It is proposed that the Multi-Contractor Framework Agreement scope of works will include but will not be limited to (non-exhaustive list): โ Remove timber related safety hazards which may present a danger to members of the public or to ESB staff; โ Prevent physical damage to Overhead Network. It comprises planned timber cutting and associated works under the following headings: โ 38kV: 3 year cycle; โ 10/20kV: Rural Network, 3 year cycle; โ Low Voltage: Rural Network, 6 year cycle; โ 10/20kV: Urban Network, 4 year cycle; โ Low Voltage: Urban Network, 4 year cycle. It also includes unplanned/response driven timber cutting and associated works for: โ New Works-timber clearance and associated works; โ Hazards on existing Network (not on the current programme cycle); โ Forestry-line related; โ MV Live Line-timber clearance + associated works; โ Emergency response e.g. storm; โ Transmission-timber clearance + associated works; โ Project related works.
Deadline
The time limit for receipt of tenders was 2016-09-09.
The procurement was published on 2016-08-06.
Suppliers
The following suppliers are mentioned in award decisions or other procurement documents:
Contract notice (2016-08-06) Object Scope of the procurement
Title: Scrub-removal work
Reference number: D20/CON/822
Short description:
It is proposed that the Multi-Contractor Framework Agreement scope of works will include but will not be limited to (non-exhaustive list):
โ Remove timber related safety hazards which may present a danger to members of the public or to ESB staff;
โ Prevent physical damage to Overhead Network.
It comprises planned timber cutting and associated works under the following headings:
โ 38kV: 3 year cycle;
โ 10/20kV: Rural Network, 3 year cycle;
โ Low Voltage: Rural Network, 6 year cycle;
โ 10/20kV: Urban Network, 4 year cycle;
โ Low Voltage: Urban Network, 4 year cycle.
It also includes unplanned/response driven timber cutting and associated works for:
โ New Works-timber clearance and associated works;
โ Hazards on existing Network (not on the current programme cycle);
โ Forestry-line related;
โ MV Live Line-timber clearance + associated works;
โ Emergency response e.g. storm;
โ Transmission-timber clearance + associated works;
โ Project related works.
Notice metadata
Original language: English ๐ฃ๏ธ
Document type: Contract notice
Nature of contract: Works
Regulation: European Union, with participation of GPA countries
Common procurement vocabulary (CPV)
Code: Scrub-removal work๐ฆ
Additional CPV: Tree-clearing services๐ฆ Place of performance
NUTS region: รire/Ireland๐๏ธ
Procedure
Procedure type: Negotiated procedure
Type of bid: Submission for all lots
Award criteria
The most economic tender
Please note the following information in relation to Notice sections above:
โIV.1.3) โ Number of Participants to the Framework Agreement 45โ.
The number of 45 stated in section IV.I.3) is an estimate only of the final number of contractors that may be required. The final number of contractors appointed to the framework agreement will depend on the contractor resource capacity of those ultimately determined by the Contracting Entity to have submitted the most economically advantageous tenders in accordance with the award criteria for this enquiry/in the procurement documents. The final number of contractors admitted to the framework agreement will be that number determined by the Contracting Entity to be sufficient to meet the framework agreement requirements and may be more or less than 45. More information will be set out in the Invitation to Tender, at that stage of the Procurement process.
โII.2.9) โ Information About the Limits on the Number of Candidates to be Invited โ 55โ.
The Contracting Entity reserves the right to increase or decrease this number subject to the number of applications/candidates that successfully pre-qualify.
โIII.2.3) โ Information About Staff Responsible for the Performance of the Contract โ Obligation to indicate the names and professional qualifications of the staff assigned to performing the contractโ.
As stated in the PQQ available to download from www.etenders.gov.ie using RFT ID 107893. Applicants/candidates that successfully pre-qualify and are subsequently Invited to Tender will be required to provide detailed information in their tender response in relation to their employees/staff including, but not limited to, the names and the qualifications of the employees/staff they propose to assign to works that may arise under the framework agreement. More information will be set out in the Invitation to Tender, at that stage of the Procurement process.
Please also note:
โ Note 1 โ Incomplete Pre-Qualification Questionnaires (PQQ) and/or Missing Information/ Documentation:
Subject to applicable law the Contracting Entity is not obliged to engage in a clarification process in respect of questionnaires that are not complete or are missing information/documentation and these questionnaires may be rejected by the Contracting Entity. Therefore Applicants/candidates are advised to ensure that they return Fully Completed questionnaires in order to avoid the risk of elimination from the Procurement process on the basis of an incomplete questionnaire.
