Ballough Above Ground Installation (AGI) is a key piece of infrastructure on the Republic of Ireland transmission gas network. Numerous key pipelines converge on Ballough AGI. The AGI is located west of Lusk in North Co. Dublin adjacent to the M1 motorway.
The scope of this construction contract is to create a bypass around Ballough AGI.
As part of the contract the following new works will be required:
โ a new AGI, north of Ballough AGI adjacent to the existing 900 mm Gormanston to Ballough pipeline. The new AGI will contain above and below ground pipework, valves, pig trap facilities and associated civils and electrical/instrumentation works,
โ a new 700 m long, 750 mm bypass pipeline from the new AGI to the existing 750 mm Pipeline to the West.
As per the PQQ Document.
Deadline
The time limit for receipt of tenders was 2018-11-05.
The procurement was published on 2018-10-05.
Suppliers
The following suppliers are mentioned in award decisions or other procurement documents:
Object Scope of the procurement
Title: Ballough Bypass
18/160
Products/services: Construction work for gas pipelines๐ฆ
Short description:
โBallough Above Ground Installation (AGI) is a key piece of infrastructure on the Republic of Ireland transmission gas network. Numerous key pipelines...โ
Short description
Ballough Above Ground Installation (AGI) is a key piece of infrastructure on the Republic of Ireland transmission gas network. Numerous key pipelines converge on Ballough AGI. The AGI is located west of Lusk in North Co. Dublin adjacent to the M1 motorway.
The scope of this construction contract is to create a bypass around Ballough AGI.
As part of the contract the following new works will be required:
โ a new AGI, north of Ballough AGI adjacent to the existing 900 mm Gormanston to Ballough pipeline. The new AGI will contain above and below ground pipework, valves, pig trap facilities and associated civils and electrical/instrumentation works,
โ a new 700 m long, 750 mm bypass pipeline from the new AGI to the existing 750 mm Pipeline to the West.
As per the PQQ Document.
1๏ธโฃ
Additional products/services: General construction work for pipelines๐ฆ
Additional products/services: Pipelaying construction work๐ฆ
Additional products/services: Gas supply mains construction work๐ฆ
Place of performance: รire/Ireland๐๏ธ
Main site or place of performance: Lusk, Co Dublin.
Description of the procurement:
โBallough Above Ground Installation (AGI) is a key piece of infrastructure on the Republic of Ireland transmission gas network. Numerous key pipelines...โ
Description of the procurement
Ballough Above Ground Installation (AGI) is a key piece of infrastructure on the Republic of Ireland transmission gas network. Numerous key pipelines converge on Ballough AGI. The AGI is located west of Lusk in North Co. Dublin adjacent to the M1 motorway.
The scope of this construction contract is to create a bypass around Ballough AGI.
As part of the contract the following new works will be required:
โ a new AGI, north of Ballough AGI adjacent to the existing 900 mm Gormanston to Ballough pipeline. The new AGI will contain above and below ground pipework, valves, pig trap facilities and associated civils and electrical/instrumentation works,
โ a new 700 m long, 750 mm bypass pipeline from the new AGI to the existing 750 mm Pipeline to the West. A trenchless crossing (approx. 150 m long) of the M1 motorway is required. The new pipeline will be a welded steel pipeline and will have a wall-thickness of 19,1 mm. The design pressure of the new pipeline is 85 bar,
โ 2 No. new 900 mm pipeline connections (approx. 100 m each) from the new AGI to the existing 900 mm Gormanston to Ballough pipeline,
โ 3 No. stopple locations requiring 9 No. split tees to be welded onto existing 750 mm and 900 mm diameter pipelines and under-pressure drilling of the pipeline at each split tee plus line stoppling / local bypass piping at the stopple locations,
โ modifications to the pipework arrangement at Ballough AGI including associated civil works,
โ testing and commissioning of all pipeline and AGI works,
โ discharge of the duties of PSCS / Contractor in accordance with applicable H&S legislation,
โ additional elements relating to the above scope of works.
