
Postal town: Dublin
Country: Ireland 🇮🇪
E-mail: highcourtcentraloffice@courts.ie📧
Phone: +353 1 8886000📞
Source: OJS 2024/S 093-282953 (2024-05-12)
Contract notice (2024-05-24) Procedure Administrative information
Time limit for receipt of tenders or requests to participate: 2024-06-27 12:00:00 📅
Changes Other additional information
“PQQ deadline extended by 2 weeks until June 27th 2024”
Source: OJS 2024/S 101-310455 (2024-05-24)
Contract notice (2024-06-17) Procedure Administrative information
Time limit for receipt of tenders or requests to participate: 2024-07-11 12:00:00 📅
Changes Other additional information
“PQQ Deadline extended until July 11th”