The scheme is to provide a pedestrian and cycle link between Grange Road and Tramore Valley Park and includes:
The 5m wide pedestrian/cycle track is to be constructed on a constrained site through the existing woodland requiring site clearance and tree felling.
The pavement will be constructed on earthworks/vegetated and mechanically stabilised embankments along its length.
The N40 pedestrian/cycle overbridge comprises a 2-span steel structure. The main northern bridge span over the dual carriageway comprises a 46.57m truss and 16m southern span comprises steel beams over the Cork City and Harbour Watermain.
Landscaping, permanent fencing, pavement markings and bespoke signage are required along the track.

Deadline

The time limit for receipt of tenders was 2021-11-16. The procurement was published on 2021-10-05.

Who? What? Where?
Procurement history
Date Document
2021-10-05 Contract notice
2021-11-24 Additional information
Contract notice (2021-10-05)
Object
Scope of the procurement
Title: Cycle path construction work
Reference number: CCC/092/21
Short description:
The scheme is to provide a pedestrian and cycle link between Grange Road and Tramore Valley Park and includes: The 5m wide pedestrian/cycle track is to be constructed on a constrained site through the existing woodland requiring site clearance and tree felling. The pavement will be constructed on earthworks/vegetated and mechanically stabilised embankments along its length. The N40 pedestrian/cycle overbridge comprises a 2-span steel structure. The main northern bridge span over the dual carriageway comprises a 46.57m truss and 16m southern span comprises steel beams over the Cork City and Harbour Watermain. Landscaping, permanent fencing, pavement markings and bespoke signage are required along the track.
Show more
Notice metadata
Original language: English ๐Ÿ—ฃ๏ธ
Document type: Contract notice
Nature of contract: Works
Regulation: European Union, with participation of GPA countries
Common procurement vocabulary (CPV)
Code: Cycle path construction work ๐Ÿ“ฆ
Additional CPV: Soil-stripping work ๐Ÿ“ฆ
Place of performance
NUTS region: Southern ๐Ÿ™๏ธ

Procedure
Procedure type: Open procedure
Type of bid: Submission for all lots
Award criteria
The most economic tender

Contracting authority
Identity
Country: Ireland ๐Ÿ‡ฎ๐Ÿ‡ช
Awarding authority type: Regional or local authority
Awarding authority name: Cork City Council
Postal address: City Hall
Postal code: Co.Cork
Postal town: Cork
Contact
Internet address: http://www.corkcity.ie ๐ŸŒ
E-mail: john_gibson@corkcity.ie ๐Ÿ“ง
Phone: +353 214924159 ๐Ÿ“ž
URL for documents: http://irl.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=198925&B=ETENDERS_SIMPLE ๐ŸŒ
URL for participation: http://irl.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=198925&B=ETENDERS_SIMPLE ๐ŸŒ

Reference
Dates
Date dispatched: 2021-10-05 ๐Ÿ“…
Submission deadline: 2021-11-16 ๐Ÿ“…
Publication date: 2021-10-08 ๐Ÿ“…
Identifiers
Notice number: 2021/S 196-507275
OJ-S issue: 196

Object
Scope of the procurement
Short description:
The scheme is to provide a pedestrian and cycle link between Grange Road and Tramore Valley Park and includes:
The 5m wide pedestrian/cycle track is to be constructed on a constrained site through the existing woodland requiring site clearance and tree felling.
The pavement will be constructed on earthworks/vegetated and mechanically stabilised embankments along its length.
The N40 pedestrian/cycle overbridge comprises a 2-span steel structure. The main northern bridge span over the dual carriageway comprises a 46.57m truss and 16m southern span comprises steel beams over the Cork City and Harbour Watermain.
Landscaping, permanent fencing, pavement markings and bespoke signage are required along the track.
Estimated total value: 6 500 000 EUR ๐Ÿ’ฐ
Short description:
The 5m wide pedestrian/cycle track is to be constructed on a constrained site through the existing woodland requiring site clearance and tree felling. To minimise environmental disruption the works construction must be restricted to the minimum footprint within the lands made available. Existing under/over ground services are to be protected. Existing foul and surface water chambers along the route are to be raised/lowered to suit new surface levels.
Show more
The pedestrian/cycle track pavement comprises a stone carpet on flexible surfacing on subbase. The pavement will be constructed on earthworks/vegetated and mechanically stabilised embankments along its length. Due to steep topography of the site 5no. ambulant disabled pedestrian/bicycle steps are incorporated into the track.
Show more
A 220m long pedestrian/cycle bypass track will be constructed at the southern end of the track on earthworks/vegetated and mechanically stabilised embankments.
Filter drains of various diameter shall be constructed along the track.
2 no. precast reinforced concrete box culverts shall be installed under the track to carry the pedestrian / cycle link over the existing watercourse.
The N40 pedestrian/cycle overbridge comprises a 2-span steel structure. The main northern bridge span over the dual carriageway comprises a 46.57m truss and 16m southern span comprises steel beams over the 1.8m diameter concrete Cork City and Harbour Watermain. The bridges substructure is reinforced concrete construction, founded on reinforced concrete bored cast in place piles. A concrete stairway to Tramore Valley Park is to be constructed at the northern end of the bridge.
Show more
The northern access ramp to N40 Pedestrian/cycle overbridge, 4m wide and approximately 120m long will connect the brideg to Tramore Valley Park.
The Cork City and Harbour w
Estimated value excluding VAT: 6 500 000 EUR ๐Ÿ’ฐ
Duration: 18 months
Place of performance
Main site or place of performance: Cork

Procedure
Legal basis: 32014L0024
Time of receipt of tenders: 16:00
Languages in which tenders or requests to participate may be submitted: English ๐Ÿ—ฃ๏ธ
Tender validity period: 12 months
Tender opening date: 2021-11-16 ๐Ÿ“…
Tender opening time: 16:00

Contracting authority
Identity
National registration number: N/a
Contact
Contact point: John Gibson
Address of the buyer profile: https://irl.eu-supply.com/ctm/Company/CompanyInformation/Index/250 ๐ŸŒ
Documents URL: http://irl.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=198925&B=ETENDERS_SIMPLE ๐ŸŒ

Complementary information
Review body
Name: High Courts
Postal address: Four Courts
Postal town: Dublin
Postal code: D7
Country: Ireland ๐Ÿ‡ฎ๐Ÿ‡ช
Phone: +353 18886000 ๐Ÿ“ž
E-mail: highcourtcentraloffice@courts.ie ๐Ÿ“ง
Body responsible for mediation procedures
Name: High court
Source: OJS 2021/S 196-507275 (2021-10-05)
Additional information (2021-11-24)
Object
Notice metadata
Document type: Additional information
Common procurement vocabulary (CPV)
Code: Earthmoving work ๐Ÿ“ฆ

Reference
Dates
Date dispatched: 2021-11-24 ๐Ÿ“…
Publication date: 2021-11-29 ๐Ÿ“…
Identifiers
Notice number: 2021/S 231-607755
Refers to notice: 2021/S 196-507275
OJ-S issue: 231
Additional information
Deadline for Responses changed to 16:00hrs Monday 29th November 2021