Single supplier Framework Agreement for the completion of maintenance works on the existing network infrastructure, the design and construction of new customer connections and network extensions as required. The successful Applicants responsibilities will include but not be limited to: โ maintenance and emergency maintenance works, โ standby and emergency cover, โ telecommunications network design work and associated ancillaries, โ telecommunications duct network construction to include open trench, mole plough and directional drill, โ traffic management, โ duct and sub-duct supply, โ supply of prefabricated chambers plus frames and covers, โ sub duct installation, โ duct testing and commissioning, โ cable installation, โ re-instatement, โ provision of as-built information, โ provision of resources, โ attainment of required permits and consents. The successful Applicant will be required to complete the roles of Project Supervisor Design Phase (PSDP) and Project Supervisor Construction Stage (PSCS).
Deadline
The time limit for receipt of tenders was 2019-01-28.
The procurement was published on 2018-12-17.
Suppliers
The following suppliers are mentioned in award decisions or other procurement documents:
Contract notice (2018-12-17) Object Scope of the procurement
Title: Construction work for communication lines
Reference number: 18/166
Short description:
Single supplier Framework Agreement for the completion of maintenance works on the existing network infrastructure, the design and construction of new customer connections and network extensions as required. The successful Applicants responsibilities will include but not be limited to:
โ maintenance and emergency maintenance works,
โ standby and emergency cover,
โ telecommunications network design work and associated ancillaries,
โ telecommunications duct network construction to include open trench, mole plough and directional drill,
โ traffic management,
โ duct and sub-duct supply,
โ supply of prefabricated chambers plus frames and covers,
โ sub duct installation,
โ duct testing and commissioning,
โ cable installation,
โ re-instatement,
โ provision of as-built information,
โ provision of resources,
โ attainment of required permits and consents.
The successful Applicant will be required to complete the roles of Project Supervisor Design Phase (PSDP) and Project Supervisor Construction Stage (PSCS).
Single supplier Framework Agreement for the completion of maintenance works on the existing network infrastructure, the design and construction of new customer connections and network extensions as required. The successful Applicants responsibilities will include but not be limited to:
โ maintenance and emergency maintenance works,
โ standby and emergency cover,
โ telecommunications network design work and associated ancillaries,
โ telecommunications duct network construction to include open trench, mole plough and directional drill,
โ traffic management,
โ duct and sub-duct supply,
โ supply of prefabricated chambers plus frames and covers,
โ sub duct installation,
โ duct testing and commissioning,
โ cable installation,
โ re-instatement,
โ provision of as-built information,
โ provision of resources,
โ attainment of required permits and consents.
The successful Applicant will be required to complete the roles of Project Supervisor Design Phase (PSDP) and Project Supervisor Construction Stage (PSCS).
You must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and time specified in the PQQ documents. Please note that all tenders are electronic, as such no paper copies will be accepted or read. Please submit via the etenders system not later than 12:00 local time Wednesday 16.1.2019.
You must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and time specified in the PQQ documents. Please note that all tenders are electronic, as such no paper copies will be accepted or read. Please submit via the etenders system not later than 12:00 local time Wednesday 16.1.2019.
Object Scope of the procurement
Short description:
Single supplier Framework Agreement for the completion of maintenance works on the existing network infrastructure, the design and construction of new customer connections and network extensions as required. The successful Applicants responsibilities will include but not be limited to:
Single supplier Framework Agreement for the completion of maintenance works on the existing network infrastructure, the design and construction of new customer connections and network extensions as required. The successful Applicants responsibilities will include but not be limited to:
โ maintenance and emergency maintenance works,
โ standby and emergency cover,
โ telecommunications network design work and associated ancillaries,
โ telecommunications duct network construction to include open trench, mole plough and directional drill,
โ traffic management,
โ duct and sub-duct supply,
โ supply of prefabricated chambers plus frames and covers,
โ sub duct installation,
โ duct testing and commissioning,
โ cable installation,
โ re-instatement,
โ provision of as-built information,
โ provision of resources,
โ attainment of required permits and consents.
The successful Applicant will be required to complete the roles of Project Supervisor Design Phase (PSDP) and Project Supervisor Construction Stage (PSCS).
Duration: 84 months
Additional information:
You must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and time specified in the PQQ documents. Please note that all tenders are electronic, as such no paper copies will be accepted or read. Please submit via the etenders system not later than 12:00 local time Wednesday 16.1.2019.
You must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and time specified in the PQQ documents. Please note that all tenders are electronic, as such no paper copies will be accepted or read. Please submit via the etenders system not later than 12:00 local time Wednesday 16.1.2019.
Place of performance
Main site or place of performance: Nationwide
Legal, economic, financial and technical information Conditions for participation
Suitability to pursue the professional activity:
Please refer to tender documents available to download from www.etenders.gov.ie only.
Contract execution
Legal form to be taken by the group of economic operators to whom the contract is to be awarded:
Requests to participate may be submitted by single entities or by groups of service providers. A group will not be required to convert into a specific legal form in order to submit a request to participate, but may if the Contracting Entity considers it necessary to ensure that the contract is carried out to its satisfaction, be required to do so prior to award of the contract. The Contracting Entity also reserves the right to contract with each member of the group on the basis of joint and several liability, or with one member of the group as a main contractor with a number of sub-contractors or on any other basis as the Contracting Entity considers appropriate.
