The project is to take place in the grounds of St. Marys GFC at Ardee Co. Louth, located on the south side of Ardee Town just off the main N2. The works will be scheduled on 2 seperate phases. Phase 1 of the project includes the construction of a walking track around the pitch to the rear of the site with the walking pathway commencing at the carpark area. The walking track will be illuminated via existing lighting and additional lighting to match existing that will allow the entire track to be used all year around. Phase 2 of the project includes works to upgrade existing car parking area with tarmacadam surface and all associated surface water drainage systems, lighting and line markings for 92 car parking spaces, which will include seven number of disabled parking spaces. The intended completion date for the Project is proposed for August 2019.
Deadline
The time limit for receipt of tenders was 2018-10-17.
The procurement was published on 2018-09-17.
Suppliers
The following suppliers are mentioned in award decisions or other procurement documents:
Object Scope of the procurement
Title:
โProposed Walking Track and Carpark Surfacing and All Associated Site Works.
St Marys GFC Ardeeโ
Products/services: Construction work๐ฆ
Short description:
โThe project is to take place in the grounds of St. Marys GFC at Ardee Co. Louth, located on the south side of Ardee Town just off the main N2. The works...โ
Short description
The project is to take place in the grounds of St. Marys GFC at Ardee Co. Louth, located on the south side of Ardee Town just off the main N2. The works will be scheduled on 2 seperate phases. Phase 1 of the project includes the construction of a walking track around the pitch to the rear of the site with the walking pathway commencing at the carpark area. The walking track will be illuminated via existing lighting and additional lighting to match existing that will allow the entire track to be used all year around. Phase 2 of the project includes works to upgrade existing car parking area with tarmacadam surface and all associated surface water drainage systems, lighting and line markings for 92 car parking spaces, which will include seven number of disabled parking spaces. The intended completion date for the Project is proposed for August 2019.
Show more
Estimated value excluding VAT: EUR 300 000 ๐ฐ
The project is to take place in the grounds of St. Marys GFC at Ardee Co. Louth, located on the south side of Ardee Town just off the main N2. The works will be scheduled on 2 seperate phases. Phase 1 of the project includes the construction of a walking track around the pitch to the rear of the site with the walking pathway commencing at the carpark area. The walking track will be illuminated via existing lighting and additional lighting to match existing that will allow the entire track to be used all year around. Phase 2 of the project includes works to upgrade existing car parking area with tarmacadam surface and all associated surface water drainage systems, lighting and line markings for 92 car parking spaces, which will include seven number of disabled parking spaces. Access will be provided throughout the construction process for the everyday activities of the club to be carried out unimpeded. A work area will be cordoned off to allow the contractor to park work vehicles adjacent to the work area. The final details of this lies at the discretion of St. Marys GFC commitee and the contractor will have to pay due consideration toward having to safely and carefully traverse from the road to the work site adjacent to the clubhouse and playing fields. The intended completion date for the Project is proposed for August 2019. The contractor will be obligated to provide a draft programme of works with Tender submission for review. In submitting a Bona Fide Tender, the contractor takes responsibility to complete the project within the time frame as submitted unless otherwise agreed with the Client. The tendering contractor must provide evidence of public and employee insurance and provide evidence of their experience in carrying out such projects.
Show more Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
Scope of the procurement
Estimated total value excluding VAT: EUR 300 000 ๐ฐ
Duration of the contract, framework agreement or dynamic purchasing system
The time frame below is expressed in number of months.
Description
Duration: 2
Information about electronic catalogues
Tenders must be presented in the form of electronic catalogues or include an electronic catalogue
Scope of the procurement
Information about European Union funds: Rural Development Programme 2014-2020
Description
Additional information: LEADER Grant
Legal, economic, financial and technical information Conditions for participation
List and brief description of conditions: Member of CIF
Economic and financial standing
Selection criteria as stated in the procurement documents
Technical and professional ability
Selection criteria as stated in the procurement documents
Information about staff responsible for the performance of the contract
Obligation to indicate the names and professional qualifications of the staff assigned to performing the contract
Procedure Type of procedure
Open procedure
Administrative information
Time limit for receipt of tenders or requests to participate: 2018-10-17
12:00 ๐
Languages in which tenders or requests to participate may be submitted: English ๐ฃ๏ธ
Tender must be valid until: 2018-10-19 ๐
Conditions for opening of tenders: 2018-10-17
12:00 ๐
Complementary information Review body
Name: St Marys GFC Ardee
Postal address: ST. Marys GFC Club
Postal town: Ardee
Postal code: Co Louth
Country: Ireland ๐ฎ๐ช
Source: OJS 2018/S 180-407309 (2018-09-17)
Contract award notice (2019-05-17) Contracting authority Name and addresses
Postal address: C/O St Marys GFC, Drogheda Road, Louth
Object Scope of the procurement
Title:
โProposed Walking Track and Carpark Surfacing and all Associated Site Works
St Marys GFC Ardeeโ
Short description:
โThe project is to take place in the grounds of St. Marys GFC at Ardee Co. Louth, located on the south side of Ardee Town just off the main N2. The works...โ
Short description
The project is to take place in the grounds of St. Marys GFC at Ardee Co. Louth, located on the south side of Ardee Town just off the main N2. The works include the construction of a walking track around the pitch to the rear of the site with the walking pathway commencing at the carpark area. The walking track will be illuminated via existing lighting and additional lighting to match existing that will allow the entire track to be used all year around.
Show more
Total value of the procurement (excluding VAT): EUR 220 000 ๐ฐ
Description
Main site or place of performance: St Marys GFC Ardee Co Louth.
Description of the procurement:
โThe project is to take place in the grounds of St. Marys GFC at Ardee Co. Louth, located on the south side of Ardee Town just off the main N2. The works...โ
Description of the procurement
The project is to take place in the grounds of St. Marys GFC at Ardee Co. Louth, located on the south side of Ardee Town just off the main N2. The works include the construction of a walking track around the pitch to the rear of the site with the walking pathway commencing at the carpark area. The walking track will be illuminated via existing lighting and additional lighting to match existing that will allow the entire track to be used all year around.
Show more Award criteria
Price
Description
Additional information: Leader Grant.
Procedure Administrative information
Previous publication concerning this procedure: 2018/S 180-407309
Award of contract
1๏ธโฃ
Contract Number: 1
Title: Proposed Walking Track and all Associated Site Works
Date of conclusion of the contract: 2019-05-16 ๐
Information about tenders
Number of tenders received: 4
Number of tenders received by electronic means: 4
Name and address of the contractor
Name: Envirogreen
National registration number: 6378337B
Postal address: St. Peregrine, Flemington, Balrath
Postal town: Navan
Postal code: Co Meath
Country: Ireland ๐ฎ๐ช
Phone: +353 419825434๐
E-mail: tomoconnor@envirogreen.ie๐ง
Fax: +353 419825434 ๐
Region: รire/Ireland๐๏ธ
URL: http://www.envirogreen.ie๐
The contractor is an SME โ Information on value of the contract/lot (excluding VAT)
Estimated total value of the contract/lot: EUR 400 000 ๐ฐ
Total value of the contract/lot: EUR 220 000 ๐ฐ
Complementary information Review body
Postal address: ST. Marys GFC Club, Co. Louth
Source: OJS 2019/S 097-233563 (2019-05-17)