Show more Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
Duration of the contract, framework agreement or dynamic purchasing system
The time frame below is expressed in number of months.
Description
Duration: 18
Information about the limits on the number of candidates to be invited
Envisaged number of candidates: 5
Description
Additional information:
โYou must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and...โ
Additional information
You must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and time specified in the PQQ documents. Please note that all tenders are electronic, as such no paper copies will be accepted or read. Please submit via the etenders system not later than 12:00 hrs local time Monday 5.11.2018.
Legal, economic, financial and technical information Conditions for participation
List and brief description of conditions:
โPlease refer to tender documents available to download from www.etenders.gov.ie only.โ Economic and financial standing
Selection criteria as stated in the procurement documents
Technical and professional ability
Selection criteria as stated in the procurement documents
Conditions for participation
Legal form to be taken by the group of economic operators to whom the contract is to be awarded:
โRequests to participate may be submitted by single entities or by groups of service providers. A group will not be required to convert into a specific legal...โ
Legal form to be taken by the group of economic operators to whom the contract is to be awarded
Requests to participate may be submitted by single entities or by groups of service providers. A group will not be required to convert into a specific legal form in order to submit a request to participate, but may if the Contracting Entity considers it necessary to ensure that the contract is carried out to its satisfaction, be required to do so prior to award of the contract. The Contracting Entity also reserves the right to contract with each member of the group on the basis of joint and several liability, or with one member of the group as a main contractor with a number of sub-contractors or on any other basis as the Contracting Entity considers appropriate.
Procedure Type of procedure
Negotiated procedure with prior call for competition
Administrative information
Time limit for receipt of tenders or requests to participate: 2018-11-05
12:00 ๐
Languages in which tenders or requests to participate may be submitted: English ๐ฃ๏ธ
Languages in which tenders or requests to participate may be submitted: Irish ๐ฃ๏ธ
The time frame below is expressed in number of months.
Minimum time frame during which the tenderer must maintain the tender: 6
Complementary information Information about electronic workflows
Electronic ordering will be used
Electronic invoicing will be accepted
Electronic payment will be used
Additional information
โDocuments are available to all candidates who register their interest through e-tenders. All queries for clarification must be submitted via etenders...โ
Documents are available to all candidates who register their interest through e-tenders. All queries for clarification must be submitted via etenders messaging facility. The questionnaire must be completed and returned to the address detailed in the attached document not later than 12:00 hrs (local time) Monday 5.11.2018
Show more Review body
Name: The High Court
Postal address: High Court Central Office, Four Courts, Inns Quay,
Postal town: Dublin
Country: Ireland ๐ฎ๐ช
Phone: +35 318886000๐
E-mail: highcourtcentraloffice@courts.ie๐ง
URL: http://www.courts.ie๐ Review procedure
Precise information on deadline(s) for review procedures:
โPrecise information on deadline(s) for review procedures:
Please refer to Statutory Instrument 131 of 2010, European Communities (Award of Contracts by...โ
Precise information on deadline(s) for review procedures
Precise information on deadline(s) for review procedures:
Please refer to Statutory Instrument 131 of 2010, European Communities (Award of Contracts by Utility Undertaking) (Review Procedures) Regulations 2010 (and in particular Regulation 7 and 10(2)).
Show more
Source: OJS 2018/S 194-440028 (2018-10-05)
Contract award notice (2020-07-31) Contracting authority Name and addresses
Contact person: Tender Admin
Object Scope of the procurement
Short description:
โBallough Above Ground Installation (AGI) is a key piece of infrastructure on the Republic of Ireland transmission gas network. Numerous key pipelines...โ
Short description
Ballough Above Ground Installation (AGI) is a key piece of infrastructure on the Republic of Ireland transmission gas network. Numerous key pipelines converge on Ballough AGI. The AGI is located west of Lusk in North Co. Dublin adjacent to the M1 motorway.
The scope of this construction contract is to create a bypass around Ballough AGI.