Legal form to be taken by the group of economic operators to whom the contract is to be awarded
Requests to participate may be submitted by single entities or by groups of service providers. A group will not be required to convert into a specific legal form in order to submit a request to participate, but may if the Contracting Entity considers it necessary to ensure that the contract is carried out to its satisfaction, be required to do so prior to award of the contract. The Contracting Entity also reserves the right to contract with each member of the group on the basis of joint and several liability, or with one member of the group as a main contractor with a number of sub-contractors or on any other basis as the Contracting Entity considers appropriate.
Procedure
Legal basis: 32014L0025
Envisaged number of candidates: 5
Objective criteria for choosing the limited number of candidates:
A maximum of five (5) applicants will be invited to tender. If there is more than one applicant ranked at fifth place, all the fifth placed applicants will be invited to tender.
Time of receipt of tenders: 12:00
Languages in which tenders or requests to participate may be submitted: English ๐ฃ๏ธ
Irish ๐ฃ๏ธ
Tender validity period: 6 months
Complementary information Review body
Name: The High Court
Postal address: High Court Central Office
Postal town: Four Courts, Inns Quay
Postal code: 7
Country: Ireland ๐ฎ๐ช
Phone: +35 318886000๐
E-mail: highcourtcentraloffice@courts.ie๐ง
Internet address: http://www.courts.ie๐
Information about review deadlines:
Precise information on deadline(s) for review procedures:
Please refer to Statutory Instrument 131 of 2010, European Communities (Award of Contracts by Utility Undertaking) (Review Procedures) Regulations 2010 (and in particular Regulation 7 and 10(2)).
Source: OJS 2018/S 245-562070 (2018-12-17)
Contract award notice (2020-01-09) Object Scope of the procurement
Short description:
Single supplier framework agreement for the completion of maintenance works on the existing network infrastructure, the design and construction of new customer connections and network extensions as required. The successful applicants responsibilities will include but not be limited to:
โ maintenance and emergency maintenance works,
โ standby and emergency cover,
โ telecommunications network design work and associated ancillaries,
โ telecommunications duct network construction to include open trench, mole plough and directional drill,
โ traffic management,
โ duct and sub-duct supply,
โ supply of prefabricated chambers plus frames and covers,
โ sub-duct installation,
โ duct testing and commissioning,
โ cable installation,
โ re-instatement,
โ provision of as-built information,
โ provision of resources,
โ attainment of required permits and consents.
The successful applicant will be required to complete the roles of Project Supervisor Design Phase (PSDP) and Project Supervisor Construction Stage (PSCS).
Single supplier framework agreement for the completion of maintenance works on the existing network infrastructure, the design and construction of new customer connections and network extensions as required. The successful applicants responsibilities will include but not be limited to:
โ maintenance and emergency maintenance works,
โ standby and emergency cover,
โ telecommunications network design work and associated ancillaries,
โ telecommunications duct network construction to include open trench, mole plough and directional drill,
โ traffic management,
โ duct and sub-duct supply,
โ supply of prefabricated chambers plus frames and covers,
โ sub-duct installation,
โ duct testing and commissioning,
โ cable installation,
โ re-instatement,
โ provision of as-built information,
โ provision of resources,
โ attainment of required permits and consents.
The successful applicant will be required to complete the roles of Project Supervisor Design Phase (PSDP) and Project Supervisor Construction Stage (PSCS).
Notice metadata
Document type: Contract award notice
Procedure
Type of bid: Not applicable
Award criteria
Lowest price
Reference Dates
Date dispatched: 2020-01-09 ๐
Publication date: 2020-01-14 ๐
Identifiers
Notice number: 2020/S 009-018056
Refers to notice: 2018/S 245-562070
OJ-S issue: 9
Additional information
You must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and time specified in the PQQ documents. Please note that all tenders are electronic, as such NO paper copies will be accepted or read. Please submit via the eTenders system not later than 12:00 local time 16.1.2019.
You must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and time specified in the PQQ documents. Please note that all tenders are electronic, as such NO paper copies will be accepted or read. Please submit via the eTenders system not later than 12:00 local time 16.1.2019.
Object Scope of the procurement
Short description:
Single supplier framework agreement for the completion of maintenance works on the existing network infrastructure, the design and construction of new customer connections and network extensions as required. The successful applicants responsibilities will include but not be limited to:
Single supplier framework agreement for the completion of maintenance works on the existing network infrastructure, the design and construction of new customer connections and network extensions as required. The successful applicants responsibilities will include but not be limited to:
โ sub-duct installation,
The successful applicant will be required to complete the roles of Project Supervisor Design Phase (PSDP) and Project Supervisor Construction Stage (PSCS).
Additional information:
You must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and time specified in the PQQ documents. Please note that all tenders are electronic, as such NO paper copies will be accepted or read. Please submit via the eTenders system not later than 12:00 local time 16.1.2019.
You must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and time specified in the PQQ documents. Please note that all tenders are electronic, as such NO paper copies will be accepted or read. Please submit via the eTenders system not later than 12:00 local time 16.1.2019.
Place of performance
Main site or place of performance: Countrywide.
Award of contract
Date of contract conclusion: 2019-11-01 ๐
Name: KN Network Services (Ire) Ltd
Postal town: Clondalkin
Country: Ireland ๐ฎ๐ช Information about tenders
Number of tenders received: 3
Reference Additional information
You must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and time specified in the PQQ documents. Please note that all tenders are electronic, as such no paper copies will be accepted or read. Please submit via the eTenders system not later than 12.00 local time 16.1.2019.
You must submit through the etenders system before the deadline. The submission deadline is strict and no submissions will be possible after the date and time specified in the PQQ documents. Please note that all tenders are electronic, as such no paper copies will be accepted or read. Please submit via the eTenders system not later than 12.00 local time 16.1.2019.