โ Note 2 โ Information About the PQQ:
To receive more information about the PQQ, including any amendments and/or clarifications and to request any clarifications and/or to respond to the PQQ, you must register your interest for this process on the eTenders website at RFT ID 107893.
Please note the following information in relation to Notice sections above:
โIV.1.3) โ Number of Participants to the Framework Agreement 45โ.
The number of 45 stated in section IV.I.3) is an estimate only of the final number of contractors that may be required. The final number of contractors appointed to the framework agreement will depend on the contractor resource capacity of those ultimately determined by the Contracting Entity to have submitted the most economically advantageous tenders in accordance with the award criteria for this enquiry/in the procurement documents. The final number of contractors admitted to the framework agreement will be that number determined by the Contracting Entity to be sufficient to meet the framework agreement requirements and may be more or less than 45. More information will be set out in the Invitation to Tender, at that stage of the Procurement process.
โII.2.9) โ Information About the Limits on the Number of Candidates to be Invited โ 55โ.
The Contracting Entity reserves the right to increase or decrease this number subject to the number of applications/candidates that successfully pre-qualify.
โIII.2.3) โ Information About Staff Responsible for the Performance of the Contract โ Obligation to indicate the names and professional qualifications of the staff assigned to performing the contractโ.
As stated in the PQQ available to download from www.etenders.gov.ie using RFT ID 107893. Applicants/candidates that successfully pre-qualify and are subsequently Invited to Tender will be required to provide detailed information in their tender response in relation to their employees/staff including, but not limited to, the names and the qualifications of the employees/staff they propose to assign to works that may arise under the framework agreement. More information will be set out in the Invitation to Tender, at that stage of the Procurement process.
Subject to applicable law the Contracting Entity is not obliged to engage in a clarification process in respect of questionnaires that are not complete or are missing information/documentation and these questionnaires may be rejected by the Contracting Entity. Therefore Applicants/candidates are advised to ensure that they return Fully Completed questionnaires in order to avoid the risk of elimination from the Procurement process on the basis of an incomplete questionnaire.
โ Note 2 โ Information About the PQQ:
To receive more information about the PQQ, including any amendments and/or clarifications and to request any clarifications and/or to respond to the PQQ, you must register your interest for this process on the eTenders website at RFT ID 107893.
Object Scope of the procurement
Short description:
It is proposed that the Multi-Contractor Framework Agreement scope of works will include but will not be limited to (non-exhaustive list):
โ Remove timber related safety hazards which may present a danger to members of the public or to ESB staff;
โ Prevent physical damage to Overhead Network.
It comprises planned timber cutting and associated works under the following headings:
โ 38kV: 3 year cycle;
โ 10/20kV: Rural Network, 3 year cycle;
โ Low Voltage: Rural Network, 6 year cycle;
โ 10/20kV: Urban Network, 4 year cycle;
โ Low Voltage: Urban Network, 4 year cycle.
It also includes unplanned/response driven timber cutting and associated works for:
โ New Works-timber clearance and associated works;
โ Hazards on existing Network (not on the current programme cycle);
โ Forestry-line related;
โ MV Live Line-timber clearance + associated works;
Multi-contractor Framework Agreement for Timber Cutting and Associated Works at or near Overhead Lines in the Republic of Ireland. The duration of the framework agreement is 3 years with an option to extend, at the contracting Entity's discretion, for a further 1+1+1 years.
Multi-contractor Framework Agreement for Timber Cutting and Associated Works at or near Overhead Lines in the Republic of Ireland. The duration of the framework agreement is 3 years with an option to extend, at the contracting Entity's discretion, for a further 1+1+1 years.
Duration: 72 months
Description of renewals:
Note that the duration in months stated above represents the maximum duration of the framework agreement in the event that the Contracting Entity exercises its option to extend the framework agreement beyond its initial 3 years, for a further 1+1+1 years.
Note that the duration in months stated above represents the maximum duration of the framework agreement in the event that the Contracting Entity exercises its option to extend the framework agreement beyond its initial 3 years, for a further 1+1+1 years.
Description of options:
Option to extend the framework agreement at the Contracting Entity's discretion for a period of 1+1+1 years.
Place of performance
Main site or place of performance: Throughout the Republic of Ireland.
