N59 Rossow Bends
Improvement of the existing N59 National Secondary Route comprising the construction of a Type 3 single carriageway road (6,0 m carriageway road with 0,5 m hard strips and verges of approximately 2,0 m to 3,0 m) for a distance of approximately 2 km, with approximately 650 m of the scheme being constructed off-line.
Construction of a cycleway 2,5 m wide alongside the improved N59 in sections.
Improvement of existing side road junctions.
Construction of two new river bridges and widening one existing river bridge.
Construction of culvert crossings and associated earthworks.
Various landscaping, environmental and mitigation works.
Various accommodation works including access to properties and lands.
Various fencing and safety barrier systems.
Various roadmarking and signing.
Various works including diversion of assets of utilities and service providers.
Various road drainage works including the provision of drainage outfalls.
New pavement construction and some pavement overlay.
Other ancillary works.
Deadline
The time limit for receipt of tenders was 2015-04-10.
The procurement was published on 2015-02-27.
Suppliers
The following suppliers are mentioned in award decisions or other procurement documents:
Who?
What?
Procurement history
Date |
Document |
2015-02-27
|
Contract notice
|
2015-07-02
|
Contract award notice
|