As part of the contract the following new works will be required:
โข a new AGI, north of Ballough AGI adjacent to the existing 900 mm Gormanston to Ballough pipeline. The new AGI will contain above and below ground pipework, valves, pig trap facilities and associated civils and electrical/instrumentation works.
โข a new 700 m long, 750 mm bypass pipeline from the new AGI to the existing 750 mm pipeline to the West.
As per the PQQ document.
Show more Description
Main site or place of performance: Lusk, Co. Dublin.
Description of the procurement:
โBallough Above Ground Installation (AGI) is a key piece of infrastructure on the Republic of Ireland transmission gas network. Numerous key pipelines...โ
Description of the procurement
Ballough Above Ground Installation (AGI) is a key piece of infrastructure on the Republic of Ireland transmission gas network. Numerous key pipelines converge on Ballough AGI. The AGI is located west of Lusk in North Co. Dublin adjacent to the M1 motorway.
The scope of this construction contract is to create a bypass around Ballough AGI.
As part of the contract the following new works will be required:
โข a new AGI, north of Ballough AGI adjacent to the existing 900 mm Gormanston to Ballough pipeline. The new AGI will contain above and below ground pipework, valves, pig trap facilities and associated civils and electrical/instrumentation works.
โข a new 700 m long, 750 mm bypass pipeline from the new AGI to the existing 750 mm pipeline to the West. A trenchless crossing (approx. 150 m long) of the M1 motorway is required. The new pipeline will be a welded steel pipeline and will have a wall-thickness of 19.1mm. The design pressure of the new pipeline is 85 bar.
โข 2 No new 900 mm pipeline connections (approx. 100 m each) from the new AGI to the existing 900 mm Gormanston to Ballough pipeline.
โข 3 No stopple locations requiring 9 No split tees to be welded onto existing 750 mm and 900 mm diameter pipelines and under-pressure drilling of the pipeline at each split tee plus line stoppling/local bypass piping at the stopple locations.
โข modifications to the pipework arrangement at Ballough AGI including associated civil works.
โข testing and commissioning of all pipeline and AGI works.
โข discharge of the duties of PSCS / Contractor in accordance with applicable H&S legislation.
โข additional elements relating to the above scope of works.
Show more
Additional information:
โYou must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and...โ
Additional information
You must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and time specified in the PQQ documents. Please note that all tenders are electronic, as such no paper copies
Will be accepted or read. Please submit via the eTenders system not later than 12.00 local time
Monday 5 November 2018.
Procedure Administrative information
Previous publication concerning this procedure: 2018/S 194-440028
Award of contract
1๏ธโฃ
Contract Number: 1
Title: Ballough Bypass
Date of conclusion of the contract: 2020-05-29 ๐
Information about tenders
Number of tenders received: 2
Name and address of the contractor
Name: Murphy International Ltd
Postal town: Kildare
Country: Ireland ๐ฎ๐ช
Region: รire/Ireland๐๏ธ
The contractor is an SME โ
Complementary information Additional information
โDocuments are available to all candidates who register their interest through e-tenders. All queries for clarification must be submitted via etenders...โ
Documents are available to all candidates who register their interest through e-tenders. All queries for clarification must be submitted via etenders messaging facility. The questionnaire must be completed and returned to the address detailed in the attached document not later than 12:00hrs (local time) Monday 5 November 2018.
Show more Review body
Postal address: High Court Central Office, Four Courts, Inns Quay
Review procedure
Precise information on deadline(s) for review procedures:
โPlease refer to Statutory Instrument 131 of 2010, European Communities (Award of Contracts by Utility Undertaking) (Review Procedures) Regulations 2010 (and...โ
Precise information on deadline(s) for review procedures
Please refer to Statutory Instrument 131 of 2010, European Communities (Award of Contracts by Utility Undertaking) (Review Procedures) Regulations 2010 (and in particular Regulation 7 and 10(2)).
Show more
Source: OJS 2020/S 150-368769 (2020-07-31)