Legal, economic, financial and technical information Conditions for participation
Suitability to pursue the professional activity:
As stated in the PQQ available to download from www.etenders.gov.ie using RFT ID 107893.
Economic and financial standing:
As stated in the PQQ available to download from www.etenders.gov.ie using RFT ID 107893.
Minimum level(s) of standards:
As stated in the PQQ available to download from www.etenders.gov.ie using RFT ID 107893.
Technical and professional ability:
As stated in the PQQ available to download from www.etenders.gov.ie using RFT ID 107893.
List and brief description of rules and criteria:
As stated in the PQQ available to download from www.etenders.gov.ie using RFT ID 107893.
Contract execution
Deposits and guarantees required:
As stated in the PQQ available to download from www.etenders.gov.ie using RFT ID 107893 and will be confirmed in the Invitation to Tender.
Main financing conditions and payment arrangements and/or reference to the relevant provisions governing them:
As stated in the PQQ available to download from www.etenders.gov.ie using RFT ID 107893. This will also be confirmed in the Invitation to Tender.
Legal form to be taken by the group of economic operators to whom the contract is to be awarded:
While economic operators are not obliged to take a particular legal form for the purposes of submitting a tender the Contracting Entity reserves the right to require the successful tenderers to contract on such basis as the Contracting Entity may determine. See also as stated in the PQQ available to download from www.etenders.gov.ie using RFT ID 107893.
Legal form to be taken by the group of economic operators to whom the contract is to be awarded
While economic operators are not obliged to take a particular legal form for the purposes of submitting a tender the Contracting Entity reserves the right to require the successful tenderers to contract on such basis as the Contracting Entity may determine. See also as stated in the PQQ available to download from www.etenders.gov.ie using RFT ID 107893.
Contract performance conditions:
The Contracting Entity is preparing a draft Multi-Contractor Framework Agreement and schedules that will be provided to the Pre-Qualified Applicants at the next stage of the Procurement process i.e. the Invitation to Tender stage. The Multi-Contractor Framework Agreement will set out the terms and conditions pertaining to the technical, commercial, financial, safety and legal requirements for the timber cutting works to be covered by the Multi-Contractor Framework Agreement. The works will be procured utilising bespoke terms and conditions based on the FIDIC conditions of contract for plant and design โ build for electrical and mechanical plant, and for building and engineering works, designed by the contractor (incorporating FIDIC 1
The Contracting Entity is preparing a draft Multi-Contractor Framework Agreement and schedules that will be provided to the Pre-Qualified Applicants at the next stage of the Procurement process i.e. the Invitation to Tender stage. The Multi-Contractor Framework Agreement will set out the terms and conditions pertaining to the technical, commercial, financial, safety and legal requirements for the timber cutting works to be covered by the Multi-Contractor Framework Agreement. The works will be procured utilising bespoke terms and conditions based on the FIDIC conditions of contract for plant and design โ build for electrical and mechanical plant, and for building and engineering works, designed by the contractor (incorporating FIDIC 1
Procedure
Envisaged number of candidates: 55
Objective criteria for choosing the limited number of candidates:
As stated in the PQQ available to download from: www.etenders.gov.ie using RFT ID 107893. The envisaged number to be invited to tender is estimated to be 55 approximately. This number may be increased or decreased depending on the degree of interest and whether or not the applications meet the objective selection criteria set by the Contracting Entity in the Pre-qualification Questionnaire (PQQ).
Objective criteria for choosing the limited number of candidates
As stated in the PQQ available to download from: www.etenders.gov.ie using RFT ID 107893. The envisaged number to be invited to tender is estimated to be 55 approximately. This number may be increased or decreased depending on the degree of interest and whether or not the applications meet the objective selection criteria set by the Contracting Entity in the Pre-qualification Questionnaire (PQQ).
Number of participants to be contemplated: 45
Time of receipt of tenders: 12:00
Languages in which tenders or requests to participate may be submitted: English ๐ฃ๏ธ
Tender validity period: 12 months
Please note the following information in relation to Notice sections above:
โIV.1.3) โ Number of Participants to the Framework Agreement 45โ.
The number of 45 stated in section IV.I.3) is an estimate only of the final number of contractors that may be required. The final number of contractors appointed to the framework agreement will depend on the contractor resource capacity of those ultimately determined by the Contracting Entity to have submitted the most economically advantageous tenders in accordance with the award criteria for this enquiry/in the procurement documents. The final number of contractors admitted to the framework agreement will be that number determined by the Contracting Entity to be sufficient to meet the framework agreement requirements and may be more or less than 45. More information will be set out in the Invitation to Tender, at that stage of the Procurement process.
