Expansion of St Luke's Radiation Oncology Centre at Beaumont Hospital

Health Service Executive (HSE)

The project is located at St Luke's Radiation Oncology Centre (Beaumont) and consists of:
โ€” An horizontal expansion, of approximately 4 500sq m Nett Floor Area (NFA) over three (3Nr.) floors to an existing facility;
โ€” To provide for departmental adjacencies including Bunkers for six (6Nr.) Linear Accelerators and support accommodation;
โ€” Provision of on-grade car-parking. The Design shall allow for structural capability of a five (5Nr.) storey structure, to allow for future expansion.

Deadline
The time limit for receipt of tenders was 2016-09-19. The procurement was published on 2016-08-29.

Who?

What?

Where?

Procurement history
Date Document
2016-08-29 Contract notice