The number of 45 stated in section IV.I.3) is an estimate only of the final number of contractors that may be required. The final number of contractors appointed to the framework agreement will depend on the contractor resource capacity of those ultimately determined by the Contracting Entity to have submitted the most economically advantageous tenders in accordance with the award criteria for this enquiry/in the procurement documents. The final number of contractors admitted to the framework agreement will be that number determined by the Contracting Entity to be sufficient to meet the framework agreement requirements and may be more or less than 45. More information will be set out in the Invitation to Tender, at that stage of the Procurement process.
โII.2.9) โ Information About the Limits on the Number of Candidates to be Invited โ 55โ.
The Contracting Entity reserves the right to increase or decrease this number subject to the number of applications/candidates that successfully pre-qualify.
โIII.2.3) โ Information About Staff Responsible for the Performance of the Contract โ Obligation to indicate the names and professional qualifications of the staff assigned to performing the contractโ.
As stated in the PQQ available to download from www.etenders.gov.ie using RFT ID 107893. Applicants/candidates that successfully pre-qualify and are subsequently Invited to Tender will be required to provide detailed information in their tender response in relation to their employees/staff including, but not limited to, the names and the qualifications of the employees/staff they propose to assign to works that may arise under the framework agreement. More information will be set out in the Invitation to Tender, at that stage of the Procurement process.
As stated in the PQQ available to download from www.etenders.gov.ie using RFT ID 107893. Applicants/candidates that successfully pre-qualify and are subsequently Invited to Tender will be required to provide detailed information in their tender response in relation to their employees/staff including, but not limited to, the names and the qualifications of the employees/staff they propose to assign to works that may arise under the framework agreement. More information will be set out in the Invitation to Tender, at that stage of the Procurement process.
Subject to applicable law the Contracting Entity is not obliged to engage in a clarification process in respect of questionnaires that are not complete or are missing information/documentation and these questionnaires may be rejected by the Contracting Entity. Therefore Applicants/candidates are advised to ensure that they return Fully Completed questionnaires in order to avoid the risk of elimination from the Procurement process on the basis of an incomplete questionnaire.
Subject to applicable law the Contracting Entity is not obliged to engage in a clarification process in respect of questionnaires that are not complete or are missing information/documentation and these questionnaires may be rejected by the Contracting Entity. Therefore Applicants/candidates are advised to ensure that they return Fully Completed questionnaires in order to avoid the risk of elimination from the Procurement process on the basis of an incomplete questionnaire.
โ Note 2 โ Information About the PQQ:
To receive more information about the PQQ, including any amendments and/or clarifications and to request any clarifications and/or to respond to the PQQ, you must register your interest for this process on the eTenders website at RFT ID 107893.
Complementary information Review body
Name: Chief Registrar
Postal address: Four Courts, Inns Quay
Postal town: Dublin
Postal code: 7
Country: Ireland ๐ฎ๐ช
Phone: +353 18886000๐
Internet address: http://www.courts.ie๐ Body responsible for mediation procedures
Name: N/a
Postal town: N/a
Service from which information about the review procedure may be obtained
Name: Your Legal Advisor
Postal town: Your Legal Advisor
Source: OJS 2016/S 153-277293 (2016-08-06)
Contract award notice (2017-08-11) Object Scope of the procurement
Short description:
Multi-Contractor Framework Agreement for Timber Cutting and Associated Works at or near Overhead Lines in the Republic of Ireland.
Notice metadata
Document type: Contract award notice
Procedure
Type of bid: Not applicable
Contracting authority Identity
Postal address: Saint Margaret's Road
Postal town: Finglas
Contact
E-mail: joanne.newman@esb.ie๐ง
Object Place of performance
Main site or place of performance: Republic of Ireland.
Award of contract
Date of contract conclusion: 2017-06-26 ๐
Name: 36 contractors awarded โ details available on request from email address below
Postal address: Various
Postal town: Various
Country: Ireland ๐ฎ๐ช
E-mail: networkscontractorprocurement@esb.ie๐ง Information about tenders
Number of tenders received: 44
Contracting authority Contact
Internet address: www.esb.ie๐
Complementary information Review body
Name: The High Court (only after review with ESB Networks Procurement)
Postal address: Chief Registrar, Four Courts, Inns Quay
Source: OJS 2017/S 155-322558 (2017-08-11)